1st Change Order 11/04/2016MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: East Martello Museum ADA Upgrades TO CONTRACTOR: Barracuda Bulldlers Inc. 5601 3r° Avenue Key West, FL 33040 The Contract is changed as follows: CHANGE ORDER NO: 2 INITIATION DATE: November CONTRACT DATE: March 23, 2016 The original IContract Sum) (Guaranteed Maximum Price)...................................$149,780.00 Net change by previously authorized Change Orders ................... ....................... $ 2,025.00 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.....$151,805.00 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order... $ 6,040.00 The new (Contract Sum) (Guaranteed Maximum Price) Including this Change Order is ....................... ...............................................................I...... $157,845.00 The Contract Time will be (increased)e��•(decreased) (unchanged] by ...................... 4 days The date of Substantial Completion as of the date of this Change Order is .............. 01/2412017 Detailed description of change order and justification: This change Order is 4.03% of the original contract price ARCHITECT: CONTRACTOR: 1 •A• Date DIRECTOR PROJECT MANAGEMENT: VV Doug Sposito COUNTY/ASSISTANT ADMINISTRATOR. Roman ast si Kevin Ison Christine Hurley W1,01b 'AN 1W 11 0I.OD6 Date _g�..: _ �- x. �-._. t...,,�:�._ -� ,:.,_i. _, -moo..,-•--�� ,�_�`.a- �-_-�,:�. -� .�:�. � ..�.-:_-�....�_ Change Order Attachment per Ordinance No. 0044999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The eourtywd nwW has a varlaace In alevatlon ftm the or/y/nal specllleaHons to the actual elevallom • Change Order was included In the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,o00 or 5% of contract price (whichever is gnuder). Yes ❑ No® If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ®No ❑ Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: BARRACUDA B U I L D E R S OF KEY WEST. INC. COVER LETTER Barracuda Builders of Key West, Inc. 55013rd Avenue, Key West, FL 33040 Florida License Number: CGC1521253 Ofc: (305) 396-7752 Fax: (305) 396-7832 Cell: (305) 747-4637 To: Monroe County BOCC Date: November 9, 2016 Attn: Chris Rivera Proposal 1t: 16-097 Email: rvera-chrisLtDmonroecountv•fi eov Project: East Martello Museum Courtyard Ramp & Stairs Chris, Upon layout of the Courtyard Ramp, we determined the actual elevation dNference between the Museum and Courtyard is 49" (drawings show 39.5"). This elevation discrepancy requires an additional 10 Linear Feet of Ramp as well as (2) additional Risers on the Concrete Stairs. Due to this difference, please find attached our Change Order Proposal required for this additional work. In addition to these costs we are requesting to add 4 days to the Contract Time. Please review these Items and let me know If there are any questions or comments at this time. Respectfully, Bryan Wofsey Barracuda Builders of Key West, Inc. - President www.barracudabuilders.com 16-087 East Martello Museum - Enlarge Courtyard Ramp & Stairs I Barracuda Builders of Key West, Inc. 44MBARRACUDA 56013rd Avenue, Key West, FL 33040 B ll I L D E R OF MEvriESN, INC Florida License Number: CGC1521253 Oft: (305) 396-77S2 fax:(305)396-7932 Cell: (305) 747-4637 CHANGE ORDER PROPOSAL To: Monroe County BOCC Date: November 9, 2016 Attn: Chris Rivera Proposal#: 16-087 Email: rnrgra thris&ltnonroetounrv•fl stov Project: East Maltell0 Museum Courtyard Ramp & stairs Barracuda Builders,of Key West, Inc. is pleased to quote the Sum of $6,040 to provide all supervision, labor, materials, tools, equipment and cleanup for the above referenced project. AS per our Weekly Construction Meeting on Tuesday, November 8th, 2016, the following is a breakdown of the scope of work included In this proposal: Courtyard Ramp & Stairs 10 Linear feet of Concrete Ramp Including Fill, Vapor Barrier, & Reinforcing Steel .................... ............ J52,475A0 (2) Additional Stair Risers .......... ............. ........._...........,..........................._................._......................................42,835.00 20 Linear Feet of Aluminum Handrail ................................... ... $6,040.00 Timeline: Add 4 Days to Contract Time... Accepted by: (Authorized Signer) Date: Barracuda I;uildefs of Key West Bryan Wofsey, President I I ) le Nol iai Date: As required by the Florida United Businesses Associarion starting July 1, 2016, the following Is information regarding the Florida Horneownar's Construction Recovery Fund: Foyment, up to o Ifnthed omomi; maybe avolhsm from the FlorMo Nomeowners' Constructlon Recoveryfund if you lose money on a project performed under mntrot; where the lass resaRs p»m speclflad MaN ans of Flondo low by a Ransed contractor. For ryormotion obout the Recovery Fund and ilR^4 o ckim, ca,rtad the FlorldO Cons[nMion Industry tkensnp 9eoro at the JoRowlry tekphone number and address: www.barracudabuilders.com Construction Industry Licensing Board 2602 Blalrstorm Rd Tallahassee, FL 32399-1039 BS0-497-139S 16-087 East Martello Museum • Enlarge Courtyard Ramp & Stairs (Ai rry�/�aSla Oct st,6AA. of V.,Ivs Cm 4Y v l .Sk rj J Lr-A,._l zw 12, yoS !wi 4-.,L P j sw r & 1,,V6 =I- . 4, g-r - IIIglq-4►b Co�.1ye�►A l..,p ��?,yot �► Stuo 7 B,sa� = 6 rLiac f if 4 L AAAi Vts��l Scoff W w.,k Uk 10 if � Rip AAA .2 K4w WAAA v if OP I&OV?i S -, 4 7G ;o ♦ �� 4P33_7al A1y MEMORANDUM TO: Board of County Commissioners From: Kevin Wilson Assistant County Administrator Date: November 21, 2016 RE: Change Orders Attached is a proposed Change Order #2 Barracuda Builders, Inc., East Martello Museum ADA Updates. The Contract Sum will be increased by this Change Order $6,040.00. The date of Substantial Completion as of the date of this Change Order is January 24, 2017. According to Ordinance No. 004-1999 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Assistant County Administrator intends to approve this change order on Wednesday, November 23, 2016. vin son As ist ounty Administrator KW/ef