Loading...
1st Change Order 01/19/2011Item Description Unit Quantity Unit Price CHANGE - OWER ❑ cy 23443 ORDER 93 772.00 ARCHITECT El R ndl' Material cy 23443 4.00 CONTRACTOR ❑ -. Total ALA DOCUMENT G701 FIELD ❑ W5 OTHER ❑ PROJECT: Runway Safety Area CHANGE ORDER NUMBER: 1 (name, address Improvements. 3491 South Roosevelt Blvd. DATE: December 7 2 10 Key West, Florida 33040 ARCHITECT'S PROJECT NO: CONTRACT DATE: TO CONTRACTOR: Quality Enterprises USA, Inc. (name, address 3894 Mannix Dr. Suite 216 CONTRACT FOR: $ 2,296,711.98 Naples, Florida 34114 p: Q U The Contract is changed as follows: Modifications requested by the owner to remove additional muck material. w sz Item Description Unit Quantity Unit Price Subtotal 1 Unsuitable Excavation cy 23443 4.001$ 93 772.00 20 R ndl' Material cy 23443 4.00 93 772.00 -. Total Al W5 LLJ X: cc: WX cD U_ CC Not v0d u* sighed J k�ji.the Owner, Architect, and Contractor. LLJ _j — < - The original (Contract Sum) (Guaranteed Maximum Price) was ......................... ..............................$ 2,296,711.98 Net change by previously authorized Change Orders ............................................ ............................... S 0.00 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was ....................$ 2,296,711.98 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order in the amount of .............................................. .............................. 187 544.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order will be ... S 2,484,255.98 The Contract Time will be (increased) (unchanged) by Forty-Five (45) days The date of Substantial Completion as of the date of this Change Order therefore is March 22, 2011. NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed authorize onstruction Change Directive until the cost and the ti ;changfc nt ractor case a change order is execute rsede the con - 7 7, r� �' / h ENGIN R TRA URS Co orati n Quality Enterprises USA, Inc. 00ft CLEPM a f rice which have been both the owner and Address Address Address � 7650 Corporate Center Drive 3894 Mannix Dr. Suite 216 ��U4 �� ' ,, 'F'1r 0 4" Suite 400 Naples, Florida 34114 /� �C FL !27,1-/d Miami, F133126 -1220 X Y Andres Gutierrez, PE BY Louis J. Gaudio, VP BY DATE December 7, 2010 DATE ► 2/1 + o DATE M CAUTION: You should sign an original AIA document that has this caution pr nt d in ref. �A .-assures-that-Changes; will not be obscured as may occur when documents are reproduced. ` AIA DOGU4f1 N" G'6! a FE - 3 2011 i CLEAR 7 -ORDER a 1987 EDITION a AIA • 01992 • THE \ CTS, 1735 NEW YORK AVE. NW, WASHINGTON D.C. 20006 f G701-198 ) JAN i 2011 (� / A- - v — IgF:\keywest\ RSA \New RSA (11- 26 -07jtUocuments(511 CO #2(12-07 =10).oc Mayor H ath r arruthers Januar 19, 11 QE ' t3UALITY ENTERPRISES U 5 A C . December 7, 2010 SENT VIA E Mail: Andres_Gutierrez @URSCorp.com Mr. Andres Gutierrez P.E URS Corporation 7650 Corporate Center Dr, Suite 400 Miami, Florida 33126 -1220 RE: Monroe County Key West International Airport Change Order Request for Additional Muck Removal Dear Mr. Gutierrez: Quality Enterprises USA, Inc. respectfully request a change order in the amount of One Hundred Eighty Seven Thousand Five Hundred Forty Four and 00 /100 dollars ($187,544.00) for the removal of addition muck discovered during construction at both the east and west end of the project limits. Area #1 located at the east end of the project is a 200ft x 300ft x 6ft deep area which equates to 11,111 cy. Area #2 and #3 are at the east end of the project and measure 400ft x 100ft x 6ft deep and 31 Oft x 50ft x 6ft deep, totaling 12,332 cy, for a total combined volume of 23,443 cy. Su mmary: Unsuitable excavation - 23,443cy x $4.00 cy = $93,772.00 Rehandling Material - 23,443cy x $4.00 cy = $93,772.00 Grand Total - $187,544.00 In addition, we would like to request an extension of 45 days for this additional work. Upon your approval and direction, we will proceed with removal of this muck material. Please contact me directly should you need any additional information. Very truly..yours.,...- ._ -... Louis J. Gaudio Vice President - Project Management Cc: Mr. Peter Horton - KWIA Airport Director 208 Tintern Court 3894 Mannix Drive, Suite 216 Chesapeake, VA 23320 Naples, FL 34114 -5406 (757) 548 -8000 (239) 435 -7200 Fax (757) 548 -2600 Fax (239) 435 -7202 Lic# CBCA57231 QE QUALITY ENTERPRISES U s n c . January 6, 2011 SENT VIA FED EX OVERNIGHT April Pearson Senior Administrator - Airport Business Key West International Airport 3491 South Roosevelt Boulevard Key West, Florida 33040 305- 809 -5204 direct RE: Monroe County Key West International Airport Change Order Request for Additional Muck Removal Dear April: Please find attached Change Order #1 and original change order request letter for the above referenced project. Please contact me directly should you need any additional information. Ver Louis J. Gaudio Vice President - Project Management 208 Tintern Court 3894 Mann ix Drive, Suite 216 Chesapeake, VA 23320 Naples, FL 34114 -5406 (757) 548 -8000 (239) 435 -7200 Fax (757) 548 -2600 Fax (239) 435 -7202 Lic# CBCA57231