2014-001 Sewer Force Main 07/16/2014T 4 n •
TASK ORDER NO. 2014-001 TO
MASTER SERVICES AGREEMENT
BETWEEN
OWNER AND ENGINEER
II, .�
This is Task Order No. 2014 -001 dated J V �Lu 1, 2014 attached to and made part of the Master Services
Agreement dated January 19, 2012, between CDM Smith Inc. (ENGINEER) and Monroe County (OWNER).
This Task Order describes the Scope of Services, Time Schedule, Charges, and Payment Conditions for the Task
Order known as:
Marathon Airport Terminal Sewer Laterals — Construction Administration Services (the "Project ")
1. Scope of Services
ENGINEER shall provide for OWNER the following specific Services:
See attached Exhibit `A'
2. Time Schedule
The time periods for the performance of ENGINEER'S Services are as follows:
270 days from Execution of this task order.
3. Compensation and Invoicing
Compensation for Services of Engineer described in this Task Order will be on the following basis:
Lump sum amount of $69,510 (see attached Exhibit `B')
4. Terms and Conditions
The terms and conditions of the Agreement referred to above shall apply to this Task Order except to the extent
expressly modified herein. IN the event of any such modification, the modification shall be set forth below and
the Article of the Agreement to be modified shall be specifically references. Modifications included in this Task
Order are:
N/A
7/2008 Page 1
Task Order — Master Services Agr.
Marathon Airport Terminal Sewer Lateral — Construction Administration Services
Task Order No. 2014 -001
June ,2014
r
Acceptance of the terms of this Task Order is acknowledged by the following authorized signatures of the parties to the
Agreement:
OWNER
M
Title: W a4,j p ►-
EN
d� G
U
Title: I ' " A U c) GI ATf
7/2008
Task Order — Master Services Agr.
,l
Page 2
Marathon Airport Terminal Sewer Lateral - Construction Administration Services
Task Order No. 2014 -001
June ,2014
Exhibit'A' to
Task Order No. 2014 -001
Florida Keys Marathon Airport
Marathon Airport Terminal Sewer Force Main Connection
Construction Administration Services
This Authorization, when executed, shall be incorporated in and become part of the Agreement for
Professional Services between the Monroe County (OWNER), and CDM Smith Inc. (ENGINEER), dated
January 19,2012 hereafter referred to as the Agreement.
PROJECT BACKGROUND
OWNER has requested that ENGINEER provide construction administration and supervision services for
the construction of the system to connect the existing Marathon Airport Terminal Building (TB) to the
central sewer system.
SCOPE OF WORK
A wastewater pump station pumps wastewater from the Marathon Airport Terminal Building to a
wastewater treatment facility with an effluent disposal injection well. The OWNER is abandoning the
existing treatment facility and sending the TB wastewater to the central City of Marathon sewer force
main. The force main is located in the Monroe County Right of Way adjacent to the Highway 1 Right of
Way, which runs along the front of the TB.
TASK 1 ENGINEERING SERVICES DURING CONSTRUCTION
The ENGINEER will provide engineering services during construction as specified below and intends to
contract with a qualified Minority Business Enterprise (MBE) subcontractor to provide a project
representative (PR) for construction observation services. The ENGINEER will provide the following
services:
Subtask 1.1- Construction Progress Meetings
The ENGINEER will prepare for and conduct a preconstruction meeting for the project within three
weeks of construction contract award. The ENGINEER will prepare for and attend three additional
progress or special purpose meetings during the anticipated six (6) month project duration to Final
Acceptance. It is anticipated that one of the special purpose meetings will be a substantial completion
inspection.
Subtask 1.2 - Shop Drawing Review
The ENGINEER will review shop drawing submittals for compliance with the requirements of the
Contract Documents. Ten submittal reviews are budgeted for this project. A single re- submittal of each
rejected shop drawing will be counted within the ten shop drawing reviews conducted for this task.
CPM Page 1 of 4
3/21/14
Subtask 1.3 - Construction Observation and Requests for Information
The ENGINEER will provide construction observation during the anticipated four (4) months of actual on-
site construction during the five (5) month construction period. These services include:
• Three (3) six (6) hour days per week by the PR (up to 48 days) including startup services and
substantial and final acceptance walk through.
• PR will provide an electronic report of each site visit with status photographs and a summary of
project activity.
• Responses to up to Five (5) Requests for Information (RFIs) from the contractor.
Subtask 1.4 - Well Abandonment Observation
The ENGINEER will supply a qualified staff to observe the existing injection TB effluent disposal well
abandonment activities for a total of two (2) 8 -hour days to verify that the abandonment specifications
are adequately followed by the contractor.
Subtask 1.5 - Project Final Acceptance /Closeout
• The ENGINEER will provide closeout services including the following:
• Recommendation of Final Acceptance Payment to Contractor
• Permit Closeout
• Review of record drawings (a total of two reviews) provided by the contractor, produced by an
OWNER approved surveyor.
TASK 2 - PROJECT MANAGEMENT AND QUALITY CONTROL
Subtask 2.1- Project Management
The ENGINEER's project manager will prepare and submit monthly written status reports for an
anticipated project life of five (5) months. This task also includes monthly internal project status review
meetings.
Subtask 2.2 - Quality Control (QC) Technical Review
The ENGINEER maintains a QC program on all of our projects. Activities performed under this task
consist of those generally administrative functions required to maintain the project on schedule, within
budget, and that the quality of the work products defined within this scope is consistent with the CDM
Smith's quality management system.
DATA OR COORDINATION BY OWNER
1. Coordination with TB and other airport tenants for potential access and brief service interruption
issues
2. Information about current and future use of the TB
3. Information on existing wet well pumps
CStfjith Page 2 of 4
3/21/14
4. Copies of existing TB facility environmental permits
ASSUMPTIONS
The following are assumptions this scope of work is based on, and any variations thereof may require a
scope and fee modification:
1. As this is work on an existing system, unanticipated circumstances (e.g., environmental
contamination, differing site conditions, etc.) may require a change to the scope and fee.
2. If additional on -site inspection is required by the FAA or other funding or permitting agency, a
modification to the scope and fee for this Task Order may be required.
Total construction period from Notice to Proceed (NTP) to Final Acceptance is five (5) months.
4. Airport staff will manage day -to -day coordination tasks with contractor for access, etc.
DELIVERABLES
The ENGINEER will provide the following deliverables. In addition to each format listed, the ENGINEER
will provide each deliverable in Adobe PDF® format via email. If format is not listed, only Adobe PDF®
electronic document is provided
• Pre- construction meeting minutes
• One hard copy of each reviewed submittal
• A status report for each construction visit
• Responses to Request for Information by the contractor
• One hard copy of the substantial completion inspection punch list
• Electronic Review comments for contractor - produced record drawings
• Project status report monthly
TIME OF COMPLETION /SCHEDULE
The ENGINEER will commence work within seven (7) days of a written notice to proceed from the
OWNER.. The estimated overall time for construction is five (5) months.
COMPENSATION AND PAYMENT
For the basic services performed under this Scope of Work, the OWNER agrees to pay the ENGINEER the
lump sum fee of $ 69,510. Partial payment to be made on a monthly basis in proportion to the
percentage of work completed. For invoice purposes only the value of each task is as shown in Table 1.
The ENGINEER will submit monthly written status reports to accompany each invoice.
CPM Page 3 of 4
3/21/14
Table 1: For Invoice Purposes Only
Task No.
Task Description
Task Value
1
Engineering Services During Construction
$ 59,540
2
Project Management, and Quality Control
$ 9,970
Total Lump Sum
$ 69,510
With Page 4 of 4
3/21/14
Exhlbit'B'
FLORIDA KEYS MARATHON AIRPORT
TERMINAL SEWER LATERAL - CONSTRUCTION SERVICES
LABOR AND NON -LABOR PROJECT COST ESTIMATE
31312014
Officer
$200 /Hour
MH $
Principal / Associate
$180 /Hour
MH $
Senior
Professional
$155 /Hour
MH $
Professional II
$135 /Hour
MH $
Professional I
$120 /Hour
MH $
CADD Supervisor
$ 125 /Hour
CADD Operator
$ 85 /Hour
Administration
$85 /Hour
MH $
Labor Totals
MH $
TASK 1 ENGINEERING SERVICES DURING
CONSTRUCTION
Task 1.1 - Construction Progress Meetings
0
$0
24
$4,320
0 $0
0
$0
0
$0
0
$0
0
$0
2
$170
26
$4,490
Task 1.2 - Shop Drawing Review
0
$0
6
$1,080
0 $0
0
$0
28
$3,360
0
$0
0
$0
8
$680
42
$5,120
Task 1.3 - Construction Observation /RFIs
0
$0
8
$1,440
0 $0
0
$0
20
$2,400
0
$0
0
$0
4
$340
32
$4,160
Task 1.4 - Well Abandonment Observation
0
$0
0
$0
16 $2,480
0
$0
0
$0
0
$0
0
$0
2
$170
18
$2,650
Task 1.5 - Project Final Acceptance /Close -out
0
$0
8
$1,440
0 $0
0
$0
16
$1,920
0
$0
0
$0
4
$340
28
$3,700
$20,140
Subtotal Task 1 Services
TASK 2 - MEETINGS, PROJECT MANAGEMENT
AND QUALITY CONTROL
Task 2.1 - Project Management
0
$0
32
$5,760
0 $0
0
$0
0
$0
0
$0
0
$0
6
$570
38
$6,270
Task 2.2 - Quality Control (QC) Technical Review
4
$800
8
$1,440
4 $620
2
$270
0
$0
0
$0
0
$0
2
$170
20
$3,300
$9,570
Subtotal Task 2 Services
TOTAL LABOR
4
$800
86
$15,480
20 $3,100
2
$270
0
$0
0
$0
0
$0
28
$2,380
204
$29,710
2.7%
52.1%
10.4%
0.9%
0.0%
0.0%
0.0%
8.0%
OTHER DIRECT COSTS (ODC'S)
$3,100
Travel & Subsistence
$1,100
Reproduction, Equipment & Software
400
Communications
$4,600
TOTAL ODC's:
$ 36,200
OUTSIDE PROFESSIONAL (RPR)
$69,510
GRAND TOTAL FEE