10th Change Order 02/02/2017MONROE COUNTYIENGINEERING/PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Construction of the Monroe County Fire
Training Academy, Crawl Key, FL
TO CONTRACTOR:
Pedro Falcon Electrical Contractors, Inc.
31160 Avenue C
Big Pine Key, FL 33043
The Contract is changed as follows:
CHANGE ORDER NO: 10
INITIATION DATE: January 18th, 2017
CONTRACT DATE: May 20'h, 2016
The original (Contract Sure) (Guaranteed Maximum Price)..................................$1,818,835.00
Net change by previously authorized Change Orders. ...........................................$113,837.25
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was...$1,932,672.25
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged by this Change Order..............$0.00.'
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order
is........................................................................................................... 3 1,9 2,6 The Contract Time will be (increased) (decreased) (unchanged) by..........................105 days
The date of Substantial Completion as of the date of this Change Order is..............April 18, 2017
Detailed description of change order and justification:.
Can JanuarL'i8.`", 2017
20") 2016. Contractor
January 1 '', 201 T Gig
3E� the �rc�iect only nee
This chap e Order is
Not valid until ai ned
ARCHITECT:
CONTRACTOR:
tW
DIRECTOR PROJECT MANAGEMENT..
Doug S
COUNTY/ASSIST. ADMINISTRATOR
Roman Gastesi
Kevin Wilson
Christine Hurley
�m
Date
Change Order Attachment per Ordinance No. 004-1999
9 Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
Contractor has been given the rest of the time allotted to complete the project, since the
lifting of the stop work.
Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
Change Order exceeds $25,000 or 5% of contract price (whichever is greater).Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Monroe County Engineering
1100 Simonton Street, 2-216
Key West, FL 33040
Project Management
1/18/2017
Christian Brisson
Pedro Falcon Electrical Contractors Inc.
31160 Avenue C
Big Pine Key FI
RE: Cancellation of Stop -work Order, Crawl Key Fire Training academy
Dear Christian,
The purpose of this letter is to cancel the Stop -Work Order issued onApril 20t" 2016. You are hereby
directed to resume performance on the Crawl Key Fire Academy job in accordance with the terms and
conditions of the Contract. Please contact me with any questions regarding the contents of this notice.
Sincerely,
Johnnie Yong
Cc:D. Sposito, J Callahan, C Mather, S Hudson D Tegreene, A Mytnik