Loading...
6th Change Order 06/07/2013.op, CouN'I'Y /ENGINEERING / PROJECT MANAGEMENT , ROJECT TITLE: Renovation and Addition of Fire Station ##17 In Conch Key TO CONTRACTOR: Pedro Falcon Electrical Contractors, Inc. 31150 Avenue C Big Pine Key, FL 33043 The Contract is changed as follows: CHANGE ORDER NO: 6 INITIATION DATE: May 30, 2013 CONTRACT DATE: September 21, 2011 The original (Contract Sung) (Guaranteed Maximum Price)...... S1,695,000.00 Net change by previously authorized Change Orders ......... ................ .......................... S 250,127.53 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was .............$1,945,127.53 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ....... $ 2,864.00 The new ( Contract SE�[M) (Guaranteed Maximum Price) including this Change Order is ....... $1,947,991.53 The Contract Time will be (increased) (decreased) (unchanged) by ... ............................... 14 Days The date of Substantial Completion as of the date of this Change Order is ...................... June 26, 2013 Detailed description of change order and justification: Furnish and install a 13oof Drain or the g2 i t g - Loot _ I t was discovered during construction that the gxistina roof held water. The roof drain is to help eliminate the accumulation of water on the roof CONTRACTOR: al Elect Cont 06!0 e ' r tors, Inc. Date DIRECTOR OF PROJECT MANAGEMENT: David it Date DIRECTOR PUBLIC WORKS /ENGINEERING (941Q'� (3 K vin Wilson Date COUNTY /DEPUTY ADMINISTRATOR Roman Gastesi /Debbie Frederick Date A \ (.() / -7/1 c mg oiiirI :.u;u . .3 u,u.,tur C Pedro Falcon Electrical Contractors, Inc. .31160 Avenue C, Big Pine Kiy, F1, 33043 -4516 (,705)872-2200 • Fax(305)872-2219 • falconel(a CGC: 1507617 i EC0001491 i EC13003416 Request for Change Order 30 May 2013 Project: Conch Key Fire Station No. 17 Change Order Request No: Six Description: Provide Roof Drain at Existing Roof Provide Roof Drain Bob Hi) son & Company Add the Sum of :............................................ ............................... $ L 2 � )8.00 Additional Project Management for Above Items PFEC Addthe Sum of :........................ ............................... .......................$300.0() SUBTOTAL ALL OF THE ABOVE: ................................................... $2, 98.00 Industrial • Commercial • I'nsti'tutional • Utility Established 1985 OH &P Overheadat 5% ................................................. ............................... ........................$130.00 Subtotal...................................................... ............................... $ 2,728.00 Profitat 5% ........................................................ ............................... ........................$136.00 Permit Fees and Design Drawings are Not Included in this proposal other than as reimbursement for fees already paid by PFEC. If additional permit fees are required the Owner is to pay for all permit fees. If Design Drawings are required then the Owner is to supply Design Drawings. Net Amount of Request for Change Order: ................................................... S2,864.00 Additional Time .Requested for Change: 2 Weeks (14 Calendar Days). Respectfully Submitted, Ken Bygler Project Manager 8UB I L S N ROOFING & SHEET METAL 522 W. Mowry Drive Homestead, FL 33030 P.O. Box 901543 Homestead, FL 33090 305 - 246 -0209 305 -248 -1982 Fax Monroe: 305 -451 -2927 COMMERCIAL t RESIDENTIAL • REROOFING • ROOF REPAIRS • NEW ROOFING METAL ROOFING • WATER PROOFING • ROOF MAINTENANCE LICENSED & INSURED SERVING DADE BROWARD AND FLORIDA KEYS CC 0,057388 CCC1328538 H12573 May 22, 2013 To: Pedro Falcon Contractors • Project Name: Conch Key Firc Station • Project Location: S Conch Ave Conch Key FL Change order #1 Provide labor and material to install one roof drain to improve drainage at the lower nat Price for the above scope of work - $2,298.00 Note: Above installation is based upon the approval of the local building official. Mick Cronie 4 Cell # ( 786) 357 -7017 Bob Nilson & Co. Inc. www.bobhilson.com Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Water retention on the roof was discovered during construction. The installation of a roof drain will reduce the water retention. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: rA MEMORANDUM TO: Board of County Commissioners From: Teresa Aguiar Acting County Administrator Date: June 5, 2013 RE: Change Orders Attached is a proposed change order for Pedro Falcon Electrical Contractors, Inc. for the Renovation and Addition of Fire Station #17. Change Order #6 is for $2864.00 to furnish and install a roof drain on the existing roof. According to Ordinance 026 -1998 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Administrator /Deputy Administrator intends to approve this change order on Friday, June 7, 2013. C Teresa Aguiar Acting County Administrator TA: adc Campo -Abra From: Campo -Abra Sent: Thursday, June 06, 2013 8:53 AM To: County Commissioners and Aides Subject: Change Order - Fire Station #17 in Conch Key Attachments: Change Order.pdf Please review the attached Change Order #6 submitted by Pedro Falcon Electrical Contractors, Inc. for Fire Station #17. If you have any questions please refer them to Ann Riger at 295 -4439 or riser- ann @monroecounty- fl.sov Abra Campo Sr. Administrative Assistant Office of Monroe County Administrator The Historic Gato Cigar Factory 1100 Simonton Street, Suite 205 Key West, FL 33040 Office: 305.292.4441 Fax: 305.292.4544 camoo- abra(c'bmonroecounty -fl.aov `. Please consider the environment before printing this email. PLEASE NOTE: Florida has a very broad public records law. Most written communications to or from the County regarding County business are public record, available to the public and media upon request. Your e -mail communication may be subject to public disclosure.