Change Order No. 1
BOCC
CHANGE ORDER NO.1
Project Title: Key Deer Paved Pathway
Job No. N/ A
::t ,.....,
Contractor: The Brewer Company of Florida, Inc. Contract Dat~ ~ ~ r-
::0 C") ?-; ,." rT1
~r": CD CJ
. '1:;;;:::-'~_
Nature of the Change: Add 349 days to contract time for change in deSig~;;fie~ ~
modifications of the drainage system due to adjacent wetlands and poor ~g~ ~
Adjustment in final quantities based upon field measurements as follows: SE6~~A~MQH.
~ ITI .c:- ;.u
~ 0
The changes result in the following: Increase in the contract amount by $31,242.50. Increase
in the contract time of 349 days. Revised contract amount is $174,640.37, expiring on March
30, 1998.
p'epa'edZ{A~..
By: U W
County Engineer
By:
~:
Division Director
Date:
(2- -/7 --78
Date:
/2../"I'rd'
Approved As to Correctness and Form:
By:
Date:
Contract
Walter R.. Briwer
The ab7J:lhanges a'ifr'Jfted: \
Attest: rd~{~. ~4U
Debra A. Brown
Assistant ~eCrel.QIY
By:
Title:
President
A
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
-en:~~ .
PROVED TO FO
A Al I .
B
By:
~~ ~-~
Mayor /Chairma n
ATTACHMENT TO CHANGE ORDER NO.1
KEY DEER PAVED PATHWAY
FINAL QUANTITIES
Item # Description Chanae Amount
1 ) # 6 4" yellow solid add 200 LF @ .89 1 78.00
2) # 7 6" white solid add 700 LF @ 1 .39 973.00
3) # 8 12" white solid add 195 LF @ 7.50 1 ,462.50
4) # 9 24" white stop bar add 24 LF @ 41.00 984.00
5) #10 White stop message add 1 @ 550.00 each 550.00
6) # 11 White bike diamond add 10 @ 89.00 each 890.00
7) #14 Well markers add 23 @ 15.00 each 345.00
8) #15 Delineators add 44 @ 65.00 each 2,860.00
9) #16 French Drains add 23 @ 1,000.00 each 23,000.00
TOTAL: $31,242.50