Change Order No. 1 BOCC May 20, 1997
CHANGE ORDER NO. 1
Project Title: Little Torch Key Roads II Job No. N/A
Contractor: Pavex Corporation Contract Date:
November 12, 1996
Nature of the Change: Adjustment of quantities based upon final field
measurements.
The changes result in the following: Reduce contract amount by
$4,857.30 due to the following changes: See Attached
Prepared and Approve : / -
BY: BY:
/�- '
County Engineer Divis'• •ire•tor
DATE: 7 DATE: -7 .. 7
Approved As to Correctness and Form: �.
By: Date:
Attorney for Monroe County
The above changes are accepted: :_
f -, ` J
Attest: Q•f-� (P .c,1il��t' ca : `'
. . 1---- 1
g' ^"'. BARBARA A. BUCHANAN
_,; • ,a, ••*; MY COMMISSION # CC352293 EXPIRES By .
"'' March 26, 1998
+ '• , � 3 Q c
� '�'fi,���h °,.• � BONDED THRU TROY FAIN INSURANCE, INC . COntraC epresentat e
11
• , ie , _ r 7 Title: Ailo.r c7 C1Ai✓i9G45
sem
-.=
° BOARD OF COUNTY COMMISSIONERS
' ' OF MONROE CO TY, FLORIDA
Atte : DANNY L. KOLHAGE, Clerk
By • /� �
Cle MAY*R/CHAIRMANdf
APPROVED AS TO FOI'M
• . • AL F GA3o
ma y.
ROBERT N. ,oL,FFEE
DATE _ S�" /"
BOCC May 20, 1997
Change Order No. 1 con't.
1) Item 7 - 4" Solid Yellow Strip, Add 2706 LF @ .50 /LF = +1,353.00
2) Item 8 - 4" Skip Strip, Deduct 210 LF @ .60 /LF = (126.00)
3) Item 9 - 4" Solid White Strip, Deduct 165 LF @ .50 /LF= (82.50)
4) Item 10 - 24" Stop Bars, Add 15 LF @ 3.00 /LF = + 45.00
5) Item 12 - RPM's, Add 70 EA @ 4.00 /ea = + 280.00
6) Item 13 - Traffic Signs, Deduct 56 EA @ 225./ea = (12,600.00)
7) Item 19 - Relocate Traffic Sign (New Item), Add 11 Ea
@ 115.00 /ea = +1,265.00
8) Item 20 - Additional Asphalt (New Item), Add 60TN
@ 70.00 /tn = +4,200.00
9) Item 21 - Guardrail Posts, Used (New Item), Credit
for 27 EA @ 6.00 /ea = (162.00)
10) Item 22 - Rip Rap Bags (New Item), Add 126 EA
@ 7.70 /ea = 970.20
Total (4,857.30)
Original Contract Amount = $570,976.80
Final Contract Amount = $566,119.50