12th Change Order 04/24/2017MEMORANDUM TO: Board of County Commissioners From: Roman Gastesi County Administrator Date: March 20, 2017 RE: Change Orders Attached is a proposed Change Order #12 Pedro Falcon Electrical Contractors, Inc., Construction of the Monroe County Fire Training Academy, Crawl Key, FL for a time extension of 6 days. The Contract Sum will be increased by $17,780.89. The date of Substantial Completion as of the date of this Change Order is April 24, 2017. According to Ordinance No. 004 -1999 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners at least 24 hours prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. RG /gg MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Construction of the Monroe County Fire Training Academy, Crawl Key, FL TO CONTRACTOR: Pedro Falcon Electrical Contractors, Inc. 31160 Avenue C Big Pine Key, FL 33043 The Contract is changed as follows: I= The original (Contract Sum) (Guaranteed Maximum Price) ................ ......... ........................ ........ $1,818,835.00 Net change by previously authorized Change Orders ................. ......................... $115,875.70 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was ... $1,934,710.70 The (_Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ....... $17,780.89 The new (Contract Sum ) (Guaranteed Maximum Price) including this Change Order is............................ ............................................................................... $1,952, 491.59 The Contract Time will be (Lincreased) (decreased) (unchanged) by ................. .... 6 days The date of Substantial Completion as of the date of this Change Order is .............. 24, 2017 This than e Order is -1.C?% of the on final contract ri e> It M me] ji, a I • DIRECTOR PROJECT MANAGEMENT' Doug S Y9 741 �/>.//7 10 COUNTYIASSIST. ADMINISTRATOR - 7 Roman G Date Kevin Wilson Christine Hurley f 31160 Avenue C, Big Pine Key, FL 33043 -4516 (305) 872 -2200 - Fax (305) 872 -2219 EC 13003416 6 CGC 1507617 www.pedrofalcon.com Request for Change Order Per email dated 04/12/16 Date submitted: 04/26/16 Project: Crawl Key Fire Academy Change Order Request No: Thirteen Description: 1. Turn the extractor on a 90 degree angle to accommodate better access to the machine, turning this machine now requires that a new drain be installed on the backside of the building through the exterior wall (that is why this is significant). 2. Installation of a commercial size ice maker into the garage bay, this will include drilling a new drain hole unless the extractor is rotated, then it can use the drain installed for the extractors proposed location. 3. Placement and connection of an under counter ice maker which is already at the academy to be installed in the classroom, the installation of the ice maker needs a potable water feed, condensate drain, and possibly a pump to feed the condensate drain up into the sink trap already proposed in the classroom. 4. Installation of backing and hookups for the wall mounted TVs in the classroom. Item #1: Subcontractors Work Plumbing work (see proposal below from Gary's Plumbing Dated 04/14/16)......$772.45 Self Perform Work Waterproof and patch concrete; Install housekeeping concrete pad with rebar and dowel pad to raise machine to make drain work ....................$1,102.05 laabor: $627.00 (Diamond blades, drill bits, jack hammer, grinder, skill saw, Materials: $250.05 ; %' oncrete mixer, truck delivery, extension cords, dust masks, Others: '$225.00 / gloves, safety glasses, painting rollers and pan, rags, broom I shovel, wheel barrow, water hose, 5 gallon bucket, sponge, trowel, rubbing stone, hammer drill (large and small), pliers, hammer, drill. impact drill, chalk line and chalk, level, garden hoses and water gun) Item #3: Subcontractors Work Plumbing work (see proposal below from Gary's Plumbing Dated 04/14/16)......$900.00 Subcontractors proposal is for $715.00, contractor adds $185.00 materials /tools Cabinet work: .................... ............ ....... ................... <$175.00> Credit for 36" base ($275.00) Add a vertical side on refrigerator side: $85.00 Add brace to support countertop: $15.00 Electrical: Install conduit, wire and boxes ......................... ......................$407.83 Labor: $201.96 Materials: $180.87 Others: $25.00 (small tools and consumable) Subtotal ....................................................... ............................... $1,132.83 Project Coordination: 1 Hours @ $ 100 ............................................. ............................... $100.00 SUBTOTAL Item #3: SUBCONTRACTORS WORK; SELF PERFOM WORK AND COORDINATION . ............................... $1,232.83 Overhead@ 5% ...................................... ............................... .........................$61.64 Subtotal ....................................................... ............................... $1,294.47 Profit@ 5% ......................................,............. ............................... $64..72 TOTAL ALL OF THE ABOVE FOR ITEM # 3 .... ............................... $1,359.19 Item #4: Subcontractors Work Electrical/Data: Install conduit, wire and boxes ................. ........................$359.84 Labor: $164.66 Materials: $177.86 Others: $17.33 (small tools and consumable) Self Perform Work Install wood backing ................... ............................... ........................$107.13 Labor: $66.00 Materials: $16.13 Others: $25.00 (small tools and consumable) Respectfully Submitted, Christian Brisson Project Manager 31160 Avenue C, Big Pine Key, FL 33043-4516 (305) 872-2200 - Fax (305) 872-2219 EC 13003416 1 CGC 1507617 www.pedrofalcon.com Request for Change Order Per email dated 02/15/17 Date submitted: 02/28/17 Project: Crawl Key Fire Academy Change Order Request No: Seventeen Description: Install epoxy grout for all floor and wall tile. Subcontractors Work Install epoxy-grout for all floors and wall tile ................... ......................$2,650.00 Project Coordination: 2 Hours *, $100 ........................................................................... $200.00 SUBTOTAL SUBCONTRACTORS WORKAND COORDINATION ..... $2,850.00 Overhead 5% ..................................................................................................... $142.50 Subtotal .................................................................................... $2,992.50 Profit* 5% ............................................................................... . $149-63 TOTAL ALL OF THE ABOVE ..................................................... $3,142.13 Permit Fees and Design Drawings are Not Included in this proposal. If additional permit fees are required the Owner is to reimburse all permit fees. YAZMIN TILES 92330 OVERSEAS HWY SUITE 106 FL 33070 Bill To NICHOLAS BRISSON MONROE COUNTY CRAWL KEY FIRE ACADEMY 31160 AVE C BIG PINE KEY, FL 33043 Invoice Date Invoice # 2/28/2017 12886 P.O. No. Terms Project Quantity Description Rate Amount 1 Grout for all floors and walls with Epoxy -Grout 2,650.00 2,650.00 Sales Tax 6.00% 0.00 Total $2,650.00 12AA lonline at: (305) 872-2200 (305) 872-2219 EC 13003416 1 1 F 1507617 www.pedrofalcon.com Request for Change Order Per email dated 02/24/17 Date submitted: 03/02/17 Project: Crawl ley Fire Academy Change Order Request No: Nineteen Description: Asphalt paving of the open area in the middle of the Fire Academy ground. Approximately 1000 s8 in area. Contractor shall clear and scarify the un- asphalted area and place clean lime rock fill to a depth of 4 inches minimum base. Mill surrounding asphalt to provide smooth transition. Lime rock base shall be compacted and graded so that the new asphalt layer will match the existing adjacent grades. Provide tack coat as per section 02511- 3.01(D) in the project specifications. Provide 2 inch thickness of asphaltic concrete, level with adjacent surfaces. Subcontractors Work 13 & L Beneway; See enclosed proposal below) A) Preparation: .......................................... ............................... $ 4,200.00 1) Remove 5" existing sub -base 111 SY 2) Install 4" DOT lime rock and compact 3) Saw cut existing edge B) Asphalt: ................................................ ............................... $3,150.00 1) 2" Asphalt (15 tons) SUBTOTAL SUBCONTRACTORS WORK ..... ............................... $ 7,350.00 Project Coordination: 2 Hours @ $ 100 .............................................. ............................... $200.00 f 936 CRANE BOULEVARD SUGARLOAF, FL 33042 TELEPHONE: 305-743-4394 FAX: 305- 743 -4294 March 1, 2017 Pedro Falcon Electrical & General Contractors 31160 Avenue C Big Pine, FL 33043 Attn: Christian Brisson CRAWL KEY ADDITIONAL ASPHALT PROPOSAL A. Prep 1. Remove 5" existing sub -base 111 SY 2. Install 4" DOT limerock, compact 3. Saw cut existing edges Prep Base Total $4,200.00 B. Asphalt 1. 2" Asphalt 15 Tons Asphalt Total $3,150.00 Total Price: $7,350.00