The original Contract Sum ..................... ............................... ....................$255,830.00
Net change by previously authorized Change Orders .............. ..............................$ 0.00
The Contract Sum prior to this Change Order was ..................... ....................$255,830.00
The Contract Sum will be changed by this Change Order ............. .....................$23,196.50
The new Contract Sum including this Change Order is ............... ....................$279,026.50
The Contract Time will be increased by ....................... ............................... 0 Days
The date of Substantial Completion as of the date of this Change Order is ....... 5/11/11
Detailed description of Change Order and justification:
As a result of unforeseen conditions of the road subgrade, limerock base and asphalt quantities were
increased from the original bid amount. The following items are included in this Change Order:
235 square yards of Limerock Base @ $73.30 per square yard = $17,225.50
235 square yards of Asphalt @$ 23.00 per square yard = $5,405.00
Additional Bond = $566.00
Net Amount of this Change Order = $23,196.50
This Chance Order is 9% of the original contract price.
Not valid until signed by Owner, and Contractor
CONTRACTOR:
Grader Mike, LLC Date
ENGINEERING SERVICES DIRECTOR: J " / � /
J S. Clarke, P.E. Date
ENGINEERING /PROJECT MANAGEMENT DIVISION
i fMA 2d`
Date
COUNTY /DEPUTY ADMINISTRATOR: ��7_ v(, 1i
D ate
2 1 L 11- i - - A
CF2� i:•�•1 f i'�c� (��. {.S+::S:iG:f�T'tJl1�1i'<���t�J