03rd Amendment 07/15/2015AMY REAVIIIN, CPA
CLERK OF CIRCUIT COURT &COMPTROLLER
MoxnaE couxrr, FLORIDA
DATE: August 18, 2015
TO: Roman Gastesi
County Administrator
ATTN.• Rhonda Haag
Sustainability Program Manager
FROM: Cheryl Robertson Executive Aide to the Clerk of Court & Comptroller JA1 1J01xXisu-4
At the July 15, 2015, Board of County Commissioner's meeting the Board granted approval and
execution of the following Item R6 Revision to Amendment No. 3 to the contract with AMEC Foster
Wheeler Environment and Infrastructure, Inc. in order to clear up inconsistencies in attachments. This
amendment attaches corrected exhibit dates, and corrects scrivener's errors at no cost to the County.
Enclosed is a duplicate original of the above - mentioned for your handling. Should you have any
questions, please feel free to contact our office.
cc: County Attorney
Finance
File ✓
-- N c Sc g 1d 1 A �
500 Whitehead Street Suite 101, PO Box 1980, Key West FL 33040 Phone: 305 -295 -3130 Fax: 305- 295 -3663
3117 Overseas Highway, Marathon, FL 33050 Phone: 305- 289 -6027 Fax: 305 - 289 -6025
88820 Overseas Highway, Plantation Key, FL 33070 Phone: 852 -7145 Fax: 305- 852 -7146
AMENDMENT NO. 3
TO THE CONTRACT
FOR
ENGINEERING, DESIGN AND PERMITTING SERVICES
FOR THE
CANAL DEMONSTRATION PROJECTS
THIS AMENDMENT NO. 3, dated =" is entered into between the County and
the CONSULTANT, to the Contract For Engineering, Design And Permitting Services,
dated the 21' day of May, 2014, as amended February 18, 2015 and September 17, 2013,
between Monroe County Board of County Commissioners, "COUNTY," and AMEC
Foster Wheeler Environment & Infrastructure, Inc., "CONSULTANT ".
WITNESSETH:
WHEREAS, much work has been performed under the Contract and the three largest
projects are underway; and
WHEREAS, a no cost six month time extension is required to allow time to complete the
design and construction administration of the remaining authorized projects; and
WHEREAS, the amount of the CONTRACT remains unchanged.
NOW, THEREFORE, in consideration of mutual promises, covenants and contracts stated
herein, and for other good and valuable consideration, the sufficiency of which is hereby
acknowledged, COUNTY and CONSULTANT agree as follows:
1. Article 2.1.2 is hereby DELETED and REPLACED with the following:
2.1.2 This CONTRACT is effective on the 21S day of May, 2014 and shall
extend through December 31, 2015. The CONSULTANT shall provide the
deliverables as specified in Exhibit A -3 "Revised Deliverable Schedule" and shall
submit invoices following Exhibit B "Schedule of Values ".
2. The total contract value between CONSULTANT and County remains unchanged at
$655,639.78.
{REMAINDER OF THIS PAGE LEFT INTENTIONALLY BLANK)
Page 1 of Amendment No. 3
IN WITNESS WHEREOF, each party caused this AMENDMENT NO. 3 to be executed
by its duly authorized representative on the day and year first above written.
MONROE COUNTY ATTORNEY
PP ,Ov'EO AS T ORM:
7 NATiLE NE W. CASSEL
ASSIS ?ANT COUP / ATTORNEY —
Da'e
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
By: .•
Mayor Ch ' an
AMEC FOSTER WHEELER
i
ENVIRONMENT &
STATE OF FLORIDA
COUNTY OF
On this 2 � day of v C , 20(�, before me the undersigned notary public,
Personally appeared 0 2!� Z , known to me to be the
Person whose name is bscribed above or who produced
As identification, and acknowledged that he /she is the person who executed the
above Amendment #3 to Engineering and Design agreement with Monroe County
for the purposes therein contained.
�� ..•••'� MAGGIE PROENZA- KANAKIS
.err 4
By:--A 4 Notary Public - State of Florida
Print Name
My commission expires: 24 Z Seal
Page 2 of Amendment No. 3
Date: e6 - .2 P ��
Exhibit A -3 Revised Deliverable Schedule
Page 3 of Amendment No. 3
Exhibit A -3 Revised Deliverable Schedule
Canal
Task
Original Contract
Revised Contract
Completion Date
Completion Date
Canal #266 Big
Task 1: Additional Data
90 days from NTP
August 31, 2015
Pine Key
Collection/Processin
Task 2: Preliminary
90 days from NTP
August 31, 2015
Design - 30% Documents
Task 3: Permitting
135 days from NTP
October 30, 2015
Task 4: 60% Construction
120 days from NTP
October 30, 2015
Documents
Task 5: 100%
225 days from NTP
October 30, 2015
Construction Documents
Com letion Submittal
Task 6: Bid Support
300 days from NTP
October 30, 2015
Task 7: Construction
Not specified
December 31, 2015
Support Services and
Engineering During
Construction
Canal #287 Big
Task 1: Additional Data
90 days from NTP
August 31, 2015
Pine Key
Collection/Processin
Task 2: Preliminary
90 days from NTP
August 31, 2015
Design - 30% Documents
Task 3: Permitting
135 days from NTP
October 30, 2015
Task 4: 60% Construction
120 days from NTP
October 30, 2015
Documents
Task 5: 100%
225 days from NTP
October 30, 2015
Construction Documents
Com letion Submittal
Task 6: Bid Support
300 days from NTP
October 30, 2015
Task 7: Construction
Not specified
December 31, 2015
Support Services and
Engineering During
Construction
Canal #290
Task 1: Additional Data
90 days from NTP
May 29, 2015
Big Pine Key
Collection/Processin
Task 2: Preliminary
90 days from NTP
May 29, 2015
Design - 30% Documents
Task 3: Permitting
135 days from NTP
May 29, 2015
Task 4: 60% Construction
129 days from NTP
May 29, 2015
Documents
Task 5: 100%
225 days from NTP
June 30, 2015
Construction Documents
Com letion Submittal
Task 6: Bid Support
300 days from NTP
October 30, 2015
Task 7: Construction
Not specified
December 31, 2015
Support Services and
En inee ing Durin
Page 1 of Amendment No. 3 Exhibit A -3
Note: NTP = Notice to Proceed which for the original contract was May 21, 2014
Page 2 of Amendment No. 3 Exhibit A -3
Construction
Canal #459 Geiger
Task 1: Additional Data
90 days from NTP
December 31, 2015
Key
Collection/Processin
Task 2: Preliminary
90 days from NTP
December 31, 2015
Design - 30% Documents
Task 3: Permitting
135 days from NTP
December 31, 2015
Task 4: 60% Construction
120 days from NTP
December 31, 2015
Documents
Task 5: 100%
225 days from NTP
December 31, 2015
Construction Documents
Com letion Submittal
Task 6: Bid Support
300 days from NTP
December 31, 2015
Task 7: Construction
Not specified
December 31, 2015
Support Services and
Engineering During
Construction
Canal #277 Big
Task 1: Additional Data
90 days from NTP
October 30, 2015
Pine Key
Collection/Processin
Task 2: Preliminary
90 days from NTP
October 30, 2015
Design - 30% Documents
Task 3: Permitting
135 days from NTP
November 30, 2015
Task 4: 60% Construction
120 days from NTP
November 30, 2015
Documents
Task 5: 100%
225 days from NTP
November 30, 2015
Construction Documents
Com letion Submittal
Task 6: Bid Support
300 days from NTP
December 31, 2015
Task 7: Construction
Not specified
December 31, 2015
Support Services and
Engineering During
Construction
Canal #29 Key
Task 1: Additional Data
90 days from NTP
May 29, 2015
Largo
Collection/Processin
Task 2: Preliminary
90 days from NTP
Design - 30% Documents
Task 3: Permitting
135 days from NTP
May 29, 2015
Task 4: 60% Construction
120 days from NTP
May 29, 2015
Documents
Task 5: 100%
225 days from NTP
October 30, 2015
Construction Documents
Com letion Submittal
Task 6: Bid Support
300 days from NTP
November 30, 2015
Task 7: Construction
Not specified
December 31, 2015
Support Services and
Engineering During
Construction
Overall Project
12 months after NTP
July 15, 2015
Management
Note: NTP = Notice to Proceed which for the original contract was May 21, 2014
Page 2 of Amendment No. 3 Exhibit A -3
Exhibit B
Schedule of Fees
(Note: This Exhibit B has not changed from the original contract
it is attached here so that the reference to Exhibit B will not
cause concern that an Exhibit is missing form the Amendment #3)
131Page
AMEC ENVIRONMENT & INFRASTRUCTURE, INC
2014 SCHEDULE OF FEES
(STANDARD A)
Personnel
A. Professional (Engineer, Geologist, Scientist and Project Management)
Staff I
$71.00 /hour
Staff 11
$77.00 /hour
Project
$86.00/hour
Senior
$109.001hour
Principal lPro ect Manager
$155.001hour
Senior Principal/Senior Project Mana er
$159.00/hour
Chief Engineer/Scientist
$194.00 /hour
8. Technical Services (Engineering and Science)
Technician I
$45.001hour
Technician II
$55.00/hour
Senior Technician I
$60.00/hour
Senior Technician II
$70.00/hour
Project Administrator/Project
Coordinator /Subcontract AdmiNstrator /Project
Accountant
$75.00/hour
Technical Writer /Document Processor
$78.00/hour
CADD /Drafts erson includes PC/CAD I
$66.001hour
CADD/Drafts rson includes PC/CAD 11
$101.00/hour
Admin I
$40.00 /hour
Admin II
$52.001hour
C. Surveying Services
Field Surveyor I
$43.00/hour
Field Surveyor 11
$47.00lhour
Survey Technician I
$67.00/hour
Survey Technician 11
$72.00/hour
Survey Party Chief
$75.001hour
0. Information Management
Software Engineer
$92.00/hour
Data Technician
$132.00 /hour
Senior Software Engineer
$162.001hour
Business Analyst
$132.00 /hour
AMEC ENneoNMENT & INFRASTRUCTURE, INC
2014 SCHEDULE of Fees
(STANDARD A)
PAGE 2
E. Contract Labor
From time to time, AMEC retains outside Professional and Technical labor on a
temporary basis to meet peak workload demands. Such contract labor will be charged at a 10%
markup..
II. Expenses
A. Travel Expenses
1. Transportation: Company pickup truck/personal vehicle, per mile - $0.445
a. Company pickup truck per day - $75.00
b. Common carrier or car rental multiplies by (as covered in 7.3.1 of the
Contract to be the amounts authorizes by Section 112.062, Florida Statutes)
2. Per Diem Expenses: direct expenses in accordance with Florida State Statutes
B. Disposal of Hazardous Waste Samples
Samples of waste will be disposed by permitted methods after a determination is made
that the waste is defined by RCRA to be hazardous. Due to the requirements for some
hazardous assessments, disposal and invoicing of incurred expenses may take place
after invoicing of the originally contracted work.
C. Equipment / Other Expenses
(Does not include personnel)
Digital Field Documentation Equipment
$75.00 /day (min 2 days)
(cameras, water [ever & measuring tapes, GPS
units, etc.
Geophysical Equipment GPR Equipment
$1,000 /da min 2 days)
Underwater Camera Equipment/Video up to
$1,900.00 /day
50 feet depth and low turbid
Environmental Monitoring & Sampling Equipment $100.00 to $450.00 1day
(Dust, OVA, Air Monitoring, Noise Meter, Light Meter) Depending on the equipment and scale
required
Special equipment or supplies, permits,
Actual cost x 1.15
shipping, charges, special printing or other
items not customarily provided by AMEC
D. Communications
In -house costs for long- distance phone, telex, telecopier, postage — project labor
charges x 5%
Ill. Subcontract