4th Change Order 12/21/2016MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
East Martello Museum ADA Upgrades
TO CONTRACTOR:
Barracuda Builders of Key West, Inc.
6601 3rd avenue, Key West, FL 33040
The Contract is changed as follows:
CHANGE ORDER NO: 4
INITIATION DATE: 12/16/2016
CONTRACT DATE: 3/23/2016
The original (Contract Sum) (Guaranteed Maximum Price)..................................$149,780.00
Net change by previously authorized Change Orders............................................$51.580.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was... $201,360.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unc anaed) by this Change Order ....... $00.00
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ...... $201,360.00
The Contract Time will be in [ease (decreased) (unchanged) by......................14 Days
The date of Substantial Completion as of the date of this Change Order is........... 2/21 /2016
Detailed description of change order and justification:
ARCHITECT: _
CONTRACTOR: `
DIRECTOR PROJECT MANAGEMENT:
COUNTY/ASSISTANT ADMINISTRATO
IzJi
11-r ' / — Date
ea'14
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Material ordering delay
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
Change Order exceeds $25,000 or 5% of contract price (whichever is greater).
Yes ❑ No EK
If Yes, explanation as to why it is not subject for a calling for bids:
* Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: