3rd Change Order 10/28/2016 MEMORANDUM DATE: November 1, 2016 TO: Cheryl Robertson, Deputy Clerk FROM: Beth Leto, KWIA RE: CO#3 -Douglas N. Higgins, Inc. Enclosed please find the fully-executed original of no-cost Change Order #3 increasing substantial completion by 60 days to December 22, 2016, for the Marathon Airport-T-er-minal) Force Main-C-ormection-and Tenant-Sewer Le`ra1 P_zojectp The change order was executed by County Administrator Roman Gastesi on 10/28/16 in accordance with Ordinance 004-1999. Should you have any questions, please feel free to contact me at x5239. cc: Don DeGraw T.J. Henderson Pedro Mercado John Chandler Paul Waters Ernie Coughlin Bill Chase r1• N 0 x? 4f • MONROE COUNTY /FLORIDA KEYS MARATHON INTERNATIONAL AIRPORT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 3 Marathon Airport Terminal Force Main Connection and INITIATION DATE: October 23, 2016 Tenant Sewer Lateral Project CONTRACT DATE: October 21, 2015 TO CONTRACTOR: Douglas N. Higgins, Inc. 3390 Travis Pointe Rd. Suite A Ann Arbor, MI 48108 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price) $273,130.00 Net change by previously authorized Change Orders .$ -0- The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was $273,130.00 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order $ -0- The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is $27 0 00 The Contract Time will be (increased) (decreased) (unchanged) by days The date of Substantial Completion as of the date of this Change Order is December 22. 2016 Detailed description of change order and justification: No cost time extension of 60 days required due to delivery of eg-uipment and parts for the Main Pump Station and the decommission of the existing system. The no cost time extension takes the substantial completion date from October 23. 2016 to December 22. 2016. This change Order is 0.0% of the original contract price. Not valid until signed by Owner, Architect (if a • plicable), and Contractor '' / f 27/ Zo /G ARCHITECT: — i ' D iY i� ate CONTRACTOR: `---`'~ 4 L 4 `bj�°�' - ` J L D oD•las N. iggins, Inc. ate 4_ 1 0 L DIRECTOR OF AIRPORTS: _ _.• x. a* Donald De I Date COUNTY /ASSISTANT ADMINISTRATOR: / t>7' I ) S° Roman G stesi Date Kevin E. Wilson Christine Hurley Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ❑ No If Yes, explanation: • Change Order was included in the original specifications. Yes ® No ❑ If Yes, explanation of increase in price: Additional time only. No additional costs. • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Knight-Cary From: Paul Waters <paulw@dnhiggins.com> Sent: Wednesday,October 26, 2016 3:09 PM To: Knight-Cary; Henderson-Thomas Subject: MTH Sewer Laterals Change Order-Time Extension Subject:MTH Sewer Laterals Change Order=Time Extension Mr.Thomas Henderson DN Higgins, Inc. is requesting a 60 day no cost contract extension moving the substantial completion date from October 23, 2016 to December 22,2016.The delay is due to the delivery of equipment and parts for the Main Pump Station. Thanks you. Paul R.Waters Regional Manager-Florida Keys Douglas N Higgins, Inc. 5509 5th Ave.#3 Key West, FL 33040 • paulwna.dnhiggins.com Cell: 305-797-1019 Office: 305-292-7889