Item E�4_
Cudjoe Status
January 2014
(Snapshot at January 10, 2014)
Finance Status
FKAA
Advances to date $33.5 million
Invoiced for 14 January 2014 $10.0 million
Expenditures to date
-Fully processed against advances $14.4 million
- "in process" w /in County $ 11.2million
Subtotal Expenditures $ 25.6 million
Advance Balance on hand
$ 7.9 million
1IPage
CURRENT STATUS REPORT
(As of January 10, 2014)
CUDJOE REGIONAL WASTEWATER PROGRAM
1. Inner Islands' Collection
System
2. Advanced Wastewater
Treatment Facility
3. Outer Islands' Collection
System
4. Public Information
Meetings
5. On -Site Systems
Wharton -Smith continues concrete work on major structures.
Electric and yard piping continue. Drilling of effluent injection
wells initiated.
Action: Complete structural work and site utilities Complete
4 injection wells for effluent disposal.
FKAA continues to schedule meetings with the public and
interested groups to provide project status and to receive input.
Website updates ongoing.
Other Big Pine Key meetings delayed until redesign of new
gravity areas has been developed.
21 Page