Change Order No. 1 BoCC . 0W 19 q
CHANGE ORDER NO. 1
Project Title: Job No. N/A
Sombrero Beach Restroom - Handicap Addition
Contractor: Contract Date:
E. G. Braswell Construction, Inc. 3/24/94
Nature of the Change: Add 29 days of contract time. No change in
cost.
The changes result in the following: A time delay due to lack of
manpower and weather.
Prepared a Approv d:
BY: ElGj BY:
Director of ngineering Divisi 'rector o
DATE: 7 - ' ' � J� DATE: ?l py 5 T ,
Approved As to Correctness and Form: T,
z z
By :p Date: N t_
y fo o e County
The above changes are accepted:
Attest: E G 61; ASV./ EL Co N INC, •
Con p act Representa ve
Date: 10 Pk
Title: ESIi ENfl
Approved:
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
Attest: DANNY L. KOLHAGE, Clerk
i \ I
Cl rk MAYOR /CHAIRMAN
•
■
E. G. Braswell Construction' 1"c.
STATE CERTIFIED GENERAL CONTRACTORS C:GC' 046370
5640 LAUREL AVENUE KEY WEST, FLORIDA 33040 (305) 296 -0305
hax: (305) 296-1824
August 18, 1994
Engineering Department
5100 College Road
Key '<est, l 33040
PE: Sombrero Beach Restroom
Dear . Peacock:
I am writing to address the lack of progress on the remodeling project at the Sombrero
Teach Restrooms. This company has suffered from a lack of manpower all summer. A check
of the Classified Ad section of the Key est Citizen will show that we have continuously
run help wanted ads. ' The torential rains during the month of 'August impacted significant-
ly on our scheduling.
As you know, the plumbing has been roughed in. The toilet partitians have been ordered
from Global lid-South Janufacturing moo. of '.'iiami.
'e will have a crew on site on August 22, 1994 and will see that the project is manned
until completion.
S' n ere y,
, : g ;� . �, .sw
EGJ /chb