2nd Change Order 03/05/1997
MONROE COUNTY
ENGINEERING/ CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: ISLAMORADA/MARATHON LIBRARIES
CHANGE ORDER NO: 2
Total Previous Change Orders
Current Change Order
Original Contract Amount
Revised Contract Amount
$19.779.00
$7.964.00
$310.189.00
$337.932.00
Detailed description of change order and justification:
ON 10/18/9ti BOCC GRANTED APPROVAL OF CONTRACT WITH D.L. PORTER CONSTRUCTION.
INC. FOR THE ISLAMORADA/MARATHON LIBRARIES. ON 06/19/96 BOCC GRANTED APPROVAL
OF CHANGE ORDER #1 TO INCREASE THE PROJECT IN THE AMOUNT OF $19.779.00.
CONTRACT ALLOWS $750.00 FOR TESTING. ACTUAL COST FOR COMPLETE TESTING IS AN
ADDITIONAL $3392.00. THE INCREASE IS PRIMARILY DUE TO AN UNDERESTIMATED TESTING
ALLOWANCE BY THE ARCHITECT IN THE ORIGINAL BID SPECIFICATIONS. THE REMAININ~
CHANGES HESUL T FROM REQUESTS OF MODIFICATIONS FROM THE BUILDING DEPARTMENT
COUNTY BIOLOGIST. FIRE MARSHALL'S OFFICE. AND THE OWNER. TO IMPROVE THE OVERALL
PROJECT. THEREBY INCREASING THE CONTRACT PRICE FROM $329.968.00 TO $337.932.00.
CONTRACTOR: Q
D. L. Porte
ARCHITECT/ENGINEER:
Th mas E. Pope,
CONSTRUCTION MANAGER:
COUNTY ENGINEER
DIRECTOR OF PUBLIC WORKS
COUNTY ADMINISTRATOR:
CMD007-1I29/97
B
ISLAMORADA LIBRARY
CHANGE ORDER SHEDULE
Description Amount
Additional reinforcing in parapet wall 1,875.00
Substitute aluminum storm shutters with head & sill track 925.00
Cover existing window & trim out between buildings 547.00
Excess over sod allowance 1,300.00
Excess over testing allowance 3,392.00
Install gutter system from old bldg along new corridor 1,725.00
Transplant Gumbo Limbo trees 550.00
Unused landscape allowance (3,000.00)
Fim alarm panel with battery backup 1,475.00
Vertical bars omitted from filled cell masonry (300.00)
Undersized septic tank and drain field (400.00)
Existing entry doors not reversed (125.00)
7,964.00
CO_C HART. XLS