Loading...
Miscellaneous0. Florida Department of ,environmental. Regulation South District. • 2269 Bay Strcct • Fort Myers, Florida 33901.2W 6 x��gli ; 5' Snh Marilnez, GOVernnr bale Twxchtmann, Sucr<.tyry John Shearer, Assistant Secretary Philip Wwods, pelway A$04m t Seveury CERTXFXED MAIL # P 496.201 714 RETURN RECEIPT REQUESTED Captain Thomas Brown County Administrator County of Monroe Public Service Bldg./Stock island Key West, Florida 33040 Dear Captain Brown: December 18, 1990 D.E.R. Marathon, FL Re: Monroe C unty - SWIDW Cudjoe Key Landfill SC44-139746 Let this letter serve as a follow-up to our November 8, 1990 inspection of the referenced landfill, copy enclosed. The inspection revealed the following deficiencies. 1. On December 27, 1989 the County received alternative procedure approval from the Department to use 12 inches of screened ash 'aver the gee%. A.10-geonet-bottom liner, and 12 inches of chapped tires above the ash layer. As the result of shortages of screened ash and chipped. tires, two feet of filtered sand has now replaced the ash/chipped tire layer in a portion of the landfill. Please Modify the engineering drawings of the referenced permit accordingly to show this change. 2. Two 20,000 gallon storage tanks have been installed at the landfill site. There is no mention of the construction of these tanks in the referenced permit application. One sludge storage tank is represented in the revised application plans (sheet 3 of 8, February 23, 1988). However, the'tank in the drawing is represented as a component of the on -site industrial wastewater treatment plant (IWWTP). The application to construct the IWWTP was withdrawn by the County, and the plant was.never built. In May of 1989, modification plans to the solid waste permit were submitted but did not indicate the existence of the storage tanks at their current location. Copies of pertinent portions of two of the engineering drawings are enclosed for your perusal. In accordance with specific Condition #6 of the permit, you are required to submit plans Continued..... L R�tNCItI Iwper Captain Thomas Brown Aecember 18, 1990 Page 2 to us if leachate is to b landfill. Please modify conditions. Please also taken to prevent leachate including the area under' the storage tank drum. e stored outside of the lined your permit to show existing explain what•precautions have been from discharging to unlined areas the conveyance piping extending to 3. please note, if the storage tanks are intended to store septage/sludge instead of leachate the tanks must be approved and permitted by our domestic waste section. Please clarify your intent. 4. As explained on page 3 of the inspection report; you are requested to cease accepting solid waste at the unlined section of the Cudjoe Key Landfill as soon •as an option becomes available to you which is permittable by the Department. This includes receiving an operation permit for the completed lined section, or when the transfer station becomes operational, which ever comes first. Failure to comply with this request may result in enforcement action. In addition, the current permit should be modified as necessary to address the final cover on the unlined section. Please respond to items one, two and three by February•l, 1991. Reply to item four as soon as it becomes applicable. If you have any questions please contact Ghaus Minhaj concerning solid waste •issues and Mel Reinhart concerning domestic waste issues. Both may be reached at (813)332--6975. Your cooperation is appreciated. sincerely, v Philip R. Edwards Deputy Assistant secretary PRE/BK/jrh cc., Ghaus Minhaj w/enclosures Mel Reinhart w/enclosures Lisa Gordon w/enclosures Raymond 7. Dever, P.E. w/enclosures DECgzol av 201990 D.E.R. Marathon, FL C UNTY joNROE KEY WESTLORIDA 33040 (305)294-4641 •rz ., M E M O R A N D U M DATE: June 5, 1991 TO: Board of County Commissioners FROM: Joe Kelinson .., Asst. County Attorney BOARD OF COUNTY COMMISSIONERS MAYOR, Wilhelmina Harvey, District 1 Mayor Pro Tem, Jack London, District 2 Douglas Jones, District 3 A. Earl Cheal, District 4 John Stormont, District 5 RE: Cudjoe Key Landfill; use of silica sand instead of tire chips/ash as a cover/filtration medium for the geotextile layer - update I have been in contact with Mr. R. E. Kinghorn, Vice President of Ground Improvement Techniques, Inc., (G.I.T.), the contractor working under Post -Buckley, et al. (PBS&J) on this job. Mr. Kinghorn spoke from his office in Washington state, however, he was personally involved here. After a brief review of our prior discussions, the following is an objective rendition of Mr. Kinghorn's thoughts and opinions upon this issue: 1. Shortaae of available tire chips/ash suvvlied by the Countv: This was Kinghorn's first experience using these recycled materials and, to his knowledge, the first attempt to do so in Florida. He commends this novel approach; however, the amount needed was underestimated. The most likely reason is the compaction factor. (When physically placed on the geotextile, the material compacts, accounting for less volume than originally calculated.) He estimates the chips/ash compacted about 301, accounting for the shortage (sand for example compacts 10%). Why was this not pre - calculated? Because the novel material was an unknown factor without a known compaction ratio, and the amount needed was only an estimate. -2- 2. options a. Amend the existing contract. Feasible, albeit the existin� contract had "time of the essence" and "liquidated damages' clauses. More expensive than, b. Cancel the balance of the contract with G.I.T. (Mr. Kinghorn told me'iere was a cancellation clause in the contract, however, I was unable to find same). Upon cancellation, the County could proceed to cover the geotextile as the recyclable materials became available, and do so in house. 3. Reasons to timely complete the -project: The basic liner (underneath the geotextile) is 60 mils thick (1/8 inch). It is the only medium preventing leaching of effluents into the soil. Uniform industry policy suggests that once the liner is placed, that it be covered by the protecting geotextile post haste. There is great liability potential if the liner is not protected. It is easily damaged, such as by animals, vandalism, accident, etc. It is very flammable and might be ignited by a careless cigarette. A major problem is that if the liner is breached, it could go unnoticed. Even if suspected, it is extremely difficult to located the tear, especially when the landfill is filled. If leachingg occurs after the landfill is activated, cleanup costs would be exorbitant, in addition to environmental concerns. Additionally, many landfills have backup protection to the liner, such as a layer of clay. Cudjoe is a single liner with no backup. PBS&J are obligated to provide the County with an operational facility. It is prudent operating procedure to minimize its potential liability by keeping G.I.T. on the job. (Argument against cancelling G.I.T.'s contract). G.I.T., by contract, is fully bonded. Although the geotextile can be incrementally placed, it must be covered with the filtration medium at once as it is susceptible to sunlight damage in a short time. If not totally and timely covered, the bottom liner is susceptible to damage with expensive, pervasive results. To totally protect the liner, via the geotextile, the geotextile must be covered within days. 4. Why -silica sand? Recyclable materials (tire chips/ash are currently experimental materials in the industry. Although cheap, we ran out of them. -3- The County needed to cover the geotextile in short order. Silica sand is the standard material used in Florida. Coverage/filtra- tion material must have a designated level of permeability (regular topsoil is not acceptable), but silica sand is widely accepted, and D.E.R. approval is necessary. Using 20-20 hindsight, it is easy to criticize the underprojec- tion of the amount of tire chips/ash necessary to fully cover the geotextile. It was a worthwhile experiment and we used all of that material we had, and cost benefitted thereby. According to Mr. Kinghorn, the exigency of protecting both the liner and the overlying geotextile mandated quick acquisition of an approved covering, and counter balanced the extra cost of the sand. Mr. Ray Schauer of PBS&J contacted me yesterday. He is preparing another letter which he hopes will fully answer my previous inquiries. JK/bpl