Change Order No. 1
.
THE BREWER CO. OF FLORIDA, INC.
ENGINEERS - CONTRACTORS
MANtTFACTtTRERS NON-SKIn PLANT MIXED ASPHALT
HIGHWAYS- ROADWAYS
November 25, 1996
SENT VIA HAND DELIVERY
County of Monroe
Engineering Department
5100 College Road
Key West, Florida 33040
Attention: David S. Koppel
County Engineer
RE: BIG PINE KEY VII ROAD IMPROVEMENTS
Dear Mr. Koppel:
I have enclosed one (1) original and three (3) copies of the "executed"
Change Order #1 for the above mentioned project per your request.
A copy was faxed to Stephanie in Accounts Payable today as suggested.
If you have any questions, please call our office.
Thank you for expediting our payment this month.
Have a great Thanksgiving this week !!
Sincerely,
THE BREWER COMPANY OF FLORIDA, INC.
/,
(>0 t~Lt(~_~/;_
~Debra A. Brown
Contracts Secretary
t '
. -~) VU:>{ L -( . l1.. .~
dab
Enclosures
10400 N.W. 121 WAY. MIAMI, FLORIDA 33178
OFFICE (305) 364-3595 . PLANT (305) 827-7986
BOCC
CHANGE ORDER NO. 1
Project Title: Big pine Key Rds. VII
Job No. N/A
Contractor: The Brewer Company of Florida, Inc. Contract Date:
Nature of the Change: Due to concerns from USF&WS, modifications to
roadway plans were necessary. Add 60 days of contract time. No
change in cost.
The changes result in the following: original contract completion
date - 10/15/96; New contract completion date following this Change
Order - 12/16/96.
Prepared ~ Appr~d:
BY: uV ~
County Engineer
DATE: /iJ ,2/-7'(
Approved As to Correctness and Form:
BY:
'-
D
DATE:
By:
(
Date: /6- '2-~ - ~6
The above changes are accepted:
Attest:~~O-t~~ 01lO-r
I Gwen\ Ann L. Salt Assistant sccre..::.rYJ3y:
/l
/
, /
y-/
Walter R. Brewer
Contract Representative
-90
Title:
President
DANNY L. KOLHAGE, Clerk
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
~~J~
By:
~~:f~