Loading...
1st Change Order 04/17/2013M E M O R A N D U M DATE: April 9, 2013 TO: Pam Hancock, Deputy Clerk FROM: Beth Leto, Public Works RE: CO #1 w/Keys Contracting, Inc. Enclosed please find fully- executed original of Change Order No. 001 extending contract time /completion date by one hundred eighty nine (189) days to Feb. 19, 2013, as executed today by Debbie Frederick, Deputy County Administrator, in accordance with Ordinance 026 -1998. Should you have any questions, please feel free to contact me at x4560. bpl cc: Jackie Clynes MONROE COUNTY PUBLIC WORKS CONTRACT CHANGE ORDER PROJECT TITLE: On -Site Sewer Connections at Harry Harris Park, Tavernier Fire Station, and Old Tavernier School TO CONTRACTOR: The Contract is changed as follows: CHANGE ORDER NO: 1 INITIATION DATE: 08M412012 CONTRACT DATE: 05/18/2012 The original Contract Sum. ............ . . .. ............................... .....................$44,300.00 Net change by previously authorized Change Orders .................... . ............... $ 0.00 The Contract Sum prior to this Change Order was .................... .....................$44,300.00 The Contract Sum will be increased by this Change Order ............. . ................$ 0.00 The new Contract Sum including this Change Order is .............. .....................$44,300.00 The Contract Time will be increased by .............. y The date of Substantial Completion as of the date of this Change Order is ... .... 0211912013 Detailed description of Change Order and justification: As a result of permitting delays from multiple agencies, notice to proceed was not able to be given until 08/1412012; therefore, a time extension of 188 days from date of notice to proceed was required to complete the project. PUBLIC WORKS/ENGINEERING DIVISION DI Date COUNTY/DEPUTY ADMINISTRATOR: �. C/ t- � (rjC I-IMIa ADMINISTRATOR, BUILDINGS & PARKS �3 RoYrt�Glassm� Date MEMORANDUM TO: Board of County Commissioners From: Debbie Frederick Deputy County Administrator Date: April 8, 2013 RE: Change Orders Attached is a proposed change order for Keys Contracting Services, Inc., for the On -site Sewer Connections at Harry Harris Park, Tavernier Fire Station and old Tavernier School. Change Order #1 is for a no -cost time extension of 189 days due to permitting delays from multiple agencies. According to Ordinance 026 -1998 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Administrator /Deputy Administrator intends to approve this change order on Tuesday, April 9, 2013. _ e bbie Frederick Deputy County Administrator DLF: adc Campo -Abra From: Campo -Abra Sent: Monday, April 08, 2013 1:55 PM To: County Commissioners and Aides Subject: Change Order - On -site Sewer Connections at Harry Harris Park Attachments: Change Order.pdf Please review the attached Change Order #1 submitted by Keys Contracting Services, Inc. for the On -site Sewer Connections at Harry Harris Park. If you have any questions regarding this change order please direct them to Ann Riger in Project Management at 295- 4439. Abra Campo Sr. Administrative Assistant Office of Monroe County Administrator The Historic Gato Cigar Factory 1100 Simonton Street, Suite 205 Key West, FL 33040 Office: 305.292.4441 Fax: 305.292.4544 camao- abra@monroecou ntv -fl.00v `,A Please consider the environment before printing this email. PLEASE NOTE: Florida has a very broad public records law. Most written communications to or from the County regarding County business are public record, available to the public and media upon request. Your e-mail communication may be subject to public disclosure.