Loading...
Miscellaneous - 8th Change Order ~ i t J f 1 ~ j^ '>, ... ~, I ! ; \,' ,/ ./1. ; '\ I d' i II ii" , ". (", '. , ! .... ~\ 18 August 2005 Mr. Alan French, Project Manager Monroe County Construction Management Monroe County, Florida RE: Freeman Justice Center I Request for Change Order No.8 Dear Mr. French; I have just received a letter and documentation from Mr. Greg Galmin of Tower Group the Contractor on the project for a change order request No.8. In this letter Mr. Galmin presents a chronology of communication on the issue of adequate concrete coverage in the slabs at intersections of conduit and reinforcement. ] have spoken to you on the phone reference this matter and wish to reiterate my position. Our specifications call for certain clearances and concrete coverage minimums to be maintained by the contractor in the installation of the various trades in the slab. It is incumbent on the contractor to coordinate with all his trades and to determine their method by which they can accommodate the installation. When the matter was initially brought up it was presented in a manner that suggested that the entire installation of the slab could not achieve the prescribed clearances. After several days' discussion and meeting in the field it was determined that only in the areas where significant conduit crossed was there even an issue. The resulting minor adjustment (which is typically dealt with in the industry without fanfare) was simply to pour an additional Yz" of concrete at those locations by dropping the slab form bottom at the pre-cast joists. We gave the directive that this was acceptable. In discussion in the field with the lead member of the electrical subcontractor, he voiced that this was not a significant issue and should have been dealt with by the Contractor, without comment. In discussion with our structural engineer (Pistorino & Alam), again it was reiterated as inconsequential and should have been dealt with by the Contractor without comment. By way of Mr. Galmin's letter he indicates that their work results in a Change Order Request for 12 panels that need to be adjusted. You are specifically aware that on that same visit discussed above I indicated that over 20 panels where unacceptable for finish requirements on the slab pour and needed to be replaced. During the course of the field meeting referenced above, the Contractor asked me how did I propose to lower the slabs. I replied that the method was up to him. It could be different hangars on the pre-cast joists or some form supports of his own choosing. These comments where made in the spirit of cooperation. However, I remind you, per my contract - "The Architect shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures ... in connection with the work, since these are the Contractor's responsibility under the Contracts for Construction." This brings me to my conclusion. The Contractor has submitted a change order for the above work to include time delays for performance of this work with a total of $57,737.:50. This amount and the corresponding time delay are in my opinion irresponsible and a careless disregard for the Owner (i.e. The taxpayers of Monroe County). If you review the data provided, they indicate a time expense of over 400 man hours or ten man weeks to reinstall 12 panels. This alone is preposterous at best. Additionally it should be noted that it is the contractor's responsibility to coordinate his trades prior to installation. If this problem as implied, was as significant as represented, it should have been identified at the beginning of his project planning with his trades, as is the norm and certainly during the preparation of shop drawings for slab installation. This whole issue suggests a possibly unseemly motive. I am unwilling to be an accornplil:e to this action. I therefore make the following recommendations. My comment.~ below are simply suggested options the County may exercise. It should be made clear that in no way will I recommend Monroe County, my client, authorize this change order; and I and my consultants will not approve of such a request. Option I. Instruct the contractor to proceed with the work and exercise his options under the dispute section of his contract. Option 2. Stop all work pending resolution of the issue. Option 3. Advise the Bonding Company of the Contractor's issue and request intervention by said Company. It is with much regret that requests such as this are marring the progress of the County's flagship project. Gonzalez Architects is committed to our decade long effort to see the Freeman Justice Center completed as a proud building for the community. Should you have any questions please feel free to call. Sincerely, Gonzalez Architects . Gonzalez, AlA, NCARB