1st Change Order 02/03/2012 MEMORANDUM DATE: February 3, 2012 TO: Belle DeSantis, Deputy Clerk 1 • gr.- FROM: Beth Leto, Public Works t RE: CO #1 w/ESSI, Inc. — Energy Retrofit Jackson Square Project Enclosed please find fully- executed original of Change Order No. 001 extending contract time /completion date by thirty (30) days to March 15, 2012, as executed today by Debbie Frederick, Deputy County Administrator, in accordance with Ordinance 026 -1998. Should you have any questions, please feel free to contact me at x4560 or Bob Stone at x6077. bpi cc: Jackie Clynes MONROE COUNTY PUBLIC WORKS Change Order PROJECT: CHANGE ORDER NUMBER: 001 Energy Retrofit — Jackson Square Monroe County DATE: January 26, 2012 CONTRACTOR: PROJECT NUMBER: PWD- 236 -129 -2011 Electronic System Services, Inc CONTRACT DATE: September 21, 2011 5840 Halifax Avenue NOTICE TO PROCEED: October 7, 2011 Fort Myers, Florida 33912 CONTRACT FOR: General Construction THE CONTRACT IS CHANGED AS FOLLOWS: In order to implement certain energy conservation improvements identified through the retro- commissioning process and offset by allowances provided by the Contractor as documented in Field Order No. 1, the contract time is hereby extended by (30) thirty days. The original Contract Sum was $599.000.00 The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was $599.000.00 The Contract Sum will be changed by this Change Order in the amount of $ 0 The new Contract Sum including this Change Order will be $599.000.00 The Contract Time will be increased by (30) thirty days. The date of Final Completion as of the date of this Change Order therefore, is March 15, 2012. NOT VALID UNTIL SIGNED BY THE CONTRACTOR AND THE OWNER Robert A. Stone. MCPW Electronic Systems Services. Inc Monroe County. FL Owner's Representative Contractor Owner 10600 Aviation Blvd. 5840 Halifax Avenue 1100 Simonton Street Marathon. FL 33050 Fort Meyers. FL 33912 Ke Wes FL 33040 Address Address Address BY (Signature) (Sign 'e) 7 'Lure) a - 447/3-- DATE ATE / DATE FIELD ORDER (FO) DATE January 26, 2012 FO# 1 PROJECT Energy Retrofit — Jackson Square To Electronic Systems Service Inc. CONTRACTOR 5840 Halifax Avenue, Fort Meyers, FL 33912 ADDRESS From Bob Stone MCPW OWNER'S REPRESENTATIVE 10600 Aviation Blvd., Marathon, FL 33050 5501 College Road, Key West, FL 33040 ADDRESS DESCRIPTION In consideration of the following allowances: 1. Reuse of existing flex connectors at chiller per RFI #1 2. Reuse of existing butterfly valves at chiller per RFI #1 3. Approval and use of a two compressor chiller vs. use of a specified three compressor chiller 4. $5000.00 allowance as per Spec. Section 15080, Para. 3.5.A Contractor is to supply and install the following efficiency improvements: 1. Duel turbine water flow meter for new chiller per RFI #4 2. Six outside air dampers and control actuators @ Freeman Justice Center as identified through retro commissioning 3. Three static pressure sensors @ Freeman Justice Center as identified through retro commissioning COST IMPACT 0 /4_ co / X-- NAME D TE FIELD ORDER Updated 1/26/12 Field Order Number 1 - Allowance Balance Sheet Allowances Scope Comments Amount Description Reuse existing flex connectors at chiller Existing flex connectors are Flex Connectors RFI#1 $ 510.00 in good condition and were approved for reuse in RFI #1 Reuse existing butterfly valves at Existing butterfly valves are Butterfly Valves $ 1,085.00 in good shape and were chiller- RFI#1 approved for reuse in RFI#1 Specified -Three compressor New McQuay chiller is more Two Compressor Multistack(171K)- Proposed and efficient and weighs less Chiller approved, two compressor McQuay $ 18,000.00 than what was specified (152K)Submittal while providing desired redundancy&capacity Specifications provides for a Spec section 15080,para. 3.5.A calls for $5000 allowance towards Retro-Commissioning $ 5,000.00 a 5,000 contingency post award identified efficiency improvements Energy Efficiency Improvemen s Comments Amount Descri•tion_' Enhanced control and Install Duel Turbine Water Flow Meter Flow Meter for New Chiller RFI #4 $ (5,391.00) monitoring of chilled water flow Install six outside air dampers and Will provide for implementation of specified OS Air Dampers control actuators @ Freeman Justice $ (17,517.00) Center unoccupied control sequence Install three static pressure sensors @ Enhanced air delivery system Static Pressure Sensors $ (1,687.00) Freeman Justice Center and optimize A/H fan control Total $ - MEMORANDUM DATE: JANUARY 26 2011 � /07 ' TO: DENT PIERCE, PUBLIC WORKS DIVISION DIRECTOR Q FROM: BOB STONE, MIDDLE KEY OPERATIONS DIRECTOR -e RE: ENERGY RETROFIT - JACKSON SQUARE Attached for approval is Change Order No. 1, executed by the Contractor and myself for the project referenced above. This is a no cost change order and only extends the final completion date by thirty days while still fitting within the established ARRA Grant time frame. The change order is needed to provide a little additional time for the installation of a few efficiency improvements that were identified during the new chiller installation and the ongoing retro- commissioning process. By working with the Contractor, we were able to secure certain allowances that facilitate the installation of these improvements. The additional time will also provide for proper commissioning of the equipment and systems while allowing time for submission of final payment. Please let me know if there are any questions or more information is desired. Campo -Abra From: Campo -Abra Sent Wednesday, February 01, 2012 3:59 PM To: County Commissioners and Aides Subject Change Order - Jackson Square Attachments: Change Order.pdf Please review the attached Change Order #1 submitted by Electronic System Services, Inc. for Energy Retrofit at Jackson Square. Abra Campo Sr. Administrative Assistant Office of County Administrator The Historic Gato Cigar Factory 1100 Simonton Street, Suite 2 -205 Key West, FL 33040 Office: 305.292.4441 Fax: 305.292.4544 Campo- abra(@monroecounty -fl.gov A Please consider the environment before printing this email. PLEASE NOTE: Florida has a very broad public records law. Most written communication to or from the County regarding County business are public record, available to the public and media upon request. Your e-mail communication may be subject to public disclosure. 1 MEMORANDUM TO: Board of County Commissioners From: Debbie Frederick Deputy County Administrator Date: February 1, 2012 RE: Change Orders Attached is a proposed change order for Electronic System Services, Inc. (Change Order #1 for Energy Retrofit at Jackson Square is for a no cost time extension of thirty days, while remaining within the established ARRA Grant time frame. This will change the date of substantial completion to March 15, 2012. According to Ordinance 026 -1998 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Administrator /Deputy Administrator intends to approve this change order on Thursday, January 26, 2012. 41 Amp: ,. (c1/( IiiiiM ie Frederick Deputy County Administrator DF /ac