1st Change Order 07/06/2011M E M O R A N D U M
DATE: July 6, 2011
TO: Belle DeSantis, Deputy Clerk
FROM: Beth Leto, Public Works Division
RE: Fuel Pipe Replacement Project — Stock Island Detention Center
Enclosed for your information and file, please find a fully- executed original of Change
Order No. 001, executed this date by Debbie Frederick, Deputy County Administrator, in
accordance with Ordinance 026 -1998, increasing contract sum by $1,100.00.
Should you have any questions, please feel free to contact me at x4560 or Bob Stone at
289 -6036.
bpl
cc: Jackie Clynes
Bob Stone
MONROE COUNTY PUBLIC WORKS
PROJECT:
Monroe County, FL
Fuel Piping - Replacement
Monroe County Detention Center
CONTRACTOR:
MECO Of North Florida
3626 Phoenix Avenue
Jacksonville, Florida 32206
Change Order
----------------------------------------------------
CHANGE ORDER NUMBER: 001
DATE: June 22, 2011
PROJECT NUMBER: PWD -97- 268 -2011
CONTRACT DATE: May 18, 2011
NOTICE TO PROCEED: June 6, 2011
CONTRACT FOR: General Construction
THE CONTRACT IS CHANGED AS FOLLOWS:
Change material for pipe hangers, hanger rods, couplers and anchors from zinc coated steel to a minimum
of 304 stainless steel.
The original Contract Sum was $49,792.00
The net change by previously authorized Change Orders $0 ----------
The Contract Sum prior to this Change Order was $49,792.00
The Contract Sum will be changed by this Change Order in the amount of $1,100.00
The new Contract Sum including this Change Order will be $50,892.00
This Change Order does not change the Contract Time.
NOT VALID UNTIL SIGNED BY THE CONTRACTOR AND THE OWNER
Robert A. Stone, MCPW MECO of North Florida Monroe County, FL
Owner's Representative Contractor Owner
10600 Aviation Blvd., Marathon, FL
Marathon, FL 33050
Address
BY (Signature)
ZC 6 �r I
DATE
3626 Phoenix Avenue 1100 Simonton Street
Jacksonville, FL 32206 Key West, FL 33040
Address Address
BY ( Signature) ignature)
DATE DATE
MEMORANDUM
DATE: JUNE 28, 2011
TO: DENT PIERCE, PUBLIC WORKS DIVISION DIRECTOR
FROM: BOB STONE, MIDDLE KEY OPERATIONS DIRECTOR
RE: FUEL PIPING REPLACEMENT - MONROE COUNTY
DETENTION CENTER
Attached for approval is an original of Change Order No. 1, executed by
the Contractor and myself for the project referenced above. This is an
add change order for $1,100.00
In lieu of installing zinc - coated steel pipe hangers, couplings, rods and
anchors for the above ground piping as was allowed in the bid
documents, it is the Owner's Representative's request to change the
material from zinc - coated steel to stainless steel of which should be
maintenance free for the next 20 years. This is an added value to the
County with an estimated net financial benefit and 20 -year lifetime
savings of $8,700.00 as follows:
Replacement cost of pipe hangers, rods and couplings at least two
times in the next twenty years: Labor = 1 hr. @ $25 /hr. for 50
hangers = $1,250 X 2 replacements = $2,500; Materials = $5 ea. X
50 = $250 X 2 replacements = $500; Labor of $2,500 + Material of
$500 = $3,000 20 -year replacement cost
Painting cost every two years = Labor = .5 hr. @ $25 /hr. for 50
hangers, rods & couplings = $625 per painting X 10 applications =
$6,250; Material @ $60 each X 10 applications = $600 + Labor of
$6,250 = $6,850 20 -year painting cost.
20 -year replacement & painting cost = $9,850 - cost of stainless
steel replacement of $1,100 = $8,750 of lifetime savings. This
provides a value of $438 /year ($8,750/20 years = $437.50) of
which translates to a 2.5 year payback ($1,100/$438 = 2.5)
The contractor has negotiated out his original cost for this material and
painting, bringing the cost of the change down to $1,100. This revises
the contract amount to $50,892.00. The budgeted amount for this
project is $55,000.00. Therefore, approval is recommended. Please
let me know if there are any questions or more information is desired.
Cyr - Connie
From: Cyr- Connie
Sent: Friday, July 01, 2011 9:13 AM
To: County Commissioners and Aides
Subject: Change Order
Attachments: Change Order.PDF
Please find attached a change order for your review.
Connie Cyr
Aide to Roman Gastesi, County Administrator
Monroe County
iioo Simonton Street, Suite 2 -205
Key West, FI 33040
3 - 2 9 2- 4443
3 Fax
Cur- connie(a)monroecounty- ff.gov
MEMORANDUM
TO: Board of County Commissioners
From: Debbie Frederick
Deputy County Administrator
Date: July 1, 2011
RE: Change Order
Attached is a proposed change order for MECO of North Florida. (Change Order #1 is
for increase of $1,1oo.00 for fuel piping replacement at the Monroe County Detention
Center
According to the ordinance adopted by the Board of County Commissioners, proposed
change orders are to be presented to members of the Board of County Commissioners
prior to approval, assuming they are within the Administrator's prescribed limits.
Change orders not within the Administrator's authority are placed on the BOCC agenda.
The Deputy Administrator intends to app ove this change order on Tuesday, July 5,
2011.
Debbie Frederick
Deputy County Administrator
DF :cac