Item E3Cudjoe Status
March 2017
(Snapshot at March 10, 2017)
Finance Status
(Since AUG 2012)
FKAA
Advances to date $187.2 million
(most recent $10 million on December 2016)
Expenditures to date $178.8 million
Advance Balance on hand $ 8.4 million
Construction
Deep well is fully cased and final phase of the initial testing to gain
certification from FDEP is the injection test that is currently scheduled for
Thursday, 16 March 2017. Setting of pumps and final piping are being
constructed by WWTP contractor.
E3
CURRENT STATUS REPORT FOR CUDJOE REGIONAL WASTEWATER PROGRAM
(As of February 22, 2017)
• Inner Islands' Collection
System
• Outer Islands' Collection About 320 grinder stations left to install. Considerable punch
System I list items left along with pavement overlay.
Action: Complete remaining project work and settle
remaining contract close -out issues.
• Added Collection Areas
• Advanced Wastewater I Facility in operation with excellent treatment Deep well work
• On -Site Systems Permits for several properties issued by FDOH in September
for on -site systems on Torches. Grant modification received to
extend project timeline and add /subtract certain systems.
Action: Begin construction on 10 systems that were recently
bid, upon Board approval.
11 Page