Loading...
2nd Change Order 03/05/1997 MONROE COUNTY ENGINEERING/ CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: ISLAMORADA/MARATHON LIBRARIES CHANGE ORDER NO: 2 Total Previous Change Orders Current Change Order Original Contract Amount Revised Contract Amount $19.779.00 $7.964.00 $310.189.00 $337.932.00 Detailed description of change order and justification: ON 10/18/9ti BOCC GRANTED APPROVAL OF CONTRACT WITH D.L. PORTER CONSTRUCTION. INC. FOR THE ISLAMORADA/MARATHON LIBRARIES. ON 06/19/96 BOCC GRANTED APPROVAL OF CHANGE ORDER #1 TO INCREASE THE PROJECT IN THE AMOUNT OF $19.779.00. CONTRACT ALLOWS $750.00 FOR TESTING. ACTUAL COST FOR COMPLETE TESTING IS AN ADDITIONAL $3392.00. THE INCREASE IS PRIMARILY DUE TO AN UNDERESTIMATED TESTING ALLOWANCE BY THE ARCHITECT IN THE ORIGINAL BID SPECIFICATIONS. THE REMAININ~ CHANGES HESUL T FROM REQUESTS OF MODIFICATIONS FROM THE BUILDING DEPARTMENT COUNTY BIOLOGIST. FIRE MARSHALL'S OFFICE. AND THE OWNER. TO IMPROVE THE OVERALL PROJECT. THEREBY INCREASING THE CONTRACT PRICE FROM $329.968.00 TO $337.932.00. CONTRACTOR: Q D. L. Porte ARCHITECT/ENGINEER: Th mas E. Pope, CONSTRUCTION MANAGER: COUNTY ENGINEER DIRECTOR OF PUBLIC WORKS COUNTY ADMINISTRATOR: CMD007-1I29/97 B ISLAMORADA LIBRARY CHANGE ORDER SHEDULE Description Amount Additional reinforcing in parapet wall 1,875.00 Substitute aluminum storm shutters with head & sill track 925.00 Cover existing window & trim out between buildings 547.00 Excess over sod allowance 1,300.00 Excess over testing allowance 3,392.00 Install gutter system from old bldg along new corridor 1,725.00 Transplant Gumbo Limbo trees 550.00 Unused landscape allowance (3,000.00) Fim alarm panel with battery backup 1,475.00 Vertical bars omitted from filled cell masonry (300.00) Undersized septic tank and drain field (400.00) Existing entry doors not reversed (125.00) 7,964.00 CO_C HART. XLS