Change Order No. 1 BoCC . 0W 19 q CHANGE ORDER NO. 1 Project Title: Job No. N/A Sombrero Beach Restroom - Handicap Addition Contractor: Contract Date: E. G. Braswell Construction, Inc. 3/24/94 Nature of the Change: Add 29 days of contract time. No change in cost. The changes result in the following: A time delay due to lack of manpower and weather. Prepared a Approv d: BY: ElGj BY: Director of ngineering Divisi 'rector o DATE: 7 - ' ' � J� DATE: ?l py 5 T , Approved As to Correctness and Form: T, z z By :p Date: N t_ y fo o e County The above changes are accepted: Attest: E G 61; ASV./ EL Co N INC, • Con p act Representa ve Date: 10 Pk Title: ESIi ENfl Approved: BOARD OF COUNTY COMMISSIONERS OF MONROE COUNTY, FLORIDA Attest: DANNY L. KOLHAGE, Clerk i \ I Cl rk MAYOR /CHAIRMAN • ■ E. G. Braswell Construction' 1"c. STATE CERTIFIED GENERAL CONTRACTORS C:GC' 046370 5640 LAUREL AVENUE KEY WEST, FLORIDA 33040 (305) 296 -0305 hax: (305) 296-1824 August 18, 1994 Engineering Department 5100 College Road Key '<est, l 33040 PE: Sombrero Beach Restroom Dear . Peacock: I am writing to address the lack of progress on the remodeling project at the Sombrero Teach Restrooms. This company has suffered from a lack of manpower all summer. A check of the Classified Ad section of the Key est Citizen will show that we have continuously run help wanted ads. ' The torential rains during the month of 'August impacted significant- ly on our scheduling. As you know, the plumbing has been roughed in. The toilet partitians have been ordered from Global lid-South Janufacturing moo. of '.'iiami. 'e will have a crew on site on August 22, 1994 and will see that the project is manned until completion. S' n ere y, , : g ;� . �, .sw EGJ /chb