Change Order No. 5npprov-ed by. 8ocC Oda CHANGE ORDER NO. Project Titles Job No. Monroe County Justice Building 04-016.90 Contractor. Contract Date: Hewett -Kier Construction, Inc. May 19, 1986 Hewett -Kier Construction, Inc. TO: 1888 N.W. 23rd Street Pompano Beach, Florida 33069 You are direc ed to make the changes noted belowVoard bject con tt Attest: �" A yr� n, onroe CountyDate: �o "/g�Q% f County Commissioners Approv d As To Correctness and �/ For Approved By: By: Project Director Attorney for Nlonroe County Nature of the Change: 1. Electrical Connection to Existing Generator. $ 78,619.00 2. Additional work to relocate Existing Panals 16,845.00 necessitated by time delays 3. Conduit, w^re and outlet to U.P.S., 2 paddle 609.39 fan outlets only - requested by user 4. Additional time for work included in this 35 Days Change Order 5. Additional time approved by BCC on May 19, 1987 30 Days The changes result in the following adjustment of Contract Price and Time: Contract Price Prior to this Change Order: $ 1,728,846.99 Net (Increase) (11OXX fOW0 Resulting from this Change Order: 96,070.39 Current Contract Price Including this Change Order: 1,824,917.38 Contract Time Prior to this Change Order: 364 Days . Net (Increase) (I,@XXxg( Resulting from this Change Order: 65 Davs Current Contract Time Including this Change Order: 429 Days Current Contract Completion Date: Auaust 1987 Prepared by: C. Robert Rogers, Jr. Pam, Buc uh & Jernigan, Inc. Mo County C ting Engineers Date:.�a s. y,/987 By: 73t-ert Luccaro,0.Project anaQer The Above iges are Accepted: Attes Cont actor's Representative Date: JUNE 5, 1987 Title: JAMES R. HEWETT. PRESIDENT GC/T76