At the May 18, 2011, Board of County Commissioners meeting, the Board granted
approval and authorized execution of Item C8 Professional Service Order #10 with THC, Inc. for
Key West International Airport's Noise Insulation Program (NIP) Phase 7 — Lead Paint
Remediation.
Enclosed is a duplicate original of the above -mentioned for your handling. Should you
have any questions, please feel free to contact our office.
cc: County Attorney via e-mail
Finance
File
PROFESSIONAL / SERVICE ORDER
MONROE COUNTY
To: THC, Inc. Professional Service Order No. 10
Re: PSO Agreement, Dated 10-15-03 Resolution No.
Project Name: Implementation of Noise Insulation Program (Phase 7 Lead Paint Remediatio--.I
r C
Description of Services:
N O
(See attached Scope of Services)
_. o
:;u
Multiple of Direct Salaries `a o
Lump Sum X Reimbursable Expense
Days to Complete 200 Fee this Service Order $45,186.87
Payment for Services shall be in their entirety as per PSO.
Prepared by:
Date: 4-19-11
Accepted by:
Date:
Recommended by:
Date: 4-19-11
Approved by:
Monroe County
Mayor Heath Cab&
May 18, 201
t
Date:
NTY 9ATTORN
AS T F
M RCADO
U ATTORNEY 513111
Lead Paint Remediation Budget by Task
Task No. Task Description
1 Property Owner Communication & Document Distribution
2 Lead Paint On -site Testing
3 Lead paint Testing Result Report Development & Analysis
4 Review Contractor's EPA RRP Construction Site Plan
5 Process GC's Change Order & Master Schedule Revisions
TOTAL PSO BUDGET
Lead Paint Remediation
$3,392.00
$29, 866.87
$6,424.00
$2,752.00
$2,752.00
$45,186.87
4/19/2011
PHASE 7 LEAD PAINT REMEDIATION SCOPE OF SERVICES
IMPLEMENTATION OF NOISE INSULATION PROGRAM
KEY WEST INTERNATIONAL AIRPORT
CONTRACT AMENDMENT - EPA LEAD PAINT RULE
Background
On April 22, 2010, the Environmental Protection Agency (EPA) adopted the Renovation,
Repair and Painting Lead Rule. This new federal law will require that contractors
performing renovation, repair and painting projects that disturb lead -based paint in
homes, child care facilities and schools, built prior to 1978, be certified and follow
specific work practices to prevent lead contamination.
EPA RRP General Work Practices:
• Contain the work area — warning signs, poly sheeting to seal off floors, doors and
HVAC components.
• Minimize dust.
• Flame burning; torching and using power tools without HEPA vacuum
attachments are prohibited.
• Clean thoroughly with HEPA vacuuming and wet mopping.
• Waste must be contained prior to removal from the work area and properly
stored to prevent access and release of dust and debris.
EPA RRP Work Practices for Interior Renovations:
• Remove all objects from the area or cover them with plastic sheeting.
• Close and cover all duct openings with plastic sheeting.
• Close all windows and doors, doors must be covered with plastic sheeting.
• Cover flooring in the work area (a minimum of 6 feet) beyond the perimeter of the
surfaces undergoing renovation.
• After renovation is completed, the firm must clean the work area until no dust,
debris or residue remains. This would include:
o Collect all paint chips and debris and seal it in a heavy duty bag.
o Remove and dispose of protective sheeting as waste.
o Waste transported from renovation activities must be contained to prevent
release of dust and debris.
EPA RRP Work Practices for Exterior Renovations:
• Close all windows and doors within 20' of the renovation.
• Ensure that all doors within the work area that will be used during the renovation
are covered with plastic sheeting that allows workers to pass through as well as
confining dust and debris.
• Cover the ground with plastic sheeting, extending a minimum of 10 feet beyond
the perimeter to collect falling paint debris.
Key West International Airport — Residential Sound Insulation Program 6/28/2010
Phase 7 Lead Paint Remediation Scope of Services Page 1
In situations where work areas are close to other buildings, the firm must take
extra precautions in containing the work area (such as vertical containment)
After renovation is completed, the firm must clean the work area until no dust,
debris or residue remains. This would include:
o Collect all paint chips and debris and seal it in a heavy duty bag.
o Remove and dispose of protective sheeting as waste.
o Clean all objects and surfaces in the work area and within 2 feet of the
work area with a HEPA vacuum or damp cloth or a mop for flooring.
EPA RRP - Responsible Parties:
• Residential rental property owners/managers
• General contractors
• Special trade contractors, such as painter, plumbers, carpenters and electricians
EPA RRP - Pertinent Activities:
• Remodeling or repair/maintenance
• Electrical work
• Plumbing
• Painting
• Carpentry
• Window replacement
EPA RRP - Exclusions:
• Houses built after 1978
• Housing for elderly or disabled people (unless children under 6 years old reside
or are expected to reside there)
• Zero building dwellings (studio apartments, dormitories)
• Minor repair that could disturb 6 square feet or less of paint per room or 20
square feet or less on the exterior of a home/building
• This does not include window replacement or demolition projects
EPA RRP Certified Firm Responsibilities:
• All individuals performing work are certified renovators.
• A certified renovator is assigned to each renovation and performs all
responsibilities.
• All renovations are performed in accordance with the work practice standards of
the Lead -Based Paint Renovation, Repair and Painting Program.
• Pre -renovation education requirements of the Lead -Based Paint Renovation,
Repair and Painting Program are performed.
• The program's recordkeeping requirements are kept.
Key West International Airport — Residential Sound Insulation Program 6/28/2010
Phase 7 Lead Paint Remediation Scope of Services Page 2
EPA RRP Certified Renovator Responsibilities:
• Use an EPA approved test kit to determine whether components affected by the
renovation contain lead based paint.
• Provide on the job training to workers on the work practices they will be using in
their assigned tasks.
• Must be present at the work site when warning signs are posted, while the
containment is being established and when the work area cleaning is being
performed.
• Direct work being performed by other individuals to ensure that proper work
practices are being followed.
• Must be available, either onsite or by telephone, at all times renovations are
being performed.
• Must perform project cleaning verification.
• Must have copies of their initial course completion and most recent refresher
course completion certificate.
• Must prepare required records.
• Firm and renovators certifications must be renewed every 5 years.
EPA RRP Recordkeeping Requirements (General Contractor):
• Certification that lead -based paint is not present
• Records relating to the distribution of the lead pamphlet
• Any signed and dated statements from owner -occupants documenting that the
requirements do not apply.
• Documentation of compliance with the requirements of the Lead -Based Paint
Renovation, Repair and Painting Program.
Consultant Team
The Consultant Team is composed of the following disciplines. Their billable rates are
shown in parenthesis:
THC, Inc. - THC, Inc. (THC) will provide all required construction management
services related to this contract amendment that will include the Director of
Sound Insulation Programs ($198.00), Project Manager ($115.00), Executive
Construction Manager ($135.00), On -Site Construction Manager ($110.00), and
Administrative Assistant ($81.00).
EE&G Environmental Services LLC — EE&G will provide all lead paint testing
services and will develop a Report of Findings for each of the thirty eight (38)
properties.
Required Scope of Services
Since the EPA rule was adopted after THC prepared their Scope of Services for the Key
West Noise Insulation Program - Phase 7 Construction Services, this scope of services
document reflects THC's additional responsibilities necessary to introduce and
incorporate the EPA RRP rule requirements for the thirty eight (38) eligible properties
that include the following:
Key West International Airport — Residential Sound Insulation Program 6/28/2010
Phase 7 Lead Paint Remediation Scope of Services Page 3
Task 1 - EPA RRP Certification
Task 2 - Property Owner Communication and Document Distribution
Task 3 - Lead Paint Testing
Task 4 - Lead Paint Testing Result Report Development and Analysis
Task 5 - Review Contractor's EPA RRP Construction Site Plan
Task 6 — Process Contractor's Change Order & Master Schedule Revisions
The following is a detailed summary of each task, consisting of THC staff hours and
associated reimbursable expenses:
Task 1 — Property Owner Communication and Document Distribution
THC staff (Program Manager and Administrative Assistant) will provide all required
communication to the Property Owners with regard to lead testing process, lead testing
schedule, EPA Property Owner Requirements and the distribution of required EPA
documents.
Summary of Hours - THC
Position
Hours
Hourly Rate
Total
Project Manager
16
$115.00
$1,840.00
Administrative Assistant
16
$81.00
$1,296.00
TOTALS
1
1 $3,136.00
Reimbursable Expenses
EPA Brochures
$220.00
Postage
$36.00
TOTAL
$256.00
TOTAL TASK BUDGET
Task 1 1 $3,392.00
Task 2 — Lead -Based Paint On -Site Testing
EE&G will utilize a NITON X-Ray Fluorescence (XRF) instrument to perform a lead
based paint screening of each property. The screening will be performed using
practices based on a modified version of the protocol established in the "Guidelines for
the Evaluation and Control of Lead -Based Paint Hazards in Housing" by the Department
of Housing and Urban Development (HUD) in June 1995. Testing locations will be
determined on site by an Environmental Protection Agency (EPA) Accredited Lead -
Based Paint Inspector/Risk Assessor. If necessary, EE&G will collect paint chip
samples for lead -based paint analysis to verify any inconclusive findings detected
during the screening. The paint chip samples will be analyzed utilizing Atomic
Absorption Spectrophotometry (AAS) in accordance with ASTM D3335-85A. In addition,
THC Staff (Program Manager and Administrative Assistant) will be responsible for the
Key West International Airport — Residential Sound Insulation Program 6/28/2010
Phase 7 Lead Paint Remediation Scope of Services Page 4
scheduling and coordination of all tests with the Property Owners. In addition the
Program Manager will accompany EE&G (on -site) during the entire testing process.
Summary of Hours - THC
Position
Hours
Hourly Rate
Total
Project Manager
80
$115.00
$9,200.00
Administrative Assistant
8
$81.00
$648.00
TOTALS
$9,848.00
Reimbursable Exnenses
Trip Expenses
$2,823.87
EE&G Testing Services
$17,195.00
TOTAL
$20,018.87
TOTAL TASK BUDGET
Ffi_sO77 1 $29,866.87
Task 3 - Lead Paint Testinq Result Report Development and Analysis
EE&G will prepare a final report for the structures containing both the findings and
recommendations of the LBP screening. The final reports will not contain photographs
or diagrams of the sampled materials. The reports will be based on a 15 business day
turnaround from the time the field work is completed. Upon completion of reports, THC
staff (Director of Sound Insulation Programs, Executive Construction Manager, On -Site
Construction Manager, and Project Manager) will be responsible for thoroughly
reviewing all reports and coordination with the General Contractor.
Summary of Hours - THC
Position
Hours
Hourly Rate
Total
Director of Sound Insulation
8
$198.00
$1,584.00
Project Manager
8
$115.00
$920.00
Executive Construction Manager
16
$135.00
$2,160.00
On -Site Construction Manager
16
$110.00
$1,760.00
TOTALS
$6,424.00
TOTAL TASK BUDGET
Task 3 1 $6,424.00
Task 4 - Review Contractor's EPA RRP Construction Site Plan
Once THC staff (Director of Sound Insulation, Executive Construction Manager and On -
Site Construction Manager have fully reviewed EE&G's lead paint findings for the thirty
eight (38) properties, they will need to meet with the General Contractor to review
construction site plans to insure compliance with EPA RRP rule requirements. This plan
should include a review of:
Key West International Airport— Residential Sound Insulation Program 6/28/2010
Phase 7 Lead Paint Remediation Scope of Services Page 5
1. General Contractor's EPA RRP site plan should include their means and methods of
containing the opening/area that is confirmed to have the presence of lead paint
2. General Contractor's EPA RRP site plan should include their procedure to insure that
all certified renovators have proper safety equipment.
3. General Contractor's EPA RRP site plan should explain their procedure to remove
the existing window/door or make the necessary cuts within the established
containment area.
4. General Contractor's EPA RRP site plan should include their procedure of cleaning
the rough opening (window/door) or area that was cut and remove containment.
¢iimmont of Hniirc - THC
Position
Hours
Hourly Rate
Total
Director of Sound Insulation
4
$198.00
$792.00
Executive Construction Manage
8
$135.00
$1,080.00
On -Site Construction Manager
8
$110.00
$880.00
TOTALS
1
$2,752.00
TOTAL TASK BUDGET
Task 4 $2.752.00
Task 5 Process General Contractor Change Order & Master Schedule Revisions
Once THC staff (Director of Sound Insulation, Executive Construction Manager and On -
Site Construction Manager have fully reviewed the General Contractor's plans to
conform to the EPA RRP rule on the construction site, THC will work with the General
Contractor to negotiate a Contract Change Order that will represent the additional labor
and materials required to conform to the EPA RRP rule requirements. In addition, THC
will work with the General Contractor to process a revision of the master construction
schedule, which will assume the additional construction site responsibilities related to
the EPA RRP rule.
Aliimmary of Hours - THC
Position
Hours
Hourly Rate
Total
Director of Sound Insulation
4
$198.00
$792.00
Executive Construction Manager
8
$135.00
$1,080.00
On -Site Construction Manager
8
$110.00
$880.00
TOTALS
$2,752.00
TOTAL TASK BUDGET
Task 5 $2,752.00
TOTAL OVERALL TASK BUDGET
ALL TASKS 1 $45,186.87
Key West International Airport — Residential Sound Insulation Program 6/28/2010
Phase 7 Lead Paint Remediation Scope of Services Page 6
TOTAI SUMMARY OF HOURS - THC
Position
Hours
Hourly Rate
Total
Director of Sound Insulation
16
$198.00
$3,168.00
Project Manager
104
$115.00
$11,960.00
Executive Construction Manager
32
$135.00
$4,320.00
On -Site Construction Manager
32
$110.00
$3,520.00
Administrative Assistant
24
$81.00
$1,944.00
TOTALS
$24,912.00
TOTAL REIMBURSABLE EXPENSES
ALL TASKS $20,274.87
TOTAL OVERALL BUDGET
ALL TASKS & EXPENSES $45,186.87