Loading...
Change Order No. 1 CHANGE ORDER NO. BOCC APPROVED 1/8/92 1 Job No. 04-004.90 Project Title: Roadway Improvements Key West Roads I Bertha Street Monroe County, Florida Contractor: The Brewer Co. of Florid~; Inc. Contract Date: April 3, 1991 To: The Brewer Company of Florida, Inc. 9801 N.W. 106 Street Miami, FL 33178 You are directed to make the changes noted below in the subject contract: . - ~\ By: \.U.~.o~. ~~ Chairman, Monroe County Board of County Commissioners Attest: 4,g~. R/L~t~ Date: /- 8... ,~ Approved By: r<~/t.~ ~-~ ... . Approved ~o 7orrec. tness and Form I ( UL- By: . Attorney for Monroe County Nature of the Change: (See Attachment "A") A~I'ROvtr5 BY: ::' ~L1~ W-O-R~ DJRLClG.i Iff /91.-- \.0 -'1 :"-0 -'l ~ .- j ~~ ,~ -. 'Jl ....-- co J -, i ., >..~J The changes result in the following adjustment of Contract Price and Time: Contract Price Prior to this Change Order: Net (Increase) ttL:rilQSe) Resulting from this Change Order: Current Contract Price Including this Change Order: Contract Time Prior to this Change Order: Net (Increase) (Decrease) Resulting from this Change Order: Current Contract Time Including this Change Order: Current Contract Completion Date: $189,034.65 24,011.36 $213,.046.01 120 calendar days -0- 120 calendar days Date: .JJ~<. ~ I ~"'I , Prepared by: C. Robert Roqers, Jr. Post, Buckley, Schuh &: Jernigan, Inc. as Monroe County Consulting Engineers By: Attest. Changes are Ac~epted: ~ '~~ Date: Title: Contractor's Representative U~~ ~ Attachment "A" PROPOSED ITEMS FOR CHANGE ORDER NO. 1 TO EXISTING MASTER CONSTRUCTION CONTRACT BETWEEN MONROE COUNTY AND THE BREWER COMPANY OF FLORIDA, INC., DATED APRIL 3, 1991 FOR ROADWAY. IMPROVEMENTS, KEY WEST ROADS I, BERTHA STREET, MONROE COUNTY, FLORIDA. PROJECT NO. 04-004.90 The changes are the results of requirements by the State of Florida Department of Environmental Regulation in order to obtain permits for the stormwater injection wells. Amount Item No. Description Quantity Unit Price 10 Pavement Markings Traffic Separation (Thermo.) Delete 1 Ea. $ 500.00 11 Storm Drain Pipe (12" RCP) Add 26 L.F. 40.00 12 Swale Catch Basin Add 1 Ea. 1,900.00 13 Interceptor Catch Basin Delete 13 Ea. 3,700.00 14 Injection Well Delete 13 Ea. 1,320.00 13-R Revised Interceptor Catch Basin Add 11 Ea. 5,564.16 14-R Revised Injection Well Add 11 Ea. 2,329.60 TOTAL AMOUNT PROPOSED CHANGE ORDER NO. 1 $ -(500.00) 1,040.00 1,900.00 -( 48, 100.0~ -(17,160.00 61,205.7 25,625.60 $ 24,011.36