Change Order No. 3
BOCC ~
FlLEO FOR RECmmANGE ORDER NO. 3
"94 II:E 16 P 1 :47
Project Title: Big Coppitt Roads I
DAN/-! .
Cl. K ',J I( C'
Contractor: ~l~JfBr~~.e(:nnpany of Florida, Inc.
Job No. NjA
Contract Date:
Nature of the Change: Adjustments in the final quantities are needed
based on field measurements resulting in a cost decrease of
$1,387.00. Also, a 20 day time extension is required due to rain
delays.
The changes result in the following:
Item 6 4" yellow striping delete 50 LF @ $0.65jLF (32.50)
Item 7 24" white striping delete 11 LF @ $3.50jLF (38.50)
Item 9 Reflective Pavement Markings add 21 ea @ $4.00jea 84.00
Item 10 Traffic SignsjPosts delete 7 ea @ $200.00jea (1,400.00)
(1,387.00)
Revised contract completion date is November 2, 1994.
BY: ~~
Divi~ipn Direct9r
DATE: I / .... ( 0 - 7 c.(
::~parec;;~
county, ElJS in er
DATE: if... ~~
Approved As to Correctness and Form:
By:
,
Date: II -l( -9~
f\
I r.,
Walter R. Brewer
Representative
The above changes are accepted:
Attest: .Jiuf,l't()4Vh,d! ~n Ann L Salt
I Assistant Secretary By:
Contract
/~-J- 9t/
Title:
President
Date:
Approved:
Attest: DANNY L. KOLHAGE, Clerk
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
A?.~~e~<<~~J
By: ar~-F~
MAYOR HAIRMAN