Change Order No. 1[7
CHANGE ORDER NO. 1
Monroe County Justice Building
04-016.90
tractor tractDate:
Hewett -Kier Construction, Inc.
May 19, 1986
To: Hewett -Kier Construction, Inc.
1888 N.W. 23rd St. Pompano Beach, Fla. 33069
You are directed to make the changes noted below in the subject contract:
Attest:
Date:
Feature of the Change:
(See Attachment "A")
By:
Char es Dent fierce, erector
Title: Monroe County Public Works Dept.
Approved As To Correctness and
Form
By: ttorney for Monroe County
The changes result in the following a ent of Contract Price and e:
Contract Price Prior to this Change Order: Change Order:
Net (Increase) (iSt141tK!("q) n6 from this
Current Contract Price Including this Chang6 Order:
Contract Time Prior to this Change Order:
Net (Increase) (I1*11V, XA0 Resulting from this Change Order:
Current Contract Time Including this Change Order:
Prepared by: Robert Zuccaro, P.E.
Date: September 29 1986
The Above Changes are Accepted:
Attest: I,r
Date:
GC/t18
Post,
as M4
_
$ 1,620,000.00
79,773.11
270 days
30 days
300 days
an, Inc.
Engineers
ATTACHMENT "A"
MONROE COUNTY JUSTICE BUILDING
CHANGE ORDER NO. 1
(Items 1-7 are those which were deleted from initial bid)
1. Item # 9, add carpet per original bid.
2. Item #10, omit VAT which was substituted for all carpet areas.
3. Item #19, add white oak doors with applied moldings per original bid.
4. Item #22, add HVAC controls per original bid.
5. Item #29, add original concrete drainage trough 2'-4" deep and 16" wide to
collect additional stormwater runoff from existing courthouse parking lot; omit
substituted corrugated slot drain.
6. Item #30, add finished hardware per original bid.
7. Item #31, add light fixtures per original bid.
8. Deduct tax fees and permits.
9. Re -design and install A/C to a split unit system per suggestion of Charles McCoy
and Associates and outlined in previous correspondence/drawings.
10. Add floors, doors, lights in storage rooms created by utilizing split unit A/C
system described in #9 above.
11. Add 8,000 S.F. of hardwood paneling (An allowance of $40 per sheet of paneling
purchase).
12. Re-routing of elevator sump drain lines; omit 3" floor drain and 211 dry vent in
water heater room 101; add drain pan under water heater.
13. Add concrete fill in interior block wall in 1st floor laboratory, storage room and
the 2nd floor armory per request of City of Key West inspector.
14. Additional excavation required due to encountering organic and debris material
from the demolition operations beneath the old U.S.O. building in a location
where it was not possible to obtain pre -design borings.