Change Order No. 1
p
B
Post, Buckle~ Schuh & Jernigan, Inc.
s
J
CONSULTING ENGINEERS and PLANNERS
10 PALMS PLAZA, HOMESTEAD, FLORIDA 33030-6094 . 305/248-4750 . TElEX 808435
July 28, 1983
Mr. Edward L. Stickney, Director
Monroe County Public Works Department
P.O. Box 1029
Key West, Florida 33040
RE: Chan e Order # 1 to Pavin and Gradin 1m rovements Cross Ke
Estates, Project #401-002.29
Dear Mr. Stickney:
Enclosed herewith is Change Order # 1 to the above project, for your signature and
further processing.
During the summer recesses of the County Commission, Commissioner Kenneth
Sorensen gave his verbal consent to make changes as necessary to the project,
provided the cost did not exceed a total of $5,000.00.
During the course of construction, this change in the amount of $800.00 was the only
necessary deviation from the original contract.
Very truly yours,
POST, BUCKLEY, SCHUH & JERNIGAN, INC.
as
MONROE COUNTY CONSULTING ENGINEERS
HLS/lvc
401-002.29
aJI~e~s)~~-
Project Manager
Enclosure
~'.:-'~';::;:.,.
I ~" " ' ~" ,;
n'.,.... - \(..~,
I'
r
,
7\l7fE1~: f':.,'I. PP.RO'l E.. 0
, ., . i j
, ". OOK_
A
ON_
~.;~3_ . .
2- __. Pp,GE OqJ- o_ld:__"__,,
AUG 1 1983
COUNTY ArTY.
CHANGE ORDER NO.
1
Job No.
401-002.29
Project Title:
Paving and Grading Improvements
Cross Key Waterway Estates Sub.
Contract Date:
June 3, 1983
Contractor:
The Brewer Company of Florida, Inc.
To:
The Brewer Company of Florida, Inc.
9801 N.W. 106th Street, Miami, Florida
33178
Attest:
You are directed to make the changes noted below in the subje
Date:
Approved As To Correctness and
Form
By:
Attorney for Monroe County
Nature of the Change:
During the course of construction it became apparent that 2 areas of
Boyd Drive could not be leveled up, with the contracted for overlay
of 111 asphaltic cement. It was determined that these two bumps should
be removed, the area recompacted and a leveling course of asphaltic
cement be applied, prior to the commencement of the 111 overlay.
The changes result in the following adjustment of Contract Price and Time:
Contract Price Prior to this Change Order:
Net Increase Resulting from this Change Order:
Current Contract Price Including this Change Order:
Contract Time Prior to this Change Order:
Net Increase Resulting from this Change Order:
Current Contract Time Including this Change Order:
$153,247.75
suu.uu
$154,047.75
180
-0-
180
Prepared by: R i c h a r d C. Pep e r
Date:
July 27, 1983
Post, Buckley, Schuh &. Jernigan, Inc.
~~o~r~t~ulting Engineers
.rr'!Le~anson~ct Manager
The Above Changes are Accepted:
Attest:
Da te:
Title: