Change Order No. 14 ,
GREINER
MIAMI, FLORIDA
CONTRACT CHANGE ORDER NO. 1 c ►► E n c n f <,�n t +? DATE: 11/ 2 4/ 9 3
PROJECT NAME: INSTALL AIRFIELD SECURITY FENCING AND GATES
.94 Jai R1
MARATHON AND KEY WEST INTERNATIONAL AIRPORT
FAA AIP PROJECT NO.: 3-12-0044-11- r,',3--12;0037-08
FDOT WPI NO.: 6826754
CONTRACTOR: FENCE MASTER INC.
The work under this contract shall be changed and the Contract Price adjusted
to reflect all additions and/or deletions described and indicated by
modifications to Contract Documents, including any and all drawings and
attachements thereto, all of which form a'part of this Change Order. The
General Provisions, Supplemental Provisions and Special Provisions of this
Contract shall apply to this Change Order.
This Change Order Includes:
1) Reduction in Item F-162-5.5 Pedestrian Gates (2) from $15,500 to
$12,500. This change will delete the telephone entry and card reader
and add a key pad and self -closer. The two gates will be installed at
the Marathon Airport.
2) Reduction in Item F-162-5.2 12, Cantilever Slide Gate from $14,000 to
$12,000. This gate will be installed at the Marathon Airport.
3) Item F-162-5.6 10, Swing Gate will be changed to 12, Swing Gate to
eliminate pedestrian entry. This gate will be installed at the Marathon
Airport at no additional cost to the project.
4) Provide two hundred (200) cards for gate access to the Airport Director.
These cards will be provided at no additional cost to the project.
5) Provide radio receivers (2) for all vehicular gates. The receivers will
be provided at no additional cost to the project.
Original Contract:
Amount: $_ 83,189.00 Amount After Last Change: $_ 83,189.00
This Chan e.
Contract Time Extension: None
Add: $ 0.00 Deduct: $ 5,000.00 New Contract Amount: $_ 78,189.00
Net Change: - $ 5,000.00
Change Approved: B,
AS TO MONR_OE COUNTY: BI
ATTEST: DANNY L . u0^LI- AGE , CLERK
DATE z z z