Change Order No. 38GC 4PPi(pV" 11-i-vt
CHANGE ORDER NO. 3
Project Title: Completion of Interior Job No- 04-017.00
finishing for Third Floor
of the Jail Addition (at
Jackson Square) Key West, Florida
Contractor: Gomez Construction Company Contract Date: January 5, 1988
Notice To Proceed: February 5, 1988
Gomez Construction Company
TO: 1560 Cadiz Avenue
Coral. Gabl Qs , Fl gi ja 33134
You are dire d to ma e the changes noted below in the s ject contact:
Attest: �� By: -.
Chairman, Ylonr ounty
Date: / • Board of County Commissioners
Approv A T Correctness and
Form "
Approved By: By:
Project,I,X qt ,,, . Attorney for Monroe County
(See Attachment "A")
The changes result in the following adjustment of Contract Price and Time:
Contract Price Prior to this Change Order: 1566 , 330.00
Net (Increase) (I11(99=0 Resulting from this Change Order: 23,003.50
Current Contract Price Including this Change Order: $589.333.50
Contract Time Prior to this Change Order: 187 Days
Net (Increase) (1J1(i(X%WW Resulting from this Change Order: 66 Days
Current Contract Time Including this Change Order: 253 nays
Current Contract Completion Date: October 15; 1988
Prepared by: C . Robert Rogers. Jr. Post, Buckley, Schuh do Jernigan,. Ine-
as Monroe County Consulting Engineers
Date: November 2, 1988
The Above Changes are Accepted:
Attest:
Date: // / elks
Con ctor' epresentative
Title: 7-
GC/#76
11/14/83/REVISED 3/5/87
ATTACHMENT "A"
Completion of Interior Finishing for Third Floor of the Jail Addition
(at Jackson Square)
PROPOSED ITEMS FOR CHANGE ORDER NO. 3 TO EXISTING
MASTER CONSTRUCTION CONTRACT BETWEEN MONROE
COUNTY AND GOMEZ CONSTRUCTION, DATED JANUARY
59 1988 TO COMPLETE THE INTERIOR FINISHING FOR
THIRD FLOOR OF THE JAIL ADDITION (AT JACKSON
SQUARE) KEY WEST, FLORIDA.
The changes are the results of requirements/requests by County Fire Marshal and User
request after commencement of construction, modifications due to existing conditions
and costs incurred by the Contractor due to Court/Commission ordered work
stoppages. The following items were approved by the Monroe County Board of County
Commissioners at their regular meeting held November 1, 1988.
DESCRIPTION AMOUNT
1. Furnish and install monitor light for each dormitory and
test buttom for each isolation cell tying fire alarm
system into console. $ 4,341.25
2. Furnish and install three (3) additional Exit lights
including conduit and conductors. $ 1,035.00
3. Furnish and install ten (10) additional fire sprinkler
heads including piping (6 for isolation cells and 4 for
corridor 320). $ 3,074.25
4. Deletion of 32 flush mounted sprinkler heads as called
for by contract. $ (490.20)
5. Furnish 40 institutional type sprinkler heads (32 installed
per contract and 8 for spares). $ 814.20
6. Furnish 50 institutional type sprinkler heads for install-
ation by County Staff $ 324.00
(32 heads as replacement for existing heads painted
by contractor - N/C).
7. Repair defective existing drain pan for A/C fan coil
Unit #2. $ 195.00
8. Furnish and install six (6) three speed control fan relays
for A/C fan coil units including conduit, conductors and
hook-up existing fan motors. $ 4,816.20
9. Furnish and install (approx. 200 ft.) of conduit for
speaker in dormitory 306; smoke detector for dormitory
304 and lights for corridor 302 (existing conduit blocked
up and not useable). $ 759.00
hm/GC#120 Page 1
•
ATTACHMENT "A"
(CONTINUED)
Completion of Interior Finishing for Third Floor of the Jail Addition
(at Jackson Square)
DESCRIPTION
AMOUNT
10.
Furnish and install conduit and conductors to supply
current from first floor to existing electrical receptacles
in hallway on second floor.
$ 1,150.00
11.
Furnish and install custom designed metal chase around
exposed conduit in dormitories 304 and 306.
$ 295.00
12.
Cost incurred due to Court ordered work stoppage
during installation of door on second floor. (includes
equipment rental and labor losses).
$ 3,072.00
13.
Cost incurred due to Commission ordered work stoppage
during installation of Fresh Air Vent on second floor
(includes equipment rental and labor losses).
$ 562.80
14.
Additional cost of selected hardware per Section 08711
Finish Hardware (allowance) of the Project Manual.
$ 2,675.00
15.
Caulk around all light fixtures.
N/C
16.
Furnish and install removable 1/4" thick steel cover
plates over opening around fire cabinets in hallway.
$ 380.00
TOTAL AMOUNT DUE THIS CHANGE ORDER NO. 3
$ 23,003.50
hm/GC#120 Page 2