Item E5 Cudjoe Status
June 2013
(snapshot at 18 June 2013):
Finances
FKAA
Advances to date $17.5 million
Expenditures to date
- Fully processed against advances $3.5 million
- "in process" w /in County $4.6 million
- "in process" /expected in June at FKAA $3.0 million
Subtotal Expenditures $11.1 million
Projected:
June 2013 Advance scheduled per ILA $16.0 million
Forecast 3 Quarter Expenditures $15.4 million
•
•
Construction
WWTP Ash excavation at Transfer Station nearly complete
Inner Islands Giannetti mobilized; approximately 5 miles of pipe laid
Outer Islands Layne team mobilized; final design underway
CEI FKAA / CH2MHi11
•