MEMORANDUM
Office of the County Administrator
TO: Board of County Commissioners
FROM: Debbie Frederick
Deputy County Administrator
DATE: March 2,2010
SUBJECT: County Divisions' Monthly Activity Report for February, 2010
MONTHL Y ACTIVITY REPORT - FEBRUARY, 2010
KEY WEST AIRPORT
. In February, passenger figures for January were compiled, During that month, the six
airlines serving Key West International Airport carried a total of 51,704 passengers,
This is an astonishing 20,1 % increase over January of2009,
. Working with the navy, the airport has been heavily involved with the planning of the
Blue Angels air show scheduled for next month, Since EYW and NAS Boca Chica
have concentric airspaces, coordinating Airline traffic with the schedule of the
demonstration teams has been a challenge,
. We have received our draft permit from the Army Corps of Engineers for the long
awaited construction of the Runway Safety Areas (RSA), Once the final permit
arrives, we can start work on this essential safety improvement.
MARATHON AIRPORT
. The Airport Emergency Plan (AEP) Triennial Full-Scale Exercise post event
critique/debriefing meeting was held on February 22, 2010, Exercise evaluators'
and participants' comments are being reviewed and considered for inclusion into
the AEP, AEP to be revised accordingly and submitted to FAA for review and
approval,
. Class Act Cleaning Services, the contract janitorial company at the airport, had no
staff working after 6:00 a,m, on February 12, 2010, Notice was provided to the
contractor by Certified Mail of possible contract breach/default. Request to hire
Eight B Cleaners, Inc, on a month to month temporary basis was approved by
Deputy County Administrator. An item is being placed on the agenda for the
March 17, 2010, BOCC Meeting requesting to terminate Class Act Cleaning
Services, to advertise an RFP for janitorial services, and to continue to use Eight
B Cleaners on a month to month basis in the interim,
. Proj ect Pre-Application is being prepared for submittal to the FAA for Taxiway
Pavement Marking Upgrade design and installation and Terminal Sewer Laterals
design,
1
. Several construction and operations related projects continue to be in various
stages of completion at the airport including:
. Renewal agreements for several concession and property leases are being
prepared for presentation to the BOCC.
. Airport Utility Master Plan is being updated, Proj ect funding is through an FAA
Grant.
. HMGP Wind Retrofit (Hurricane Shutter) Project: Phase II - This project has
been completed and the contractor's final payment application has been
processed, Project funding is through a sub-grant agreement with the Florida
Division of Emergency Management.
. Passenger Terminal HV AC system replacement project is substantially complete
and pending completion of punch-list items, training of airport personnel on
maintenance and operations procedures, and final inspection,
. The Environmental Assessment Project associated with the runway extension and
runway relocation proposals is on-going, A Modification to Standards regarding
the Runway Object Free Area (ROFA) has been prepared and submitted to the
FAA; awaiting reply, Project funding is through an FAA Grant.
. Airport Rescue Fire Fighting (ARFF), Index A, vehicle is currently being
manufactured; funding for this project is through an FDOT Joint Participation
Agreement (JP A),
EMPLOYEE SERVICES
I. Web site Updates (other than normal position vacancy updates, etc,):
Benefits:
KPHA Provider Directory Updates
EAP monthly bulletin
Working Wellness Newsletter
Human Resources:
Updated 1 job description
II. Turnover Numbers To Date:
Feb 2010 Turnover: ,39% Turnover as oflast Feb 2009: 1.81% Turnover
2010: 1.36%
I Resignations: 0 I Terminations: 2 I Retired: 0 I Deceased: 0 I Layoffs:O
III. Major ActivitiesIMeetings:
Human Resources
· Met with KPMG on budget allocations for General Fund Budget.
· Division Director participated in Conference Call as Membership Director for
FRMA
· Completed Annual Chamber of Commerce Survey
· IAFF Negotiation Meeting
Risk
. Reconciling insurances policies with property schedule to ensure
appropriate coverage
Benefits (GrouplW orkers Comp)
· Addendum to RFP for Employee Assistance Program posted
2
· KPHA meeting
· Courtesy meeting with Fitness Trainer on Wellness
· Two meeting with Team members: Health Benefits Volunteer Review &
Recommendations
· Health Plan Document revisions completed for March BOCC approval.
Safety
· Attended SARB meeting
· Started the respiratory fit testing program
Fit tested 25 FF on N-95's and SCBA's
BUDGET & FINANCE
Budget Analysts:
. Budget Analysts attended three day GovMax 5,0 training workshop
. Contracts Reviewed - 26
. Prepared Resolutions - 28
. Posted budget transfers and resolutions - 56
. True-up and prepared resolutions for the revenue collections of Special Revenue
Fund 158,
. Balance and true-up FY09 revenue and expenditures for Airport grant roll overs
and prepared amended resolutions to balance Finance system budget.
. Balance and true-up FY09 revenue and expenditures for all Social Services grant
rollover and prepared amended resolutions to balance Finance system budget.
. Process payables for the Monroe County Sheriff and Care Center's Byrne Grant.
. Worked on Cost Allocation Project and assisted KPMG in site field work
. Prepared agenda items for the February BOCC meeting
. Processed P AF s
. Budget Transfers (Expenditure and Project transfers)
. Reports - Reviews a Balance Sheet by Fund Daily to verify all funds are
balanced,
. Reports - Monthly Expenditure Status Report and Expenditure Audit Trail Report
is printed and forwarded to Lower Keys AARP, Big Pine AARP and Middle Keys
AARP with an attached Memo outlining the available balance remaining for this
fiscal year.
. Assist in preparing the Agenda Packet
. Resolution budget transfers monthly (Expenditure, Revenue and Project
transfers)
. Prep/approve bills for Finance/ Accts Payable
. Prepares the Monthly Bank of America Purchasing Card bill for Finance
(gathering signature approvals, travel exp reports, purchase receipts and
completed daily purchase card reports from each card holder that has made a
purchase in that month),
. Reviewed Budget & Finance Contracts
. Prepared postage billing for Finance
. Timesheets
. Reviewed Travel Expense Reports, then forwarded to Finance,
. Card Changes for Bank of America/Administration duties
3
. Communications with Purchasing and the County Atty's office on publishing the
Notice - Calling for Bids for Duck Key Security,
. Prepared Suncom billings for Finance
Grants Administration Department:
. Completion and submission of Energy Efficiency and Conservation Block Grant
application to FEEC in Tallahassee, The total grant amount will be approximately
$2,6 million, The County's request is $1 million plus $150,000 in administrative
costs, (There were a total of 160 competing applications filed with FEEC; 70 in
the Category in which Monroe County applied,)
. HSAB: Facilitated first meeting on Feb 16th, and finalized schedule for FY 2011
funding cycle, Prepared and distributed Funding Application, instructions and
attachments to all non-profits; placed advertisement of funding availability,
. Completed the County's 2010 Federal Appropriations Requests new legislative
session (to Ros-Lehtinen, Nelson and Diaz-Balart) for EOC, Transportation and
Wastewater; submitted to federal lobbyists,
. Testified at administrative law hearing in Tallahassee at DCA re: rule changes in
the Stan Mayfield Working Waterfront Grant program,
. Completed monthly expenditure reports on Byrne JAG grants (four of which are
Recovery Act funds), Reviewed, approved, processed invoices for all Byrne JAG
and RSA T grants,
. Management of various issues related 2010 HSO/HSAB contracts, including
continued required document certification for all contracted organizations;
questions/clarifications on invoices,
. FEMA: Hurricane Wilma: Continued closeout work for Wilma PW s, Working on
closeout of six large Project Worksheets from Wilma,
. FEMA: Prepared and submitted appeal of Trap Debris Project Worksheet for
Fay,
Purchasing Department:
Totals for the month of February 2010 are as follows:
. Total purchase orders processed 308
. Total orders placed for departments 82
. Total orders entered for departments 73
. Office Depot orders processed 65
. Staples Orders processed 1
. We opened 2 bids and processed another 2 which was below average from the
previous months, Addendums entered 3, contracts reviewed 21, and bills paid 4,
and voided 6 purchase orders, We also processed 703 pieces of mail which was
average from previous months,
COMMUNITY SUPPORT SERVICES
Social Services Department (SSD)
In-Home And Nutrition Services (IHNS)
OAA, Older Americans Act Programs:
Nutrition (Information in this section is for the period 1/21/1 0 -2/20/1 0)
4
. C-l Congregate Meals totaled 1267 units during the first full period of the
contract year, exceeding the goal of 1223 units/month, The Congregate Meal
program is off to a great start in 2010 with well attended meal sites,
. C-2 Home-Delivered Meals totaled 2972 units during the first full period of the
contract year, exceeding the goal of 2856 units, The Home Delivered Meal Program
received an unusually large number of referrals during January and February, which
we were able to accommodate,
In-Home Services (Information in this section is for the period 01/01/1 0 - 1/20/1 0 - new grant
year)
. III-B Screening and Assessment: 10 units this period, 8,7% year-to-date achieved,
.37% overachieved, 36 clients on the waiting list
. III-B Homemaking: 48 units this period, 3% year-to-date achieved, 5,33%
underachieved, 47 clients on the waiting list
. III-B Personal Care: 64.25 units this period, 6% year-to-date achieved, 2.33%
underachieved, 18 clients on the waiting list
We have spent $4640,92,4.24% ofIII-B funds, which is 4,09 % underachieved due to a short
first billing period,
. III-E In-Home Respite: 121 units this period, 12,8% year-to-date-achieved, 4.47%
overachieved,
. III-E Facility Respite: 362.25 units this period, 13% year-to-date achieved, 4,67%
overachieved,
We have spent $7352,68, 13% ofIII-E funds, which is 4,67% overachieved, Case Managers
will temporarily suspend bringing clients into the III-E program,
Non-OAA Programs:
CCDA (Community Care for Disabled Adults) for January 2010:
. Case Management: 3,5 units for the month were produced; 81.5 units year-to-
date,
. Homemaking: 86.25 units for the month were produced; 960,75 units year-to
date,
. Home-Delivered Meals: Monthly units were 160 meals; 1405 meals year-to-date,
. Personal Care: Monthly units were 0; 25 units year-to-date,
Overall Program Achievement was 41.73%, 16,60% underachieved,
CCE (Community Care for the Elderly) for the period 12/21/09 - 1/20/10:
. Case Management: 60.25 units for the period and 415 units year-to-date, 39,9%
achieved year-to-date, There are 101 clients on the waiting list
. Intake: 9.25 units achieved and 56 units year-to-date, 110% achieved year-to-
date,
. Chore: 32 units achieved and 32 units year-to-date, 100% achieved year-to-date,
5
. Homemaking: 710 units for the period and 4557,7 units year-to-date, 49%
achieved year-to-date, There are 88 clients on the waiting list.
. Personal Care: 501 units for the period and 3226 units year-to-date, 58,8%
achieved year-to-date, There are 46 clients on the waiting list.
. Respite: 200,5 units for the period and 980 units year-to-date, 54,5% achieved
year to date, There are 14 clients on the waiting list.
CCE overall is at 52% achievement, 6,34% underachieved, We have taken on 7 new
clients whose units will be reported next month,
ADI (Alzheimer's Disease Initiative) for the period 12/21/09 - 1/20/10: 316,75 units
were produced in the period and 1242.25 units year to date, 52,61% year-to-date
achieved, 2.29 % overachieved, Weare steadily lowering the overachievement.
HCE (Home Care for the Elderly Program) for the period 1/16/10 - 2/15/10: 22,75
billable units this period, 134 billable units year-to-date, Current spending level year to
date is at 59,82%, 6,85% underachieved, We have taken on 2 new HCE clients and those
units will be fully reported in March,
Monroe County Transit (MCT)
Department Activity for February 2010
. One-way trips provided: 1,805
Unduplicated clients served: 215
Special Needs Clients registered: 398
. Awarded the 5310 FDOT Grant for the funding of a new Paratransit bus and the
5316 FDOT Grant for funding the Mobile Data Terminals/software for the
Trapeze Dispatching and Reservation System, The awards and agreements will be
brought to the board in the fall BOCC meetings,
. Deposited Revenue: $2,216,00
Expenditures: $32,645,05
Percentage Spent Fiscal YTD: 4.2%
Social Services Department - February 2010
Community Support Services
Offices in: Key West, Marathon, Plantation Key
Incoming calls, provision of information and referrals
Unduplicated Welfare client households that received service
New Welfare cases receiving service
Low Income Home Energy Assistance Grant Program cases- 14
Low Income Crisis Assistance cases - 14
Home and field visits 51
Office visits 250
EHEAPS 4
Homelessness Prevention Approved Cases 52
Weather Assistance 2
Total Expenditures:
Interesting Community Support Services Updates:
1,221
116
29
$3,400,00
$3,070.41
$1,204,36
$35,246,00
$549.49
$43,470.26
. 2 staff members attended continued training in Tampa, Florida for the W AP
program,
6
. 2 staff members who attended an extensive training on the (W AP) Weatherization
Program are now qualified and certified inspectors to represent Monroe County
Social Services,
. One staff member reached the 5 year mark for MC employment, and will receive
a 5 year pin and $100,
Bayshore Manor (BSM)
Bayshore Manor's current census is 16 residents, The current census is four
private pay and twelve subsidized, BSM provided 570.25 hours of OA3E respite
care this month, Bayshore Manor has ten OA3E clients,
. There is one client on the wait list.
. Revenue for February 2010
. Expenditures for the same period
. Percentage of the budget spent year to date
$32,452,68
$42,581.85
38.45 %
LIBRARY
. The use and appreciation of Library services keeps growing steadily as circulation
in January totaled 39,046 items, nearly 3,000 over the December figure, as the
winter residents and visitors are now here in full force
. 372 new Library cards were issued in January, 21% above the December
additions
. 45,968 customers used Library services onsite during the month, 10% over the
Library visitors in December
. 10,320 public access computer and wi-fi sessions were provided to our customers
during the month
. Use of the Library's premium information databases has steadily and sharply
increased, In January, 2010, 18,130 searches were performed on the databases,
54% higher than January, 2009, This increase is attributed to promotion on the
County Intranet page and easy search "widgets" placed directly on the Library
web site,
. Views on the Library's Flickr site of historical images broke 300,000 this month!
Since Fall 2007, Library staff and volunteers have been scanning, describing and
sharing the Library's collection of historical photos on this popular website,
Promotion of the photos on a Facebook page entitled "I remember Key West
when"," resulted in 2,500 hits within 24 hours, This truly illustrates the power of
using appropriate social networking sites to highlight our special collections and
servIces,
. A record high of2,378 requests were placed via the Library's "HIP", The Horizon
Information Portal enables customers to log into their Library account to renew
books and request titles for hold or delivery to their local Library,
. Our spending of the FY10 budget is proceeding on its projected pace; prioritizing
in areas of discretionary funds has become part of our spending plan, and the
availability of State Aid funding and donations constantly becomes more vital to
our services, Unfortunately, the outlook for next year's State Aid funding is
grim-we could be facing a cut of 40% in that critical grant money in the next
7
State budget. More information on this will be coming to us within the next
several weeks,
EXTENSION SERVICES
. Number of services provided: 469 phone calls, 57 office visits, 35 visits to clients,
15 group teachings with 551 participants, 6 media submissions, and 938 bulletins
distributed, Total Budget for FY 09/10: $186,213,00; Year to Date Expenditures
and Encumbrances: $125,647,99; Remaining Balance: $55,280,17; Percentage of
budget spent and/or encumbered year to date: 70%,
The Extension Director accomplished the following activities:
. Facilitated the Monroe County Green Initiative Task Force (GITF) monthly
meeting, Major items of discussion were: revised draft by-laws, recycling efforts,
clean energy grants, and letters to utilities and municipalities regarding their
participation in the GITF,
. Presented an overview of the Climate Action Plan process to the BOCC.
. Presented a two-hour consumer workshop on solar electric and solar hot water
systems to homeowners in Pinellas County,
. Participated in a Climate Change Town Hall Meeting conducted by
Commissioner George Neugent.
. Attended a Florida Dept. of Environmental Protection Overseas Heritage Trail
workshop in Key Largo and thanked them for their cooperation in relocating the
Conch Key Trap Storage Area adjacent to the bicycle trail.
. Provided expert testimony in a Florida DCA v, WSG and Monroe County
administrative hearing regarding the bias against Monroe County within the
criteria used in awarding funds under the Stan Mayfield Working Waterfront
Grant Program,
. Attended a meeting of the Florida Keys Commercial Fishermen's Association to
discuss current fisheries issues,
. Met with representatives from the Florida Department of Agriculture and
Consumer Services to discuss and plan for a future visit to develop a marketing
video depicting the historical character of the Florida Keys and the importance of
commercial fishing in the Keys culture,
The Environmental Horticulture Agent accomplished the following activities:
. Invited to talk about "What is Worm Farming?" to 20 students and two adults
from the Poinciana Elementary Recycling Rangers,
. Held an insect identification workshop at the Key West Community Garden
meeting,
. Participated in three Webinars: Statewide Master Gardener Training, Turf and
Ornamental Pesticide In-Service Training, and Nutrient Deficiencies and their
Causes, Twenty-two Master Gardeners attended these sessions,
. Released parasitic wasps at ten locations: six in Key West, two in Big Coppitt,
and one in Ramrod Key,
. Set up a horticulture education booth at the Sugarloaf Firehouse Plant Sale, with
five Master Gardeners assisting ten clientele,
. Set up a horticulture education booth at GardenFest Key West, with 13 Master
8
Gardeners helping 98 clientele,
. Held six regional plant clinics (two in Key West, one in Big Pine Key, one in
Marathon and two in Key Largo) with 16 Master Gardeners assisting 25 clientele
with their plant and insect problems,
. Made seven site visits: Key West (2) - community garden, home garden; Cudjoe
Key (1) - citrus nutritional problem; Summerland Key (1) - palm problem;
Marathon (1) - plant selection and problems; Islamorada (2) - stunted Schefflera,
Bougainvillea,
. Updated the horticulture blog "Florida Keys Landscape Advisor" with a video
depicting a Mealybug destroyer lady beetle eating scale eggs,
. Set up a horticulture education booth at the Upper Keys Garden Club Garden
Walk.
The Family & Community Development Agent accomplished the following activities:
. Taught a workshop which presented findings and best practices for residents to
reduce their carbon footprint through efficiencies and retrofits, The workshop
included information about financial savings that are associated with energy
efficiency, steps that residents can take from behavior changes that are free, to
long-term investments,
. Held four workshops for the High School Financial Literacy Program bringing
supplemental materials to enhance students' learning,
. Worked with County staff researching The Energy Efficiency Community Block
Grant Program, which will provide funding to promote energy efficiency
measures and renewable energy initiatives,
. Worked on the Green Living and Energy Education (GLEE) awards submission
for Monroe County which highlighted all of the County's efforts at GHG
reduction, energy efficiency, and promotion of green principles,
. Attended the Family and Consumer Science Summit in Ocala, FL where she
shared resources she developed for energy efficiency education programs,
. Held a community workshop regarding tax deductions, tax credits and rebate
programs for energy efficient upgrades to residents' homes including appliance
rebates, home retrofit deductions, and clean energy tax credits,
GROWTH MANAGEMENT
Performance Measures For The Growth Management Division
GMD Comparative Revenue Summary
Revenue Total Total Revenue Revenue Revenue % Variance
Budget Revenue Revenue Ending Ending Ending Revenue
FY 2010 Collected in Collected February February FY February Ending
FY 2009 in FY 2008 FY 2010 2009 FY 2008 February
FY 2010
To
February
9
FY 2009
Building $2,660,000 $2,610,100 $2,857,684 $1,024,794 $1,045,535 $1,279,972 -2%
Permit
Licenses &
Permits
Planning $500,907 $602,387 $488,081 $204,168 $235,967 $274,192 -13%
Department
Fees
Code $100,000 $288,941 $110,412 $71,983 $79,629 $30,486 -10%
Enforcement
Fines &
Forfeits
. These are the primary, customer driven revenues and do not include the revenues obtained by
taxes etc,
EXPENSES
Budget Total Total FY 2010 FY 2009 FY 2008 %
FY'10 Expenses Expenses Expenses Expenses Expenses Variance
FY 2009 FY 2008 Ending Ending Ending Expenses
February February February Ending
February
FY 2009
To
February
FY 2010
Growth Mgmt. Admin, $903,834 $455,898 $648,098 $138,734 $151,869 $214,938 -9%
Geographic Info, (GIS) $287,555 $230,509 $181,935 $68,993 $77,941 $59,675 -11%
Planning $1,040,834 $899,234 $878,366 $368,079 $323,019 $384,844 +14%
Comprehensive Plan $221,000 $46,045 $74,655 0 6,308 $35,631 -100%
Planning Commission $98,142 $84,698 $88,345 $27,456 $32,885 $35,397 -17%
Environmental Resources $275,222 $268,992 $330,016 $98,926 $112,894 $132,872 -12%
Marine Resources $52,850 $51,876 $84,753 $21,888 $19,808 $40,323 +11%
Code Enforcement $1,159,509 $1,047,668 $894,006 $426,754 $369,648 $339,170 +15%
Pump-Out Boat $67,443 $70,250 $64,640 $25,238 $28,224 $18,371 -11%
Building Department $2,389,816 $2,232,844 $2,311,238 $818,678 $827,475 $887,324 -1%
Marine Resources Office
. Coordinated with Code Enforcement on procedures for abandoned vessels from
private property
. Developed and ordered pump outs signs for marinas with pump outs
. Handled approximately 35 customer inquiries; performed 3 site visits
. Awarded job for Pilot Program surveys at Key West and held coordination
meeting with Sandy Walters Associates
. Developed proposal request for boating surveys at Boca Chica harbor area,
. Coordinate with FKNMS regarding the proposal for expansion of the existing
NDZ
. Assembled information regarding the pump out program history and provided
associated memo to BOCC regarding issues the program is facing
. Responded to issues regarding a management agreement with DEP for the end of
Summerland Rd in Key Largo
10
. Coordinating efforts with Pump out USA regarding the provision of free pump outs
throughout the state
. Coordinated general maintenance on the pump out vessel and trailer
. Completed triennial channel markers surveys for FWC and provided updated
marker database
. Coordinated the disposal of seven derelict vessels for citizens
. Assisted the City of Key West with derelict vessel removals from the USCG
Museum
. Provided assistance to the City of Cedar Key regarding the development of a
public mooring field
. Coordinated maintenance on the Marine Resources survey vessel
. Coordinated with the Village of Islamorada Nearshore Water Committee
regarding assistance with funding for a pump out vessel
. Finalized Inter-Local Agreement with Key West regarding Pilot Program surveys
. Coordinated with Planning staff on a development order at Gilberts Marina
regarding liveaboards
. Completed provisions for docking facilities at the Nelson Center for the pump out
vessel
. Coordinated efforts regarding the need for a slow speed zone at Jewfish Creek
. Attended BOCC meeting in Key Largo for backup to Pilot Project agenda items
. Submitted request to FWC regarding changes in signage for boating regulatory
zones
. Coordinated with Cudjoe Key Property Owners Association regarding transfer of
aids to navigation
. Provided agenda and public notice for upcoming MP AC meeting
. Coordinate with management at Bahia Honda State Park regarding a request for
the development of a public mooring field
. Coordinated with CV A Program regarding the provision of pump outs for
commercial vessels and floating structures
. Coordinated with FKNMS regarding the provision of materials for day moorings
at the Adolphus Busch
. Pumped out 66 vessels in the Key Largo area
Geographic Information Services Office
GIS Projects
FLUM (on-going)
Zoning updates
Tier Committee GIS data updates
FLUM Amendments - Planning (maps for Ads and Meetings)
GIS Server/Intranet Site Maintenance and data updates/editing (on-going)
ArcGIS Server upgrade 9,3,1
TDRC Web Mapping Application (Public Access)
GIS Data/Map Requests
Tier Designation Review Committee draft maps
TDRC Wastewater Districts
Map, data and orthophoto Requests - Keith & Schnars
11
Addressing
12 Address Assignments
Code Enforcement Department
Number of New Cases Opened
Number of Inspections completed
Number of Cases Heard before Special Magistrate-
Fines Collected
After the Fact Fees Collected
Number of Contractor Citations Issued
Number of Contractor Citations Heard
Contractor Citations Paid (2)
390
1700
62
$ 2,559,00
$ 6,525,00
26
o
$ NO report
Flood insurance Inspection Fees Collected
Totals Collected
$ 1,260,00
$10,344,00
Planning & Environmental Resources Department
Current Planning Category
Appeal to Planning Commission in Progress
Appeal to DOAH in Progress
Code Enforcement Referral (estimated at 1 per week per Current Planner (4))
Conditional Use, Major Permit in progress
Conditional Use Minor Deviation Completed
Conditional Use, TDR in Progress
Public Assembly Permits Applied
Public Assembly Permits Issued
Public Assembly Permits in Progress
Road Abandonment in Progress
Variance, Administrative Applied
Variance Administrative in progress
Variance, Planning Commission in Progress
Permits Reviewed & Processed
Vacation Rental applied
Vacation Rental Mgr, License Applied
Vacation Rental Mgr, License Issued
ROGO related applications
ROGO Exemptions Applied
ROGO Exemptions/Denials Issued
Mixed Use Category
LDRD's Applied
Customer Service
In-person inquiries estimated at 5 per day per planner (2)
Telephone inquiries estimated at 10 per planner (7) per day
Email inquiries estimated at 5 per planner (7) per day
Request for Research Applications
Administrative Meetings
Development Review Committee/Agenda Items
Planning Commission/Agenda Items & a Keith & Schnars presentation
12
3
2
16
5
2
2
3
4
5
5
2
5
1
122
4
3
3
7
6
1
300
2100
300
3
1/3
from 9 am to 10:30 am, 1/2
Comprehensive Planning Category
Meetings
Meeting - Christine, Townsley, Mike regarding the "H", Alicia Putney
Meeting 1
Meeting - FLUM and LUD ad language for 2 projects 1
Meeting - K&S and staff for monthly staff report 1
Meeting - K&S, County Staff, sub consultants - project overview, population
projections and transportation issues 1
Meeting - K&S, sub consultants and staff on EAR process 1
Meeting - Planning Commission presentation from K&S 1
Meeting - Planning Director on SugarloafKey Overlay scheduling 1
Meeting - Sf. Admin of Environmental Resources and Planning Director
on Big Pine Development 1
Meeting - Sr, Admin of Environmental Resources and Tiffany on the
HCP ROGO criteria 1
Meeting - staff to discuss Sugarloaf Center Overlay district - Sugarloaf Key -
complete - Christine's review 1
ForrnalMeetings 10
Informal Meetings on various planning related topics 20
Planning Commission Meetings 2
Comp Plan Update meeting with K&S to review progress 1
Comp Plan Update meeting with K&S and the Division Directors 1
Comp Plan Update meeting with K&S & URS to review transportation issues 1
Comp Plan Update meetings with K&S & the Planning Commission 1
Comp Plan Update meetings with K&S and the BOCC members 5
Comp Plan Update meeting with K&S, Fishkind & the DCA to review
Population projection methodologies 1
Comp Plan Amendment BOCC Transmittal Hearing 1
Reviewed
Reviewed Wisteria Island Sub-area proposal with staff 1
Reviewed planning staff reports 4
Reviewed Comp Plan Amendments with the Growth Management Director
~~~~~ 1
Reviewed Sugarloaf Overlay District proposal 1
Analyzed and Wrote
Wrote-FLUM Transmittal BOCC packet-MDJ-complete-attorney's review 1
Wrote-FLUM Transmittal BOCC packet-127 FCT-complete-attorney's review 1
Wrote-LUD Ordinance BOCC packet-MDJ-complete-attorney's review 1
Wrote-LUD Ordinance BOCC packet-127 FCT-complete-attorney's review 1
Wrote-School Board regarding school statistics 1
Wrote-LUD Ordinance/Resolution BOCC-PC packet-Lloyd Good 1
Assisted
Assisted Gail in pulling Tavernier overlay documents 1
Assisted in setting up FWS meeting 1
13
Assisted with updating web page 1
Emailed
Emailed-127 parcel-FLUM information to Trepanier & Associates 1
Emailed-CIE/CIP to County Attorney 1
Responded to E-mails & Phone calls 25
Emails sent and received 400
Miscellaneous
Amended 2 FLUMS and 2 LUDs for BOCC transmittal packages 1
Assembled notebooks for CBRS for 8 people 1
Compiled ROGO documentation & compiled a report for K&S consultants 1
Compiled SFR permits from the HCP Master List to determine if there land
Clearing was done 1
Discussed-Road abandonment potential project with applicant & staff 1
Discussion-Bond agent regarding Key Haven Bond, sent info to current planners 1
Edited-ordinance for Sugarloaf Overlay district 1
Edited-ordinance for transmittal deadlines 1
Received-From School Board School-statistics 1
Received & reviewed monthly and statement bill from K&S 1
Answered questions on submerged land leases 1
Telephone Conversations
Comp Plan Update Teleconference with K & S to review process 1
Called Lloyd Good for change in meeting dates 1
CIP conversations with lawyers and upper management 1
Phone call-discussion with applicant regarding a plat 1
Phone call-Resident regarding conservation amendment 1
Telephone conversations 20
Estimated
Estimated at 5 per day per planner (2) - in person inquiries
Estimated at 10 per planner (7) per day - telephone inquiries
Estimated at 5 per planner (7) per day - email inquiries
300*
2100*
300*
Environmental Resources Performance Review
Site Visits
Code Enforcement Referral
Land Authority Referral
Permit Application Site Visit
Wetland Delineation
Pre App Conference
24
3
14
2
2
Other
Turtle Stranding
Site Visits (Miscellaneous)
Written correspondence/ biological assessments
Administrative Relief/Beneficial Use
Vegetation Mitigation Letter
2
75
2
1
14
Code Enforcement Assessment Memo 6
Conditional Use Staff Report 2
GIS Map (assorted) 57
Interagency Coordination (DEP, ACOE, FKEC, FL Park Serv" FWC) 7
Letter of Current Site Condition 1
Meetings & miscellaneous
Big Pine Habitat Conservation Plan 2
DRC 1
Tier Review - meetings 6
Climate Change Compact 1
Other
Habitat Mapping 3
Phone Calls (estimated 3 persons) 300
Front Counter Walk-in (estimated 3 persons) 300
F ebrua '2010' Avera es
Permit Type
Single Family Res-Conventional
Demo
Dock
Fence/Retaining Walls
Fire Protection System
LP Gas Tanks
Land Clearing
Paving
Pool & Spa
Ri prap
Fill
Air Conditioning
Deck
Boat Davits
Roofing - Resi dential
Enclosure - Other
Exterior Renovations
Addition-Residential
Building Miscellaneous
Electric Misc
Plumbing - Miscellaneous
Bio Miscellaneous
Signs
Chickee Hut
Lawn Sprinkler System
Remodeling - Residential
Commercial Misc
Roofing-Commercial
Average Days
782
9
42
15
25
22
o
276
46
10
13
o
74
43
9
83
37
87
27
12
18
4
39
175
39
23
93
17
15
Stairs
Repl. Of Single Family Resid,
MH Replaced With Sfr
Demo-FEMA Compliance
Alarms-Residential (Burglar/FI
Painting
Window Replacement
FEMA Insp Compliance Program
Gas Tanks - Above Ground
Land Clear/Exotics Walk-Thru
Pool & Spa Maint. & Repair
Post Card AlC Permit
Air Conditioning-Walk Thru
Roofing Walk - Thru
Exterior Concrete Repairs
Electric Misc Walk Thru
Plumbing - Sewer Tie-In
Plumbing - Sewer Tie-In Walk-T
Plumbing Misc Walk Thru
FEMA Insp Sale County Inspecto
Avera e Da s All Permits
Performance Statistics
Monroe County Building Department - February, 2010
Number Of Permits
AppsSubmitted
Permits Issued
Walk Thru
Cert Of Occupancy
Inspections
Total
AVERAGE PER DAY (19 Working Days)
Per Discipline: Building/Roofing
Electrical
Plumbing
Mechanical(A/C)
Gas
Plans Reviews
Total
AVERAGE PER DAY (19 Days)
Per Discipline :Abo
Bio
Bio Pend
CO,
Code Enf 2
Code Enf 3
Coord
02/01/1 0-02/28/1 0
16
o
265
70
20
2
o
19
o
93
3
14
1
o
5
8
1
2
o
o
o
53
576
489
84
13
2456
129
993
275
929
52
12
3119
164
220
72
3
1
76
Elect 77
Exam 129
Fema
File 3
Final
Fire 18
Flood 65
M-Storage 2
Mar-Bldg 371
Mech 28
Official 1
Pending 8
Plan 50
Plumb 35
Ready 2
ROGO
ROGO Ready
Roof
S,L Building 158
Track 1
UK-ABO 273
UK-BIO 106
UK-BLDG 414
UK-CODE 30
UK-COORD 329
UK-ELECT 72
UK-ENG
UK-EXAM 132
UK-FILE 14
UK-FIRE 52
UK-PENDING 52
UK-MECH 15
UK-NROGO
UK-PLAN 100
UK-PLUMB 33
UK-READY 131
UK-ROOF 16
UK-ROGO 3
UK-TRACK 26
EMERGENCY SERVICES
Fire Rescue
. Submitted SAFER grant quarterly report and payment request for period from
09/20/09 through 12/19/09 and received revenue in the amount of $155,582,90,
. Attended IAFF Local 3909 Union negotiations meeting February 22nd
. Interviewed seventeen candidates from firefighters' eligibility list established in
July to expand the FY10 hiring list.
. Attended Upper Keys Health Care Taxing District Meeting Feb 1ih
. Updated several Monroe County Fire Rescue Standard Operating Procedures
17
(SOPs) and Forms, Some of February's revisions related to uniforms, patient care
reports, response to fire and medical emergencies, radio procedures, sick leave,
timecards, personal appearance and grooming, hose testing, and station daily logs,
Training
. Firefighter II Class started with 15 students,
. EMTs and Paramedics completed the required continued education training
online,
. Volunteers attended HIP AA, Ropes & Knots and Hose Lay training,
Fire Marshal
. Reviewed 30 commercial plans for adherence to building and fire codes and
conducted 3 final inspections,
. Finalized the Request for Proposals for the installation of fire hydrants per Board
of County Commissioners' direction,
. Met with Growth Management Director regarding "Clean-Up Stock Island",
. Investigated residential trailer fire in Key Largo,
Emergency Management
. Conducted Monroe County Marathon Airport Full-Scale Exercise and Exercise
Debriefing Meeting
. Worked with All Hands Consulting on the finalization ofMC Continuation of
Operations Plan (COOP)
. Conducted a final Turkey Point Nuclear Power Plant - Radiological Emergency
Preparedness non-evaluated exercise (scheduled for March 4,2010) Emergency
Responders briefing
. Continued to work on the 2010 Local Mitigation Strategy Plan revision
. Received approval from the Florida Division of Emergency Management
(FDEM) to use the Department of Homeland Security (DHS) approved grant
funds for WebEOC (web-enabled crisis information management system)
development, customization and planning Scope of Work (SOW),
Trauma Star
. Identified new Flight Nurse and began hiring process
. Evaluated and trained seven new Qualified Flight Medics
Upper Keys Health Care District
. Advisory Board Meeting Feb lih
PUBLIC WORKS
. Pollution Control removed over 60 of debris illegally dumped in County
rights of way, and 10,05 tons for other departments (8,260 lbs of debris
from the Key West Garage; 5,260 lbs of brush from the Marathon
Airport; and 4,480 lbs of invasive exotics for the Land Authority)
. Removed 2,100 lbs of debris from Mariposa Road on Ramrod and the
Road Department installed the barriers to stop illegal dumping
. Completed annual FDEP mandated fuel tank testing
. Disposed of surplus oil tanker located at Marathon Public Works yard
. Refurbished wood chipper for the Lower Keys Road Department
. In-house Fleet technicians repaired defective fuel pump at the Marathon Garage
18
. Completed annual pre-hurricane season generator inspections
. Completed proposed FY11 vehicle replacement schedule
. Completed refurbishment of generator for chiller located at Jackson Square in
Key West
. Marathon's and Plantation Key's Garage Supervisors/Lead Mechanics completed
three days of supervisor and management training
. 15 separate events were scheduled at the Nelson GC requiring 44 hours of staff
overtime
. Installed panic buttons in Growth Management and Mayor Murphy's office
. Replaced carpet in Judge Ptomey's chambers
. Completed humidity test of PK Courthouse lobby and determined levels are
within ASHRE requirements
. Installed "PUBLIC WORKS" letters on the Spotswood Building
. All air quality test results for the Ellis Building Tax Collector's office are within
acceptable limits
. Replaced two alc package units at the Communications building
. All upper keys fire extinguishers have been checked and validated
. Formed slab and placed reinforcing for Fire Rescue at the Layton Station
. Replaced RPZ valve at Harry Harris Park
. Replaced decking at Harry Harris Park pier
. Supplied 40 tons of crushed rock to repair entry road at Grassy Key Medical
Examiner's office
. Completed resurfacing and striping of the Marathon AARP parking lot
. Completed five (5) new picnic tables and slabs at the Pines Park near the Key
West Airport
. Major repairs completed on the Gato Building HV AC system
. Final inspection completed for Stock Island Detention and Marathon Garage
overhead door wind retrofit projects
. Carpets cleaned at the Marathon Government Center
. Installed computer antennae on Sheriffs Special Ops and Jail
. Remodeled Lieutenant's office at Sheriff s Substation
. Replaced vandalized exterior lighting at the Medical Examiner's Facility
Engineering Services:
Roads and Bridges Stimulus -
Palm Drive Bridge - 99% Complete
. FDOT audit of Monroe County files and adherence to ARRA guidelines
conducted February 5, 2010; only a few minor clarifications required,
. Bridge construction and guardrail installation complete as of February 10,
2010,
. mbi k2m /Monroe County's walk through is complete; construction found
to be acceptable,
. Toppino's addressing payroll and job classification issues and will bring
the complete FDOT audit issues into compliance,
. Final FDOT site inspection expected within the next two weeks,
19
. Upon approval of inspection, final payment minus retainage will be
approved for the contractor in order to close out the project.
Geiger Creek Bridge Project-
. Pre Con Meeting held February 10,2010,
. Contract expiration date June 30,2010,
. Project is in Design Phase,
. Permits are being processed by Army Corps and Contractor was notified
to distribute the documents to all involved agencies in an effort to expedite
the process,
. The Coast Guard has also been in contact with the Contractor to
coordinate construction requirements,
Tom's Harbor Channel Bridge-
Staff provided cost estimate to FDOT for design and repairs to bridge
904600 (US 1 to Duck Key), DOT working to provide $1,159,433 of
Small County Outreach Program money to fund 75% of bridge
design/repair costs,
Proj ects -
. Hurricane Wilma 2005 - Staff working with FEMA and Dept. of Emergency
Management to close out various project worksheets from Hurricane Wilma,
. Boca Chica Road Repair project (Hurricane Wilma) - Staff met with Army Corps
of Engineers onsite, Corps determined no permit was required for work. Staff
requesting approval to advertise for construction bids on March 2010 agenda,
. Duck Key Security Cameras - Staff briefed Mr. Tom Neville from Duck Key
Security district on various types of systems to obtain direction prior to
proceeding, Staff completed draft Request for Proposals, Approval to advertise
obtained at January 2010 BOCC meeting, Upon review of scope by Duck Key
Security District RFP will be posted for responses,
. Duck Key Pedestrian Bridges -Staff attended status meeting with Duck Key
residents on May 5, 2009 to discuss pedestrian bridges, Duck Key would like two
options for pedestrian bridges (county has provided one), County staff will
research issues such as vegetation trimming, power pole locations, etc, that will
impact bridge installation, (ongoing),
. Monroe County Bus Shelter Contract - staff prepared draft request for proposals
for the bus shelter installation/maintenance contract which will expire in May
2010, Agenda item requesting discussion and direction on whether to renew or
advertise for proposals is on the March 2010 agenda,
. Big Coppitt Sewer Project - Monroe County site inspector oversaw striping of final
roads in Big Coppitt project. Construction was completed in mid-February,
. Key Largo Sewer Proj ect - Monroe County site inspector performing oversight on
four Key Largo sewer construction projects, Work involves overseeing KL
contractors to confirm compliance with Monroe County requirements, attending
construction progress meetings as needed,
. Staff investigates and follows up on resident complaints and concerns about road
restoration work, contractor adherence to safety procedures, neighborhood access
during construction,
20
. Pigeon Key Ferry Service - Staff processes monthly invoices from ferry contractor
and prepares reimbursement requests to DOT for payment through Joint Participation
Agreement for ferry service funding,
. Staff preparing Request for Proposals to renew existing ferry service contract which
expires on June 30, 2010;
. Staff processing amendment to the Joint Participation Agreement with FDOT for an
additional $250,000 funding to operate the ferry service through June 2011.
. County Right of Way Ordinances - Reviewed draft ordinance and provided
comments to County Attorney to revise right of way codes and ordinance in response
to requests for clearer restrictions on right of way use, (ongoing),
. DOT Traffic Signal/Street Light Maintenance Agreements - Staff is working with
FDOT to include non -FDOT street lights on US 1 under the agreement for
reimbursement. ( ongoing), Staff performed audit of County street light/traffic
signal accounts and is working with FKEC/Keys Energy to update records,
. Lighting Task Force - Engineering staff participated in the Lighting Task Force
meeting to look at new lighting technology for energy saving purposes, Participants
include Keys Energy and various municipalities, (ongoing),
. Cudjoe Gardens Roads - Staff worked with County Attorney to develop procedure
for road dedication, Final procedure was forwarded to Cudjoe Gardens homeowners
group for action,
. FDOT Sign Permit Request - staff is submitted a sign permit request to FDOT for the
driveway connection for the Medical Examiners Building at the request of the
Overseas Heritage Trail Coordinator. (ongoing),
. No Name Key Bridge/Keys Energy - Engineering staff is working with County
Attorney, Growth Management and Keys Energy regarding installation of electrical
service infrastructure on No Name Key Bridge and county right of way,
. Duck Key Bus Shelter - staff working with Clear Channel on request from Hawks
Cay Resort to install a bus shelter on US 1 at Duck Key, Staff is coordinating with
FDEP Overseas Heritage Trail and FDOT project staff (ongoing - wait until
direction on contract is received),
. All American Highway Wayfinding Project - staff provided input to Planning Dept.
for potential All American Highway Enhancement project. Engineering staff provided
guidance on FDOT' s LAP program,
Ongoing Work -
. General Right of Way permits reviewed - 13
. Right of way permits issued - 10
. Inspection of completed right of way work - 11
. Assistance to code enforcement on right of way issues: inspection of locations with
potential violations, providing engineering opinion of circumstances - 3 locations
. Staff handled various calls from public regarding wastewater assessment payoff,
drainage and flooding complaints, miscellaneous sewer and road inquiries, requests
for street light installation, traffic signal timing
. Staff working with County Attorney on petition by Gilbert's Marina in Key Largo to
re-name access road to their establishment.
21
PROJECT MANAGEMENT
. ADA Compliance Survey and Assessment - Public review of the Evaluation
Assessments reports placed in the Key West Library, Marathon Library and Key
Largo Library is ongoing,
. ADA Compliance Transition Plan Negotiations -BOCC approved commencement of
negotiations with the number one ranked firm on 19th of August 2009, First
negotiation meeting held August 27th, 2009, Second meeting held on October 2ih
2009, Staff compiling and providing to Bender & Associates copies of county policy
and procedures, program services, Evaluation and Survey Assessment documents,
etc, Bender submitted proposal on September 23rd,Contract approved by BOCC
December 16th, 2009, Notice to Proceed will be issued in March-April 2010,
. Warranty Support to Public Works - Staff continues to provide on-going warranty
support to Public Works for the Murray Nelson Government Center, the Freeman
Justice Center, Big Pine Park, Medical Examiner Facility and the Big Pine Key Fire
Station #13,
. Litigation Support to the County Attorney Office - staff continues to provide on-
going litigation research, documents, and support for the Freeman Justice Center,
Tower Group v, Monroe County as well as Monroe County v, Gonzalez Architects
o Freeman Justice Center Litigation-legal research and negotiations for a
settlement agreement on-going, Draft agreement prepared by outside counsel
in coordination with County Attorney's office completed and approved by all
parties, Meeting held with Tower/OHL on October 19th 2009 agreement
reached, Agreement has been executed, Initial payment of over $1.5 million
has been made, Remainder of $500K will be paid upon receipt of all releases,
o Gonzalez Architect's Litigation - staff's findings regarding costs to the county
due to design errors by architect forwarded to attorneys, Meeting held with
Project Management, consultants and County Attorney's on October 15th
2009, On going litigation, Next meeting with Legal to be held on January
22nd 2010
, ,
. Grant Research, application and administration - ongoing process
. ARRA Stimulus Fund Grant- Staff is actively researching and reviewing available
fund grants,
o FEMA- ARRA Fire Station Construction Grants: Grant submitted on July 10,
2009 is in peer and technical review process, Earliest notification of award of
funds will be late December 2009, MC not awarded Construction Grant
. SFWMD Fund Grants FY2009 -Progress reports and invoice reimbursement request
for $144,520,88 prepared by staff as per Agreement #4600001593-FY2009 for
stormwater work completed on the following county projects: ,
Total funds reimbursement received as of Nov, 5th 2009 is $144,510,75,
o Big Pine Fire Station
o Key Deer Boulevard Sodding Project
o Lower Keys Wastewater Treatment Plant
o Key Largo Wastewater Treatment Plant.
o Duck Key Wastewater Treatment Plant
o Plantation Key Fuel Facility Project
22
. SFWMD Fund Grants FY20 1 0 - Staff creating budgets, scope of work and proj ect
schedules to submit to SFWMD for stormwater drainage improvements grant funding
in FY2010, Following grants were submitted: Conch Key Fire Station
Stock Island Fire Station
Marathon Court House
Duck Key Waste Water
. TDC Fund Grants - Staff prepared and submitted applications for two projects which
have received DAC approval: Request for proposal (RFP) approved by Legal and will
be presented to the BOCC in January 2010,
o East Martello Tower- construction of emergency fire stairs and repair of
interior access stairs,
BOCC on January 20th,s meeting approved Bender and Associates as the
Architect for the East Martello Stairs Project. The project is being advertised
for bids,
o West Martello Tower - demolition and replacement of existing perimeter
fencing, Will be held until March-April meeting,
o Project Management is in the process of applying for grants for five additional
TDC projects,
. TDC Grant Compliance Inspections and Pay Applications Review - Inspections and
reviews for TDC projects were done on the following projects:
o Western Union Schooner - TDC project's first segment completed, Segment
two work is complete,
o Tropic Cinema Renovation -Project now complete,
o Ann's Beach Boardwalk Repairs TDC project application review completed,
o Marine Mammal Conservancy TDC project application review complete
o Butterfly Garden TDC project application review complete
o Sombrero Beach Playground Equipment Replacement TDC project
application review complete
o Tennessee Williams Theater Fire Curtain TDC project application review
complete
o Dolphin Research Center TDC project. Storm water segment complete
o Marathon Community Theater TDC project application review complete
o Marathon Amphitheater Sound System Project complete
. Freeman Justice Center- All Construction Completed - Close-Out Phase on-going
o Braswell Co, has been notified by County Attorney to correct grouting
problem(s) with exterior brick and stone, Second notice to Braswell from
Legal in December 2009, Braswell on site correcting grout problem(s),
. Emergency Operations Center - Marathon Airport
. Design Development phase: AlE is preparing the submission for building permit
review, No response to date from FEMA with respect to HMGP grant award increase,
FDEM confirmed that as ofFeb, 15th, 2010 they have forwarded the County's request
for $200,000,00 DHS/EOC grant to FEMA for award, The County's request is
covered under the non-competitive section of the grant program and, hence, should be
granted sometime in late FY10, The FEMA HMGP grant has an expiration date of
June 2010, We still have to file an extension request citing delays in funding
23
decisions, FAA response received (after six (6) months) and indicates there are site
objections that may require modifications,
o EOC Grant Reports and Reimbursements:
· HB7121Grant: We have received from the State's Grant Coordinator
$433,035,97 for the third (3rd) quarter of 2009, We have requested (1-
19-10) additional reimbursement of $48,889,59
· Federal HMGP Grant: We have received from the HMGP Grant
Coordinator $44,688,32 for the third (3rd) quarter of 2009, We have
requested (1-19-10) reimbursement for $24,239,70 which will
complete the Federal Grant for phase 1.
· HMGP received on Feb, 1ih, 2010 $14,451.00 and $1,338,74 from the
State of Florida the remaining grant monies for the Marathon EOC.
This completes the grant for the HMGP (Federal portion) On Feb,
22nd, 2010 received Florida States portion of the grant monies in the
amount of $48,889,59,
. Big Pine Key Fire Station -Construction Complete- Close Out Phase
Certificate of Occupancy issued August 10, 2009, All warranty issues are being
addressed by the Contractor (PFEC),
SFWMD Grant Reports and Reimbursements: Staff has submitted progress report
and reimbursement request for storm water work completed, Waiting response from
SFWMD,
Sunset Point Boat Ramp - Completed and closed out-reimbursement check received,
Received reimbursement from the Florida Fish and Wildlife Commission in the
amount of $44,966,67, Which is 75% of the cost to construct the Boat Ramp at Sunset
Point. Check was received on Feb, 18th, 2010,
RFQ-Continuing Contract for Architects/Engineers - Opening date was August 25,
2009 with 26 responses received, Selection of Committee Members and delivery of
documents completed on August 27, 2009, Public Noticed Meeting was held at the
Marathon Government Center on Friday, September 25, 2009 beginning at 9:00 AM
and all submittals were ranked, A request was presented on October 21 8t 2009 to the
BOCC for authorization to enter into negotiation with 4 top ranked firms for
continuing contracts, Received signed contracts from top three (3) ranked which will
be presented to the BOCC - approved December 16th, 2009, They are CH2M Hill,
William A Horn and MBI K2M, Contract with CSA will be submitted to BOCC at
the January 2010 meeting along with request to add Bender and Associates as 5th AlE
consultant. Selection completed and approved,
. Plantation Key Fueling Facility - Contractor is still awaiting final inspection sign off
pending payment by the County of the mitigation fees, Final close out package
received and awaiting review,
. Medical Examiner's Facility Wetlands Mitigation - The CY 2009 compliance report
was submitted to SGFWMD as required under the permit. The construction
completion certification was completed for conversion to an operating permit.
Otherwise No change in the regulatory aspects of permit compliance,
. Conch Key Fire Station- All building department reviews complete, Planning
department will require approval of a minor deviation from the plans approved by the
Planning Commission, FDOT (Ms, Ivey) advised the Planning Department that they
24
have no objections to the plans although formal approval has not yet been received
from FDOT following late January submittal of additional information,
o Grant Submittal: Grant requesting a 50 % Federal match in the amount of
$1,351,529 for the construction of the Conch Key Fire Station is in federal
reVIew process,
. Marathon Courthouse Renovations - Renovation plan revisions are complete and
enroute to the County for permit submission to the City of Marathon,
. Stock Island Fire Station - Project Management preparing request to issue RFP for
construction including site acquisition to BOCC,
o Grant Submittal: Grant requesting a 50 % Federal match in the amount of
$2,122,069 for the construction of the Stock Island Fire Station is under
federal review process,
. Surface Water Management Reviews - One review conducted, Several consultations
on plans in progress by AlE firms or owners (2-3),
. Higgs Beach Restroom Renovation - Architect to be selected January 2010, Funds
are available for design of Master Plan, To be included in Higgs Beach Master Plan,
. Higgs Beach Visitor Center - Higgs Beach Committee Public Works Director and
Project Management Department Director held meeting with FORB BOD on October
15th to plan strategy, Second meeting being held Monday November 23rd, 2009, To be
included in Higgs Beach Master Plan,
. Higgs Beach Master Plan -Architect selected, William p, Horn Architects, P,A. has
been selected and a contract will be presented to the BOCC at the March meeting,
. Nelson Gov't Center - Ongoing support for post occupancy warranty work continues,
. Pump out boat location & sewer connection- Two possible sites have been identified,
Technical feasibility has been established, Proposals for costs will be developed in
the coming weeks and a proposal agreement developed with the KL WTD and Pilot
House marina and a fund request submitted,
. Layton Fire Station Feasibility Study-Site visits to the Layton FWC property
including FWC and City of Layton personnel and the Long Key Transfer station were
made, A review of technical site requirements (land area, road access, and permit
requirements) is underway, And will target a decision recommendation after the April
BOCC meeting,
. Projects On Hold
o Public Works Rockland - on hold,
o Jefferson B. Browne Building - on hold,
Old Tavernier School Town Meeting Hall - on hold,
TECHNICAL SERVICES
We completed 377 work orders for the month of February (additional work orders due to
email problems), promoted new domain controllers to take on primary authentication
roles, installed new backup server, installed additional data on Alchemy and updated
clients, pushed out new Microsoft security updates, defragged library computers, and
fixed Exchange email space issues,
25
VETERANS AFFAIRS
Clients Assisted: 1838
New Clients Assisted: 60
Field Visits 9
Benefits Delivery At Discharge 4
Van Clients Transported: 162
(to the V AMC, Miami as well as other Miami area hospitals, without incident)
The Veterans Affairs Department:
The financial data for the month of February totals to $222,907,00 and indicates the
amount of new revenue brought into Monroe County derived from claims for the entire
department, including Key Largo and Marathon,
The financial data captured monthly will vary due to the Veterans Administration
variable time frame on adjudication of awards, as well as the amount awarded,
26
BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date: March 17.2010
Division: Countv Administrator
Bulk Item: Yes x No
Department: County Adminstrator
Staff Contact PersonlPhone #:Connie Cvr/ 292-4441
AGENDA ITEM WORDING:
Approval of a resolution directing the Supervisor of Elections of Monroe County, Florida to place on
the August 24,2010 Election Ballot a referendum question concerning whether the Superintendent of
Schools for Monroe County should be changed from an Elected Official to one Employed by the
School Board,
ITEM BACKGROUND:
PREVIOUS RELEVANT BOCC ACTION:
CONTRACT/AGREEMENT CHANGES:
STAFF RECOMMENDATIONS:
TOTAL COST:
INDIRECT COST:
BUDGETED: Yes _No
DIFFERENTIAL OF LOCAL PREFERENCE:
COST TO COUNTY:
SOURCE OF FUNDS:
REVENUE PRODUCING: Yes
AMOUNTPERMONTH_ Year
No
APPROVED BY: County Atty _ OMBIPurchasing _ Risk Management _
DOCUMENTATION:
Included
Not Required ~
DISPOSITION:
AGENDA ITEM #
Revised 7/09
Board of County Commissioners
RESOLUTION NO.
- 2010
A RESOLUTION OF THE BOARD OF COUNTY
COMMISSIONERS OF MONROE COUNTY, FLORIDA,
DIRECTING THE SUPERVISOR OF ELECTIONS TO PLACE ON
THE AUGUST 24, 2010 STATEWIDE PRIMARY ELECTION
BALLOT A REFERENDUM QUESTION CONCERNING
WHETHER THE SUPERINTENDENT OF SCHOOLS FOR
MONROE COUNTY SHOULD BE CHANGED FROM AN
ELECTED OFFICIAL TO ONE EMPLOYED BY THE SCHOOL
BOARD
WHEREAS, the School Board, in Resolution No. 745, has requested, pursuant to
Section 1001.461, Florida Statutes, that the Board of County Commissioners direct the
Supervisor of Elections to place on the ballot of the Monroe County statewide primary election
to be held August-24,-2010 a referendum question concerning changing the Superintendent of
it"
Schools from an elected official to one employed by the School Board; now therefore,
BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF
MONROE COUNTY, FLORIDA:
Section 1. Pursuant to Sec. 1001.461, Florida Statutes, the Supervisor of Elections of
Monroe County, Florida, is hereby directed to place on the ballot of the Monroe County
statewide primary election to be held August 24, 2010, the following proposition, in both
English and Spanish, to be voted upon by the voters of Monroe County, Florida:
SPECIAL ELECTION, MONROE COUNTY
EMPLOYED SCHOOL SUPERlNTENDENT
Article IX, Section 5 of the Constitution of the State of
Florida provides that the school superintendent shall be
employed by the elected district school board, when
approved by a vote of the electors. Currently, the school
superintendent of Monroe County is an elected officer.
SHALL THE SCHOOL SUPERINTENDENT OF
MONROE COUNTY BE EMPLOYED BY THE
DISTRICT SCHOOL BOARD UPON EXPIRATION OF
THE CURRENT SUPERINTENDENT'S TERM?
YES
For Approval
NO
For Rejection
Page 1 of 3
Section 2. The Supervisor of Elections is further directed to require the School Board
to obtain preclearance from the U. S. Department of Justice before placing the
referendum on the August 24, 2010 statewide primary election ballot.
Section 3. The Clerk is hereby directed to send a certified copy of this Resolution to
Harry Sawyer, Supervisor of Elections, 530 Whitehead Street, #101, Key West, Florida
33040.
PASSED AND ADOPTED by the Board of County Commissioners of Momoe County,
Florida, at a regular meeting of said Board held on this 1 ih day of March, 2010.
...G
Mayor Sylvia Murphy
Mayor Pro Tem Heather Carruthers
Commissioner Kim Wigington
Commissioner George Neugent
Commissioner Mario Di Gennaro
(SEAL)
Attest: DANNY L. KOLHAGE, CLERK
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
By:
By:
Deputy Clerk
Mayor/Chairperson
Page 2 of 3
RESOLUTION NO. 745
UPON MOTION DULY MADE, SECONDED AND PASSED BY A MAJORITY VOTE
OF THE SCHOOL BOARD OF MONROE COUNTY, FLORIDA, it is hereby
RESOL YED, that the Board of County Commissioners of Monroe County, Florida, is hereby
requested in accordance with Section 1001.461, Florida Statutes. to cause to be placed on the ballot of
the State-Wide primary election to be held on August 24, 2010, the following proposition, in both
English and Spanish, to be voted upon by the voters of Monroe County, Florida:
*****
SPECIAL ELECTION, MONROE COUNTY
EMPLOYED SCHOOL SUPERINTENDENT
Article IX, Section 5 of tbe Constitution of the State of Florida provides that the
school superintendent shall be employed by the elected district school board, when
approved -by a-vote of the electors. Currently, the school !superintendent of Monroe
County is an elected officer.
~.,~
SHALL THE SCHOOL SUPERINTENDENT OF
MONROE COUNTY BE EMPLOYED BY THE
DISTRICT SCHOOL BOARD UPON EXPIRATION
OF THE CURRENT SUPERINTENDENT'S TERM?
YES'
For A~proval
NO
For Rejection
*****
FORMALLY RESOLVED by the School Board of Monroe County, Florida, at its regular
meeting held on February 9, 2010, at Islamorada, Florida.
9:;Jffi~fI,
Chairman of the Board
ATTEST:
~---->
r. Jose P. Burke,
Superintendent
Page 3 of 3
BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date: March 17.2010
Division: Countv Administrator
Bulk Item: Yes ---.X... No
Department: County Administrator
Staff Contact /Phone #: Abra Campo x, 4445
AGENDA ITEM WORDING: Approval of the reappointment of Kim Bassett to the Health Council
of South Florida for a two year term in the category of Provider.
ITEM BACKGROUND: Ms, Bassett had been appointed to the Health Council on 12/19/07 and her
term had expired 12/18/09,
PREVIOUS RELEVANT BOCC ACTION:
CONTRACT/AGREEMENT CHANGES:
STAFF RECOMMENDATIONS: Approval
TOTAL COST: ~ INDIRECT COST:
o
BUDGETED: Yes _No
DIFFERENTIAL OF LOCAL PREFERENCE:
COST TO COUNTY
o
SOURCE OF FUNDS:
REVENUE PRODUCING: Yes
AMOUNTPERMONTH_ Year
No
APPROVED BY: County Atty _ OMB/Purchasing _ Risk Management _
DOCUMENTATION:
Included X
Not Required_
DISPOSITION:
AGENDA ITEM #
Revised 7/09
Officers
Albert Collazo
Chair
Jose Perdomo, M,H.5,A, J.D,
Vice Chair
Ed Rosasco, FACHE
Treasurer
Debra S, Walker, Ph,D,
Secretary
Fermin Leguen, M,D,
Member-at-large
Board Members
Kim Bassett
Melvyn Fletcher, M,D" F,AAP,
Pascal Goldschmidt, M,D,
Rev, Dr. Ted Greer, Jr.
Nelson Lazo
Kerry Shelby, C,PA
Fred Stock, M.5,W" LN,HA
Honorary Board Member
Hon, Carlos Alvarez
Mayor, Miami-Dade County
President & CEO
Marisel Losa, M,H.5,A
An Equal
Opportunity
Employer
HCSF
11".11111 C,\lIrl< il ,'f 'S,\Ulll fk'ridd. Irl<.
March 5, 2010
Roman Gastesi
County Administrator
County of Monroe
1100 Simonton Street
Key West, FL 33040
Dear Mr. Gastesi:
The Health Council of South Florida Inc. is pleased to request the reappointment
of Kim Bassett to the Board of Directors in the category of Provider. The
reappointment term for Ms. Bassett is two years.
Ms. Bassett is an active Board Member. The Council's Nominating Committee
reviewed her status and determined that she is in good standing and eligible for
reappointment. A resume accompanies the application form, "for nomination to
serve on the Local Health Council District XI, Monroe County".
If possible, we are respectfully requesting that this application be submitted to the
Commissioners for reappointment at the next County Commission Meeting.
Please feel free to contact Any Morello, Sr. Executive Assistant, at (305) 592-
1452, ext. 110 should you need any additional information.
Sincerely,
~~~
Marisel Losa
President & Chief Executive Officer
enclosure
8095 NW 12th Street, Suite 300 - Doral, FL 33126
Phone 305-592-1452 - Fax 305-592-0589 - Web www.healthcounciLorg - Email healthcouncil@healthcounciLorl[
Our Mission is to be the source of unbiased health data; quality program planning, management and evaluation; strong community
partnerships in MiamiDade and Monroe Counties; and targeted healthcare policy at the local, state, and national levels.
BOARD OF COUNTY COMMISSIONERS
AGENDA ITEM SUMMARY
Meeting Date: March 17.2010
Division: Countv Administrator
Bulk Item: Yes ---.X... No
Department: County Administrator
Staff Contact /Phone #: Abra Campo x, 4445
AGENDA ITEM WORDING: Approval of the appointment of Arianna Nesbit to the Health Council
of South Florida for a two year term in the category of Purchaser.
ITEM BACKGROUND: Ms, Nesbit will be replacing Kerry Shelby whose term expired 10/14/09,
PREVIOUS RELEVANT BOCC ACTION:
CONTRACT/AGREEMENT CHANGES:
STAFF RECOMMENDATIONS: Approval
TOTAL COST: ~ INDIRECT COST:
o
BUDGETED: Yes _No
DIFFERENTIAL OF LOCAL PREFERENCE:
COST TO COUNTY
o
SOURCE OF FUNDS:
REVENUE PRODUCING: Yes
AMOUNTPERMONTH_ Year
No
APPROVED BY: County Atty _ OMB/Purchasing _ Risk Management _
DOCUMENTATION:
Included X
Not Required_
DISPOSITION:
AGENDA ITEM #
Revised 7/09
Officers
Albert Collazo
Chair
Jose Perdomo, M,H.5,A, J.D,
Vice Chair
Ed Rosasco, FACHE
Treasurer
Debra S, Walker, Ph,D,
Secretary
Fermin Leguen, M,D,
Member-at-large
Board Members
Kim Bassett
Melvyn Fletcher, M,D" F,AAP,
Pascal Goldschmidt, M,D,
Rev, Dr. Ted Greer, Jr.
Nelson Lazo
Kerry Shelby, C,PA
Fred Stock, M.5,W" LN,HA
Honorary Board Member
Hon, Carlos Alvarez
Mayor, Miami-Dade County
President & CEO
Marisel Losa, M,H.5,A
An Equal
Opportunity
Employer
HCSF
11".11111 C,\lIrl< il ,'f 'S,\Ulll fk'ridd. Irl<.
March 5, 2010
Roman Gastesi
Administrator
Monroe County
1100 Simonton Street
Key West, FL 33040
Dear Mr. Gastesi:
The Health Council of South Florida Inc. is pleased to request the appointment of
Arianna Nesbitt to the Board of Directors in the category of Purchaser. The term
of the current Purchaser appointee, Kerry Shelby, has expired. Currently, Mr.
Shelby is not eligible for reappointment as he has reached the maximum of eight
years of service. The appointment term for Ms. Nesbitt is two years.
Ms. Nesbitt is the CEO of the Florida Keys Healthy Start Coalition. The Council's
Nominating Committee convened to review applications in accordance with the
Council's Bylaws and recommends the appointment of Ms. Nesbitt to the Council's
Board of Directors. A resume accompanies the application form, "for nomination to
serve on the Local Health Council District XI, Monroe County".
If possible, we are respectfully requesting that this application be submitted to the
Commissioners for appointment at the next County Commission Meeting.
Please feel free to contact Any Morello, Sr. Executive Assistant, at (305) 592-
1452, ext. 110 should you need any additional information.
Sincerely,
~~~
Marisel Losa
President & Chief Executive Officer
enclosure
8095 NW 12th Street, Suite 300 - Doral, FL 33126
Phone 305-592-1452 - Fax 305-592-0589 - Web www.healthcounciLorg - Email healthcouncil@healthcounciLorl[
Our Mission is to be the source of unbiased health data; quality program planning, management and evaluation; strong community
partnerships in MiamiDade and Monroe Counties; and targeted healthcare policy at the local, state, and national levels.
CANDIDATE FOR NOMINATION TO SERVE ON THE LOCAL HEALTH COUNCIL
DISTRICT XI, MONROE COUNTY
NAME _ \A( \ 6.f)()'c-,-- \\JeSDt+f-
BUSINESS ADDRESS'PC ;t^C:::t. {O\\ cole
(S[r~t)
t<f "I \~~S~-- F' L :"'~i.i~/ll
I (City, Slale ZIp Code)
RESIDENCE ADDRESS ll) 7C(~ C\,,,-\\( 0 ,Jc~{ ( CW'( k
(Streel)
~"'\t H,'f'HY\Et t,.l '>( l <Ke"1 I rL ?-2i;lh;)
"-~ (city, Stale Zip Code)
TEL ?rG,,"(~q3 .- <rY-\~
FAX2 l'--.,c'"\,t"J ,c'.' c:::.)t J-.:\'
I ) .' ".J" (,,')('\ .~j . ?' }I,. - ., ::1'
TEL"";, ~."j (i;"~?) 'cn:~)
FAX
MALE _ FEMALE l BLACK _ CAUCASIAN.JL- LATIN _ AGE $0 OR OlDER_
TYPE OF SEAT: PURCHASER + : PROVIDER _; CONSUMER_
EMPLOYER '.".~ '''''~. C . '"I r'i I' I
'." --", :':) +. 'J ",; \cAt ,) ("k"'~<q- '':' .-"~o L I -'. t Cr~ n"
NATURE OF BUSINESS/PROFESsh~)N j...,\:....\-' \1)/ ~ \ lei ;C""\ ~{~ \'\\\L\ I Xt"(;~ Y'U \0..J-'*, lj: L)t.C/)
/" " ",' - ~ '-".) \ ,..) ,.J r -, r l
IF CORPORA TION, INDICATE TITLE & DUTJES ,-,,-.\ () l t ~ ,(' (i "i t" (" -'. 1"Y Y t. \ \ ~ 'lJl '\(> i.:.:n'"t:;.
II \:j cl~, -\, c n ,\( ( V n , led, \'q ,((:0 ( I' ~) , IlL, dlifcl' '. ;'~h".' ~:\ Ie
'~)1t~\ t'"\n\\(\c)) (\n'\'\"fcr -t- ("\(>~~,_Y\i\.ilt) \..V)\IC. ~-e\( :":\'lry-\) ( ,
PERTINENT BIOGRAPHICAL INFORMATION (Resume or Curriculum Vitae may be attached)
,. j A C (~t! j~->R_, :s.c~.Q C"}. '~V':~~ C l,,''{~,. (~
I, (candidate's nameJ. .. )\\~~ (\ \t.' (\2 )\')'\ ~,,\ , a citizen of
the United Stales, ana a du y qualified elector of Monroe County, would, if appointed, be willing and able to
pi.!lcharge the responsibilities and functions of a member of the Local Health Council. r declare that I do not serve
" ~n\\nolhef board, agency ~ \ d~S0 ~~o~Po~er;eate~ and/or funded by the Monroe COlJ~~ ~~m~~~ion>
I Ci..~ f.", '\ / '...i'~' l,~ ~'-",',-, \, ", \C'''~ U(.\
t ~. " . f. 1,. ,; ,~) , ~ .........> ( .J
\.-'CA DID ''rE'S SIGNATURE ,-. bA E
F:\Common\80ARD\MEMBERS\AP PLI CA \FY2007-08\FonTls\Monroe Application 0403. DOC
Health Council of South Florida, Jne
8095 NW 12 Street, SVlte 300
Miami, FL 33176
305-592-1452-phone; 305-592-05B9-fax
ARIANNA N. NESBI1T
WORK HISTORY
Florida Keys Healthy Start Coalition, Inc.
Key West, Florida, August 2005 - Present
21st Century Grant Community Learning Center Campus Coordinator, Hearne, TX ISD
Hearne, Texas January - August 2005
Acting Executive Director, Mea Director, Unit Director, Boys & Girls Club of the Keys Mea, Inc.
Key West, Florida, October 1999 - November 2002
General Manager, MSean's Rendeveaux
lconium, .tI-iissouri, Summer 1997-1999,2003
Lead Teacher, Miss Pam's Kountry Kare
College Station, Texas, 1997-1999
KNOWLEDGE & SKILLS
Social Work & Youth Development
· Created and enhanced Boys & Girls Club program to attract youth from disadvantaged circumstances which
resulted in a tripling of the Club's active membership
· Daily Application of social skills, behavior modification, anger management, and crisis intervention training for
youth ages 5-18,
· Developed and implemented programs consisting of character development, leadership and citizenship training,
sex education, life skills, drug and gang prevention, arts & cultural activities, sports and ree. for youth ages 10-18
· Facilitated positive working relationships between Boys & Girls Club youth, parents/guardians, schools, sodal
services, and mental health agencies for a wrap around approach
Communication Skills
· Coordinated collaborative efforts among 13 local and state organizations to ensure the success of 3 grants
· Reinstated the Club newsletter to ensure better communication among the Club, parents, and the community
· Created a policy and procedures handbook as well as an employee hand book for the Club
· Spoke at numerous functions on behalf of the youth and the Club
Leadership & Creative Skills
· Inspired an organization that was over $15,000 in debt to believe in its mission, to make big changes, and left
them with a solid $375K working budget
· Maximized limited building resources to ensure safety, health, education, and overall satisfaction of staff and
clients
· Developed numerous fund raising events which made the Club the premiere youth organization in the
community
Not-For-Profit Skills & Knowledge
· Developed mission statement, by-laws, board operating procedures, staff development program, as well as staff
training programs
· Worked with board development issues, board building, and a creation of a board handbook
· Experience with community impact studies, book-keeping, accounting, grant management, strategic planning,
needs assessments, feasibility studies, annual fundraismg events, and capital campaigns
1078 Calico Jack Circle, Summerland Key, FL 33042
(M) 305-923-9125 ariannaag98@yahoo.com
ARIANNAN. NESBITT
Management & Financial Skills
· Researched, wrote, and implemented with collaboration with other organizations over 25 grants and 15 mini-
grants totaling over $2,500,000
. Hired, trained, and managed over 45 staff
· Developed and implemented budgets, contracts, tracking programs, services to clients, impact studies, and
financial management systems
EDUCATION
FLORIDA OUTREACH CHILDBIRTH EDUCATOR PROGRAM, Key West, FL
Childbirth Educator Certification, 2006
CAPPA,INC, Atlanta, GA
Labor Doula Certification, 2006
TEXAS A&M UNIVERSITY, College Station, TX
George Bush School Government and Public Service
2004 Masters of Public Service Administration, Youth Nonprofit Management Focus
Recipient of the Public Service Award FaIl 2004
TEXAS DEPARTMENT OF FAMILY AND PROTECTIVE SERVICES, CoIlege Station, TX
Pride Class Foster and Adoptive Parent Training, 2004
NATIONAL FOSTER PARENT ASSOCIATION, Orlando, FL
National Conference Including Abuse and GLBTQ Training, 2004
TEXAS A&M UNIVERSITY, CoIlege Station, TX
Bachelor of Science }..gricultural Economics, 1998
DEPARTMENT OF EDUCATION, Washington nc.
Associates of Child Development, 2000
NATIONAL ASSOCIATION FOR THE EDUCATION OF YOUNG CHILDREN
Local Conference, 2000,2001, and 2002
National Conference, 2000
BOYS AND GIRLS CLUBS OF AMERICA
B&GC i\1iddle Managers Track Training, 2001
Florida's B&GC il.Il Staff Conference, 2000
Youth Development Program South East Conference, 2001
B&GC Practice, Week of Youth Development Training, 2000
1078 Calico Jack Circle, Summerland Key, FL 33042
(M) 305-923-9125 ariannaag98@yahoo.com
ACTIVITIES
ARIANNA N. NESBITT
Womankind, Inc. Key West, Florida
Board Member 2007 - 2008
Key West Woman's Club, Key West, Florida
Member, 2006 - Present
YMCA Key West, Inc. Key West, Florida
Board Member, 2006 - 2008
United Way ofthe Brazos Valley, College Station and Bryan, Texas
Organizational Recommendations and Development Strategies for the Success By Six Program, 2004
Public Service Organization, Bush School, College Station, Texas
Social and Economic Impact Study Project Manager for the local United Way, 2003 - 2004
Grants Writing Committee and One Day Service Projects Committee Member 2003-2004
Carver Early Learning Elementary School, Bryan, Texas
Mentor and Reader to Emotionally and Behaviorally Disturbed Youth, 2003-2004
Habitat For Humanity, Key West, Florida, and Bryan Texas
Assisted in Building Homes for Families, 2001-2004
American Cancer Society, Relay For Life, Key West, Florida
Team Captain: Fundraising and Team Organization of Boys & Girls Club Teens 1999-2002
1078 Calico Jack Circle, Summerland Key, FL 33042
(M) 305-923-9125 ariannaag98@yahoo.com
Reply to: West Palm Beach
MEMORANDUM
TO:
Roman Gastesi
FROM:
Erin Deady
DATE:
February 20, 2010
SUBJECT:
Numeric Nutrient Criteria
EP A Rulemaking and DEP Reclassification Rulemaking
This memorandum is a summary on the status of efforts by the U.S. Environmental
Protection Agency's ("EPA") to promulgate numeric nutrient criteria for water quality standards in
Florida. I am providing this memorandum pursuant to your request, discussing some of the impacts
and considerations for Monroe County with this rule. This memorandum is not meant to be final,
but introductory to answer some of the questions you have posed to me concerning the effect of this
rule on the County. As you are aware, we have been working on this issue for quite some time and
we are working with several public and private clients on the rule development. One of our primary
clients is the Florida Association of Special Districts and they obviously have great interest in
monitoring the rule and trying to influence its outcome.
This memorandum cannot be considered comprehensive in terms of the impact of the rule
because we have not reviewed any information concerning the actual performance or
implementation success of the County's overall wastewater/stormwater planning and
implementation efforts to date. This is the best information we have on the rule at this point,
however, the rule development effort is still evolving as you know and the information contained
within this memorandum is likely to change.
I. Water Quality requirements for Monroe County
Section 6 of Chapter 99-395, Laws of Florida (L.O.F.), requires all new sewage facilities in
Monroe County, including onsite sewage treatment and disposal systems ("OSTDS"), permitted
after June 18, 1999 to comply with the following standards by July 1, 2010:
5/ ,'1/1 0
O.S
Roman Gastesi
March 11, 2010
Page 2
Table 1: B...~T aJ~d A\Vf Standards Section 6 of cba ter 99-395, L,..O,F.)
Effluent (treated ~\i'a5te,vater) concentration in nUlligral~ls pel'liter BOD TSS TN TP
(1 /L) as anllual a,-era e (n /1 is e 11al to lart er l~Ullion
B.t.~T !tallduds appl~~ to L'lcilities ,tvidl design capacitie~ less dun 100,000 10 10 10
Otls/dal'" (2:ellerall\"~ OS1DS and '~)acka2'e lants:::').
.~ \\[ stallcLuds apply to facilicies \\.;.th design capacities equal to or greater 5 5 3
than 100:;000 gallons/ cL1.y (COll111111t1ity and cen,:!al \'t'"ast~'t.ater tre,atnlent
srs re1l1S )
BOD = Bioche1l'ical Oxygen Demand; TSS = Total s1lspended solids; TN = Total nltLogell; TP = Total phosphorus.
(Section 6 also prohibited new surface water discharges of wastewater and required
elimination of existing surface water discharges by July 1, 2006.). These requirements apply to the
owners of the facilities and OSTDS systems, whether they are local governments, public or private
utilities, other private entities (restaurants, stores, condominiums, etc.), or individual homeowners.
The Florida Department of Environmental Protection ("DEP") has identified certain water
quality "impairments" in the Keys that are consistent with the impacts associated with inadequately
treated and managed wastewater, specifically nutrients and bacteria, including fecal coliform.
Typically after identifying an impaired waterbody a total maximum daily load ("TMDL") would be
established requiring pollutant load reductions to resolve the problems. In lieu of a TMDL for
Monroe County, a Reasonable Assurance Plan was developed by DEP to set forth and accelerate the
actions that have been taken or are planned to be taken to reduce nutrient loadings to near shore
waters throughout the County so that water quality standards are met and beneficial uses are
restored. The plan has been reviewed and accepted by DEP and sent to the United States
Environmental Protection Agency ("EP A") for review and comment in February 2009. However,
our best information as of last week supplied by DEP is that no action has been taken yet by EP A,
meaning that the Reasonable Assurance Plan ("RAP") is not an accepted alternative to establishing
TMDLs under the Clean Water Act.
Outstanding Florida Waters are afforded a higher degree of protection through
antidegradation permitting requirements for discharges into such waters. But canals in Monroe
County are not part of the Outstanding Florida Waters designation and more than 200 canals and
access channels were dredged from the 1950s-1970s. Although Monroe County's canals are not
Outstanding Florida Waters, DEP has specifically designated them an "area of concern" by
imposing the stringent standards noted above. These standards are also included in Senate Bill
2018 with a new December 31, 2015 compliance deadline.
2
Roman Gastesi
March 11,2010
Page 3
II. Numeric Nutrient Water Quality Standards
A. EP A Rule Development Background
Florida currently employs narrative nutrient standards to guide the management and
protection of its surface waters; standards that were previously reviewed and approved by the EP A.
In July of 2008, several environmental groups initiated a lawsuit to force EP A to establish numeric
nutrient criteria (versus narrative standards) for all of Florida's surface waters. By letter dated
January 14, 2009, the EPA notified the DEP that numeric water quality standards for nutrients
would be necessary for the State to comply with the requirements of the Clean Water Act ("CW A").
The State of Florida's efforts to establish numeric standards had been ongoing for at least seven
yearsl. With a lawsuit in the background, the efforts to establish numeric criteria were accelerated
and became litigation driven.
On August 19, 2009, EPA settled the lawsuit by entering into a consent decree with the
environmental groups whereby EP A agreed to establish numeric nutrient criteria for all lakes,
streams, and canals by January 2010, to be implemented by October 2010. Criteria for coastal
waters will be established by January 2011 and implemented by October 2011.
On January 14, 2010, EPA published for public consumption, a draft rule establishing
numeric nutrient criteria for Florida's flowing waters and lakes, which is scheduled to become
effective by October of this year. In February, EPA conducted three public workshops in
Tallahassee, Orlando, and West Palm Beach. All three public workshops began with a thirty minute
overview of the proposed numeric criteria by EP A, followed by hours of public comment. In
addition to the public comments at the workshops, EP A will also accept written comments, which
are now due by April 28, 2010. This deadline was just extended in yesterday's version of the
Federal Register.
EPA's proposed rule sets forth "in-stream" numeric nutrient water quality standards for
nitrogen, phosphorus, and chlorophyll a (as a response variable) for lakes, streams, and canals in
Florida. With regard to flowing waters, EP A utilized a regional-referenced based approach similar
to the methodology used by DEP to statistically derive criteria for flowing waters. For streams, the
threshold for total nitrogen and total phosphorus will be the 75th percentile of reference waterbody
concentrations. Concentration levels higher than 75th percentile of the regional waters selected to
establish the regional criteria will not be considered protective of designated uses. EP A used the
same reference- based approach in determining numeric nutrient criteria for South Florida canals;
I In May of 2002, DEP submitted a Draft Numeric Nutrient Criteria Development Plan to EP A. The 2002 plan was
revised in December of 2003 to respond to EP A comments. In July of 2004, the EP A and DEP entered into a mutual
agreement on the numeric criteria development plan.
3
Roman Gastesi
March 11,2010
Page 4
however, the canals selected to establish the criteria were predominately ground water feed canals
that were deemed to be meeting Class III designated uses. Essentially, EP A only selected those
canals that most mimic natural systems with regards habitat and uses. EPA's proposed water
quality standards for South Florida canals are far more protective than the standards noted in the
table above and are as follows:
C~hlorOl)hyll (I Total PIIOSpllOlllS (TP) Total Nitrogell (TN)
(~lg./L) a (lllg/L) a, b (lng/L) a
C~al1als 4.0 0.042 1.6
a Concentration values are based on annual geometric mean not to be slUpassed more than once in a t1u'ee-
year period. In addition. the long-tenll average of annual geometric mean values shall not SlUpass the listed
concentration values. (Dmation = arumal: Frequency = not to be slU])assed more than once in a t1u'ee-year
period or as a long-tellll average).
b Applies to all canals within the Florida Department ofEnviroI1111ental Protection's South Florida
bioregioll, w-ith the exception of canals \vithul tIle Everglades Protection .4.rea (EvP A) \vhere the TP
criterion of 0.010 lllg/L Cl1111ently applies.
EPA's proposed rule does not specifically limit the proposed criteria to freshwater systems,
but it is believed that the standards will apply to waterbody identification numbers ("WBIDs") that
are predominantly fresh waters as defined by Rule 62-302.200, F.A.C. DEP defines.
"predominantly fresh waters" as those "surface waters in which the chloride concentration at the
surface is less than to 1,500 milligrams per liter. For those WBIDs that have surface concentrations
greater or equal to 1,500 milligrams per liter for chloride, they would be considered predominantly
marine waters2.
Regardless of the fact that the standards currently being proposed will only apply to
predominately fresh waters, it is important to note that, in addition to in-stream protection criteria,
EP A is also proposing interim downstream protection values ("DPV") to protect downstream lakes
and estuaries. EPA proposed a "downstream protection overlay" which will further reduce EPA's
regional in-stream numbers (lower than those listed above) based on the perceived sensitivity of
downstream waters to nutrient loading. This is probably the most critical issue for Monroe County
to monitor during this part of the rulemaking effort. Simply stated, EPA's proposed DPVs for
estuarine waters for total nitrogen is established by determining the mid-point between the
estimated nutrient loadings without human sources of nutrients and the estimated current loadings.
Once the DPV for a given estuary is established, load allocations for all stream and canal reaches
(and/or WBIDs) within the estuary's watershed are set by implementing a complex formula(s) to
estimate the nutrient loading to downstream waters. The estimated loading will be used to set
2 In those cases where there is significant variation in salinity (sometimes it is marine water and sometimes it is fresh
water), the WElD will be assessed based on the salinity of the sample. It should also be noted that a given waterbody
can have more than one WBID and that WElD boundaries are subject to change.
4
Roman Gastesi
March 11,2010
Page 5
revised total nutrient criteria for in-stream protection, which, in most cases, be will lower than the
regional criteria. Simply stated, the closer a reach (and/or WBID) is to a given estuary, the more
protective the DPV will be and the likelihood of EP A establishing lower in-stream criteria is greatly
increased. It should be noted that it does not appear a similar downstream protection overlay for
estuaries has yet been developed for total phosphorous; however, it is likely one will be included in
the final rule.
Interim DPVs aside, EPA is now currently developing numeric nutrient criteria for coastal
waters, which is scheduled to be officially proposed January 2011 and implemented October 2011.
Based on the DPV approach, it is anticipated that the estuarine criteria that will be implemented in
2011 will be at least as protective as the DPVs. Consequently, it is also anticipated that
predominately marine waters that feed into estuaries (directly or indirectly) will have numeric
nutrient criteria established that will be far more protective than those currently being proposed for
predominately fresh waters.
Consequently, EPA's approach is far more protective than previous DEP's approaches. For
example, DEP tested reference streams throughout the state that were considered the healthiest and
most preserved by both DEP and EP A in order to determine if they would attain the numeric criteria
proposed by EP A. DEP determined that up to 85% of the State's most pristine waters would fail
and be considered impaired when the DPVs were considered. It should be noted that DEP did not
consider one reach of any canal in South Florida to be "healthy and preserved" as to qualify for this
field study. It can therefore be safe to assume if85% of the State's most pristine streams would fail,
then almost all, if not all, of South Florida's canals would surely fail.
B. Issues Raised in the Rule Development Process
1. Arbitrary Science
Issues have been raised about the methodologies being employed by EP A to set the numeric
nutrient criteria both in Florida and nationally. EP A's methodologies have been questioned,
especially, when one considers DEP's evaluation whereby 85% of the State's most pristine waters
would fail. EP A methodologies have also come under attack from the regulated community and
EP A's own Science Advisory Board as being technically flawed. In particular, as noted above,
EP A did not select representative canals in South Florida to establish the proposed numeric nutrient
criteria for that region. South Florida canals are predominately surface water feed with nutrient
levels that are typically much higher than one would expect to find in a system that is predominately
ground water feed. By selecting canals that are groundwater feed, the numeric nutrient criteria for
canals is artificially overprotective and virtually impossible to meet as the criteria essentially
assumes little to no surface water loading of nutrients.
5
Roman Gastesi
March 11, 2010
Page 6
The DPVs also have come under attack as being unsound. EPA utilized the Spatially-
Referenced Regression on Watershed attributes ("SPARROW") model to derive the loading
allocations associated with the DPVs. The SPARROW model has been used by U.S. Geological
Survey to assess large scale watersheds like the Mississippi River basin and Chesapeake Bay
watershed. Presumably, due to the time constraints, EP A utilized the SPARROW model without
recalibrating it to assess smaller watersheds like the eco-regions in Florida, which are being used to
establish regional numeric criteria. Consequentially, the application of the SPARROW model to
derive the DPV loading and establish permanent numeric criteria for coastal waters in 2011 has
been attacked as being unsound and arbitrary science.
Notably, the principal concern over EPA's science has been that EPA has not been able to
demonstrate a causal relationship between the level of nutrients in a given waterbody and the
waterbody's biological health. EP A has admitted to this limitation, however, has responded that
even though they cannot demonstrate a connection, "it must surely be there",
11. Economic Feasibility
The economic impacts that local governments and facility owners will have to bear in order
to even attempt compliance with these standards are astronomical. The Florida Stormwater
Association has estimated costs exceeding $75 Billion3 statewide. Some utilities have stated rate
increases up to $700.00 per household. These costs do not factor in the land acquisition cost of
residential and commercial properties needed to construct water treatment areas/facilities. The
economic impacts are further augmented by the fact that the proposed standards could very well be
unattainable even with billions of dollars of investment.
11l. National Pollution Discharge Elimination System Permitting
The establishment of numeric nutrient criteria will significantly change the National
Pollution Discharge Elimination System Permitting ("NPDES") permitting process. Currently,
Florida conducts site-specific assessment of the proposed discharges for a project to determine
whether the proposed action will cause an "imbalance". By having preset nutrient benchmarks, in
theory, NPDES permits should be reviewed in a timelier manner; however, there will no project
specific analysis. The issuance of an NPDES permit will be reduced to a simple comparison of
proposed discharge numbers versus benchmark numbers, potentially leaving no flexibility to
3 See Florida Stormwater Association's general comment letter on EPA's proposed criteria, which is attached for your
review. The $75 Billion statewide estimate is based on the cost of compliance for only stormwater capital costs that
would be necessary (not including wastewater).
6
Roman Gastesi
March 11, 2010
Page 7
account for other variables. This will directly impact an applicant's ability to renew the necessary
NPDES permits, creating potentially more enforcement issues.
IV. Effect on "Impaired Waters"
As previously noted, DEP is proposing a RAP to address the nutrient problems in the
County. However, EP A has not approved the RAP as conveyed to us by DEP late last week.
Considering that the RAP sets forth standards that are not as I!rotective as EP A's proposed
criteria4, it is likely that the RAP will have to be either revised to be consistent with EPA's criteria
or be submitted as a Site Specific Alternative Criteria ("SSAC") for nutrient criteria. If the RAP is
not approved or a SSAC is not implemented, an alternative might be that EPA require a TMDL to
be established for all impaired waters. It should also be noted that while Senate Bill 2018 appears
to be codifying the standards set forth in the RAP and establishing a December 31, 2015,
compliance deadline. The 2015 deadline will be rendered meaningless by EP A's proposed
standards which will be implemented by October 2010 for fresh waters and 2011 for marine
waters.s IfEPA's final criteria are more protective than the RAP's, DEP could propose the RAP's
less protective standards as "interim standards", while Monroe County works toward complying
with EP A's standards. Another approach might be to establish the RAP's criteria as a SSAC
although there are compliance, process and cost issues associated with that approach also.
The costs associated with establishing a SSAC or a TMDL are significant. As outlined in
the chart below, a SSAC costs $15,000 (per individual parameter, like phosphorus, nitrogen, etc.)
4 The RAP is based on achieving Total Phosphorus levels of I mglL and Total Nitrogen levels of 10 mglL (3 mglL for
AWT standards). As noted in the figure above, EPA is proposing a Total Phosphorus limit of .042 mglL and Total
Nitrogen of 1.6 nlg/L for predominately fresh water canals.
5 Objective E of the October 2009, Monroe County Area of Critical State Concern De-designation Report: All of the
Year 10 objectives which remain outstanding are related to implementation of the Monroe County Sanitary Wastewater
Master Plan. The County has made substantial effort in recent years and particularly in recent months to secure funding
for the implementation and completion of the wastewater project, not just in unincorporated Monroe County but in the
Florida Keys. The Regional Wastewater Partnership which includes Monroe County, the Florida Keys Aqueduct
Authority, the Key Largo Wastewater Treatment District, the City of Key West, Bahia Honda State Park, the City of
Marathon, the City of Key Colony Beach, the City of Layton, the Village of Islamorada, and the North Key Largo
Utility Corporation remain committed to meeting the intent of the statutory mandate to provide A WT/BAT to the
citizenry of Monroe County.
Monroe County has not completed the implementation of the Sanitary Wastewater Master Plan, the Monroe County
Stormwater Management Plan, nor the acquisition of all lands identified for acquisition in the Land Management and
Acquisition Master Plan. The County does have substantial investments in the completion of these plans and continues
to strive toward implementation and completion with the State of Florida as our partner. However, the direct language
of State Statute makes it very difficult to determine substantial progress has not been made in the implementation of the
10 Year Work Program.
7
Roman Gastesi
March 11,2010
Page 8
for the application fee6 and that does not include the costs associated with the required "Use
Attainability Assessment", monitoring data, and any other reports that might be necessary to secure
the SSAC. The difficulty in establishing a SSAC in South Florida is further augmented by the fact
that there is no established "Stream Condition Index for South Florida". Therefore, an applicant in
South Florida will have to expend more time and money in establishing a SSAC than in other parts
of the State. Based on our experience with SSACs and TMDLs, Monroe County could expect
approximately $150,000.00 minimum to establish a SSAC for one Darameter in one waterbody7.
Our experience also suggests that the establishment of a TMDL can cost up to $800,000.00, more if
the system is complex. The cost estimates associated with establishing a SSAC or TMDL do not
include the costs associated with implementation, which can be expected to be much higher. See
table on the following page.
Criteria Alternatives Costs Notes
SSAC $15,000.00 application fee per Up to $150..000.00 when the
parameter costs associated with the
require Use Attainability
Assessments, monitoring and
other studies are included.
Also would require a minimum
of3 years of data
TMDL Up to $800,000.00
As previously stated, it should be noted that the standards for predominately marine water
canals will likely be much more protective based on EPA's approach with the DPVs for
predominantly fresh water. Again, the DPVs are designed to protect downstream waters,
specifically estuaries. This additional concern is because DPVs become more protective/stringent
the closer a WBID is to an estuary. Considering most of Monroe County's "marine" canals are in
close proximity to coastal waters, it is safe to assume EP A will be proposing in 2011 criteria for
those marine waters that will be more stringent than currently being proposed for fresh waters.
Consequently, Monroe County would have to evaluate the performance from implementing its
wastewater (and stormwater) projects to achieve much more protective standards versus attempting
to establish SSACs for every one of the affected canals for each ~arameter. The alternative is that
every canal would be considered "impaired" under EP A's proposed criteria and TMDL's would be
established for every canal at a significant cost to Monroe County.
6 See 62-4.050 (4)(p )2.( q) 1., F .A.C.
7 SSACs are by definition "site specific" so it may be difficult to establish a global SSAC for all of Monroe County's
canals in one application.
8
Roman Gastesi
March 11, 2010
Page 9
v. Permitting
The imposition of the proposed numeric criteria in South Florida could result in a majority
of the region's utilities, water treatment, water supply, and water control facilities being out of
compliance with these new regulatory standards and could have significant adverse implications on
the ability to operate and maintain those facilities. As a condition of issuance of any state-issued
Environmental Resource Permit or U.S. Army Corps of Engineers permit, the applicant must
demonstrate compliance with state water quality standards including the new numeric nutrient
criteria. Therefore, these facilities may not be able to obtain the necessary state and federal
authorizations to continue their operations and service the public welfare.
C. Implementation
EP A has acknowledged that a compliance schedule would be needed in order to implement
the proposed criteria. EPA is recommending a process where the state would propose (subject to
EP A approval) "interim criteria" to allow attainment of the designated use over phased time
periods. The idea is that as a waterbody improves over time and the interim criteria levels would
move closer to the targeted numeric nutrient criteria set by EP A. However, it is not clear that DEP
would be willing or is in a position to establish interim criteria and DEP could require a SSAC
application instead. In addition to the cost of establishing a SSAC as previously discussed, one
must consider that a SSAC: (1) can take between 18 months to 3 years to finalize; (2) require DEP
and EP A approval; (3) there is no "Stream Condition Index" for South Florida, which is the primary
tool contemplated for the SSAC process; and (4) requires several detailed and costly biological
studies along 'with at least 3 years of data.
Even if DEP does develop interim criteria that is timely approved by EP A, local
governments will have to immediately secure financing and expend capital costs to begin any
compliance initiative because as you know, the planning and permitting for that takes years to
complete. Consequently, local governments like Monroe County will experience immediate
budgetary impacts.
Recently constructed facilities designed to comply with the water quality standards set by
the State pursuant to Chapter 99-395, Laws of Florida (and the RAP) may not be entirely effective
in complying with the new water quality standards. Some of these facilities may need to be re-
tooled to satisfy EP A's proposed standards; however, the costs associated with initially constructing
the new or separate facilities are also a factor to consider.
III. Reclassification of Florida's Surface Waters
In response to pressure being exerted by environmental groups and a select group of cities
and counties, DEP has continued its efforts at the reclassification of Florida's surface waters. The
9
Roman Gastesi
March 11, 2010
Page 10
principal problem with establishing numeric criteria for canal systems is that Florida's current
classification of waters did not account for "artificial" systems. Instead, Florida law has a default,
"one size fits all" class whereby a majority of Florida's natural and artificial flowing waters (canals)
are lumped together as Class III waters.
This necessarily meant that uses of artificial canals would, from a regulatory perspective, be
expected to maintain the same designated uses expected in a natural system. It was this failure to
acknowledge the biological differences between canals and natural systems that was the catalyst for
reclassifying Florida's waters to portray a more accurate picture of the aquatic universe. Initially,
DEP proposed a draft rule that included eight human uses and four aquatic uses that more
accurately portrayed the diversity of Florida's surface waters. In an earlier draft of the
reclassification rule, Monroe County was designated "Human Use-2" defined as "Protection of
shellfish harvesting for human consumption, fish consumption, and full body contact". Protection of
shellfish consumption involves maintaining a level of water quality that will prevent unpalatable
.flavor or accumulation of substances harmful to human health in shellfish tissue.
Apparently, in response to comments received by those involved in the reclassification rule
development, DEP has significantly backtracked by proposing to only add one subclass to the "one-
size fits all" Class III designation. DEP is now proposing to create one sub-class for Class III
waters (Class III-Limited). The only difference between Class III and Class III-Limited is that the
Class III-Limited classification allows for limited recreation and limited fish and wildlife
populations whereas Class III is not limited in those uses.
In order to qualify for this proposed new sub-class, Class III-Limited, a waterbody would
have to have been dredged wholly from uplands or be designated as "altered waterbodies" that were
dredged before November 28, 1975. In addition, any applicant seeking to reclassify a waterbody to
Class III-Limited would have to provide a "Use Attainability Analysis" to demonstrate the
designated use that is to be removed is in fact unattainable. What is especially troubling is that the
Use Attainability Analysis must be a full study to determine all potential attainable uses (in a
perfect world) and not simply to prove a particular use is not attainable8. Also, an applicant will
have to provide Site Specific Alternative Criteria for at least one of eight parameters: nutrients
(including nutrient response variables), bacteria, dissolved oxygen, alkalinity, specific conductance,
transparency, turbidity, or PH.
At present, since Monroe County is a designated Class II water body, this newest proposed
change does not appear to impact the County. But the reclassification rule development effort
should be monitored.
8 When determining the potential uses of a waterbody, the Use Attainability Assessment does not consider human
caused conditions except for the physical characteristics of a canal. Consequently, stormwater runoff and other
discharges that inevitably impact the biological and use potential of a canal are not factored. Essentially, a significantly
disturbed canal's designated uses are determined as if the discharges/human conditions do not exist.
10
Roman Gastesi
March 11, 2010
Page 11
IV. Impact to Monroe County
A. Wastewater Plan
According to the Wastewater Master Plan there were 246 small wastewater treatment plants
(WWTPs) throughout the Keys. The Plan states there are (were) 23,000 onsite wastewater
treatment systems in operation and approximately 2,800 early cesspools. Previous cost estimates
for implementation of wastewater treatment options will likely be "higher" than originally
anticipated ifmore stringent standards are adopted.9
B. 2010 Legislative Issues
As previously noted, Senate Bill 2018 essentially codifies the standards set forth in the RAP
and gives Monroe County five more years to achieve compliance with water quality standards.
However, EPA's proposed numeric nutrient criteria may serve to render Senate Bill 2018
meaningless with regard to the standards and the compliance deadline. The state legislature cannot
trump the Clean Water Act or EP A regulations; therefore, if EP A's criteria are more protective, then
it will be EP A's criteria that will be the operative water quality standard. Also, compliance with
EP A's standards will not be influenced by Senate Bill 2018' s compliance deadlines. EP A's criteria
will become operative this October for fresh waters and by October 2011 for marine waters. While
EP A's proposed rule does contemplate a compliance schedule, such a phased compliance approach
would require DEP to establish interim criteria. To date, DEP has not expressed any indication that
they would establish interim criteria, which would ultimately have to be approved by EP A. Instead,
DEP has indicated that the SSAC process would probably be used. Regardless, EPA's proposed
rule development has the potential to significantly render much of Senate Bill 2018 meaningless.
Senate Bill 2056, filed by Oelrich, states that the DEP is directed to contract with the
National Academy of Sciences for a review and evaluation of scientific and technological issues
related to the establishment of numeric nutrient criteria for surface waters in this state proposed by
the EP A. DEP must ensure that the review and evaluation provides opportunities for input from
scientists having expertise in nutrients and water quality and take into consideration such additional
scientific and technological factors that are necessary and appropriate to the successful
implementation of numeric nutrient criteria. The bill also requires DEP to report to the Legislature
and identify issues that must be addressed in order to implement an orderly process for nutrient
source control and abatement of nutrient enrichment and will achieve water quality standards.
9 Objective E of the October 2009, Monroe County Area of Critical State Concern De-designation Report: Obtain $80
million in bond financing secured by connection fees.
11
Roman Gastesi
March 11, 2()10
Page 12
c. (;rowth Management/Comprehensive Plan Implications
Finally, we have not completed an analysis yet on the Comprehensive Plan implications
recognizing that Section I63.3I80(13)(d), F.S., describes "financial feasibility" as a standard
adopted to make concurrency more predictable and local governments more accountable. Section
163.3164, F.S., has been amended to define the term "financial feasibility" as a local government
having sufficient revenues currently available or those revenues will be available from committed
funding sources for the first 3 years, or will be available from committed or planned funding
sources for years 4 and 5 of a 5 year capital improvement schedule. Given that the County is
seeking $80 million in bond financing to complete the Monroe County Sanitary Wastewater Master
Plan, it might be appropriate to begin reviewing the Plan, financing and implementation schedule in
light ofEPA's rulemaking efforts.
12