3rd Change Order 05/12/2017MONROE COUNTY /ENGINEERING / PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Lake Surprise Roadway and Drainage Project CHANGE ORDER NO: 3 INITIATION DATE: 4/21/17 TO CONTRACTOR: D.N. Higgins, Inc. CONTRACT DATE: 7/15/15 The Contract is changed as follows: The original Contract Sum ................................................. ............................... $2,664,839.50 Net change by previously authorized Change Orders . ............................... ....................$468,287.28 The Contract Sum prior to this Change order was ...................... ............................... $3,133,126.78 The Contract Sum will be decreased by this Final Reconciliation Change Order 3 ........... ($129,733.97) The new Contract Sum including this Change Order is ............................. ..................$3,003,392.81 The Contract Time is increased by 13 weather days and 24 holidays. The contract completion date is extended by 37 days, for a total revised contract time of 500 days. The date of Substantial Completion as of the date of this Change Order is 2/1/17. CEI detailed description of change order and justification attached: The overrun amounts to the contract bid amounts are as follows: Bid Item Description + Quantity UOM Unit cost $ Amount 12 Inlets, DT Bot, Type F <10" increase 1 EA $4,900.00 $4,900.00 17 French Drains increase 28 LF $270.00 $7,560.00 18 Valle Gutter — Concrete increase 28 LF $40.00 $1,120.00 20 Sin le Post Sign, F &I, Less than 12SF increase 1 EA $450.00 $450.00 new Modif Drainage Structure S -31 increase 1 LS $1460.63 $1,460.63 Total $ value of overruns to plan quantities $15,490.63 The underrun amounts to the contract bid amounts are as follows: Bid Item Description - Quantity UOM Unit cost $ Amount 6 Removal of existing concrete pavement decrease -19 SY $70.00 $1,330.00 8 Geos nthetic Reinforce Soil System decrease -28 SY $5.45 $152.60 9 Optional Base, Base Group 06 decrease -1344 SY $17.50 $23,520.00 10 Asphalt Concrete Su er ave SP9.5 decrease -560.5 TN $154.00 $86,317.00 16 18" Solid Pie decrease -54 LF $160.00 $8,640.00 19 Performance Turf Sod decrease -7980 SY $3.00 $23,940.00 21 Sin le Post Sign, Relocate decrease -1 AS $230.00 $230.00 22 Thermoplastic, Std, White Solid 24" decrease -2 LF $7.00 $14.00 23 Thermoplastic, Std, Yellow Solid 6" decrease -1 LF $6.00 $6.00 24 Thermoplastic, Std, White Ski 6" decrease -.215 GM $5,000.00 $1,075.00 Total $ value of underruns to plan quantities $145,224.60 Final Reconciliation Change Order 3 Net Contract Decrease Amount ($129,733.97 G C- This Final Reconciliation Change Order 3 is (4.8 %) of tht original contract price. CONTRACTOR (DN HIGGINS): ENGINEERING SERVICES DIRECTOR: a6 /17 Date ,T/v /a) Date ASSISTANT COUNTY ADMINISTRATOR: Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The CEI and FOR determined additional or fewer quantities were required per attached. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ®No ❑ Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Actual installed quantity over and underruns result in net decrease to contract amount. 3100 Overseas Highway Marathon Florida Monroe County Engineering Department April 19, 2017 Judith Clarke, P.E. 110 Simonton Street Key West, FL 33040 Project: Lake Surprise Estates Subject: Underruns The summary of contract dollar changes is shown below: Original contract amount ................................................ ............................... $2,664,839.50 Net change by previous authorized change orders #1 and #2 ........................... $468,287.28 The contract sum prior to this change order ................... ............................... $3,133,126.78 The contract sum will be increased by this change order #3 .............................. $15,490.63 The new contract sum including this change order ......... ............................... $3,148,617.41 The contract sum will decrease due to underruns ......................... ..................($145,224.60) The new contract sum including overruns /underruns ............................. $3,003,392.81 The contract time was increased 13 days due to weather and 24 days due to holidays. The summary of contract time changes is shown below: Original contract ................ ............................... ............................365 days Contract time extension from change order 2 .... .............................98 days Weather.............................................................. .............................13 days Holidays............................................................. ............................. days Total Contract days ........................................ ............................... 500 days Below is a detailed description of pay item overruns and underruns for the contract; Pay Item 6 Removal of Existing Pavement There is a plan quantity error which resulted in an underrun of 19 SY. Pay item 8 Geosynthetic Reinforced Soil System There is an error in the plan quantities. The item was field measured upon being installed per the plans and had an underrun of 28 SY. See field book for location and calculations as back -up. Pay item 9 Optional Base There is an error in the plan quantities. The item was field measured upon being installed per the plans and had an underrun of 1344 SY. See field book for location and calculations as back -up. Pay Item 10 Asphalt Concrete Superpave SP9.5 There is a plan quantity error, see asphalt paving reports. This resulted in an underrun of 560.5 TN. Pay item 16 Solid Pipe 18 "There is a plan quantity error. See summary of quantities in the as -built plans for calculations which shows an underrun of 54 feet. Pay Item 19 Performance Turf, Sod. Monroe County representative and the CEI jointly elected not to place sod in an area that would be affected by vehicle parking and in an area not disturbed by the construction. This resulted in an underrun 7980 SY. Pay Item 21 Single Post Sign Relocate The Contractor did not relocate a STOP sign on Lower Matecumbe, since it would have resulted the blocking of a homeowner's front gate. This resulted in a 1 AS underrun. Pay Item 22 Thermoplastic, Standard, White, Solid, 24" There is a plan quantity error resulting in a 2 LF underrun. Pay Item 23 Thermoplastic, Standard, Yellow, Solid, 6" There is a plan quantity error resulting in a 1 LF underrun. Pay Item 24 Thermoplastic, Standard, Yellow, Sip, 6" There is a plan quantity error resulting in a 0.215 GM underrun. The final reconciliation of actual quantities installed resulted in the following underruns for this contract. Underruns Pay Item Item Description Under/ Unit Quantity Unit Price Amount 6 Removal of Existing Pavement Under SY -19 $ 70.00 $ (1330.00) 8 Geosynthetic Reinforced Soil System Under SY -28 $ 5.45 $ (152.60) 9 Optional Base, Base Group 06 Under SY -1344 $ 17.50 $ (23 10 Asphalt Concrete Su SP9.5 Under TN -560.5 $ 154.00 $ 86,317.00) 16 18" Solid Pipe Under LF -54 $ 160.00 $ 8,640.00) 19 Performance Turf, Sod Under SY -7980 $ 3.00 $ 23,940.00) 21 Single Post Sign, Relocate Under AS -1 $ 230.00 $ (230.00) 22 Thermoplastic, Standard, White, Solid, 24" Under LF -2 $ 7.00 $ (14.00) 23 Thermoplastic, Standard, Yellow, Solid, 6" Under LF -1 $ 6.00 $ (6.00) 24 Thermoplastic, Standard, Yellow, Sip, 6" Under GM -0.215 $ 5,000.00 $ (1,075.00) Total Overrun/Underrun Final Reconciliation $ 145,224.60) If you have any questions or need clarification of the above item summaries, please call Jackson Taylor at 561 -436 -2860. Sincerely, Jackson Taylor Project Administrator, RSH Cc: Judith Clarke, Debra London, Jacki Hart, P.E, File Page 2 of 2 3100 Overseas Highway Marathon Florida Monroe County Engineering Department April 23, 2017 Judith Clarke, P.E. 110 Simonton Street Key West, FL 33040 Project: Lake Surprise Estates Subject: Change Order #3 The summary of contract dollar changes is shown below: Original contract amount ............................... ............................... ..................$2,664,839.50 Net change by previous authorized change orders #I and #2 ....... ....................$468,287.28 The contract stun prior to this change or der .. ............................... ..................$3,133,126.78 The contract sum will be increased by this change order #3 .......... .....................$15,490.63 The new contract sum including this change order ................. ..................$3,148,617.41 Below is a detailed description of change order #3; Pay item 12 Inlet Inlet S -104 was added as a recommendation from the CEI with FOR concurrence. The drainage structure was added on Lower Matecumbe Road to improve drainage, which resulted in an overrun of 1 EA. Pay item 17 French Drain. S -104 was added as a recommendation from the CEI with FOR concurrence. The drainage structure was added on Lower Matecumbe Road to improve drainage, which resulted in an overrun of 28 LF of French drain. Pay item 18 Valley Gutter. The valley gutter was extended to drainage structure S -30 to prevent erosion, which resulted in a 28 LF overrun New Item: Drainage Structure- Modify Drainage Structure S -31 was modified in order to install at the revised plan elevation for sea level rise change. This resulted in a 1 LS overrun of this item that was initially not in the contract. If you have any questions or need clarification of the above item summaries, please call Jackson Taylor at 561- 436 -2860. Sincerely, 9 4t4- T Jackson Taylor Project Administrator, RSH Cc: Judith Clarke, Debra London, Jacki Hart, P.E, File GE•ffR4 CG 144CT0l15 IND Ms. Jacki Hart, E.I. Reynolds Smith and Hills 3100 Overseas Highway Marathon, FL 33050 Reference: Lake Surprise Estates Roadway & Drainage Improvements Subject: Change Order Request #3 Dear Ms. Hart, April 11, 2017 Work on the Lake Surprise Estates Roadway & Drainage Improvements project have been completed. During the course of the project a number of items, due to adjustments in the field, have overrun their contract quantities. Douglas. N Higgins, Inc. is requesting the following items and quantities to be included in this change order. /`u AAI!`C r%Dr%CD u7 �.nrvv�� vn�cn n.a Pay Item Item Description Unit Quantity Unit Price Bid Item Total 12 Inlets, DT Bot, Type F <10' EA 1 $ 4,900.00 $ 4,900.00 17 French Drain LF 28 $ 270.00 $ 7,560.00 18 Valley Gutter LF 28 $ 40.00 $ 1,120.00 201 Single Post Sign, F &I, Less Than 12 SF AS 1 $ 450.00 $ 450.00 Modify Drainage Structure S -31 LS 1 $ 1,460.63 $ 1,460.63 Total of change order 3 $ 15,490.63 Back up for the modification made to S -31 is provided in an attached file. Kind regards, Jim Hennigar Douglas N. Higgins,lnc. 4880 Donald Ross Road, Suite 200 Palm Beach Gardens, FL 33418 (561) 469 -1622 STATE OF FLORIDA DEPARTMENT OF TRAASPORTATIOU DAILY REPORT OF CONSTRUCTION N" 0-13 CV;STRt1CTM 06W Pry. 1 .16 Date: Contract ID: D.N. Higgins Project ID: Superintendent Tuesday, July 12, 2016 Lake Surprise Drainage Imp. 772 -15 Ernie Brown High Temperature: AM Conditions: PM Conditions: Low Temperature: Clear I Clear Remarks General: DNH - Modified S -31 to lower to existing grade (lam to 11am). Set top for S -74 SAC - Began excavating for S -79, stopped because rock was to hard. Began potholing on Summerland rd Accidents: Day of Week: Contract Day: Total Days: No See Accident Report Dated: Tuesday 296 365 Visitors: Contractor(s) and Personnel # Name Type # Hrs Type # Hrs Type # Hrs 1 Prime: O.N. Higgins Supt 1 4.50 Foreman 1 9.00 Skilled 1 9.00 Semi Skilled 2 9.00 Common Water Truck 1 Trainee 4.00 2 Sub / Utility Straight Ahead Constructi Supt Foreman 1 9.00 Skilled 4 9.00 Semi Skilled Loader Common 1 9.00 Trainee Skid Loader 3 Sub / Utility Supt 2 - Sub #1 Foreman 1 1 Skilled Semi Skilled Common Trainee 4 Sub / Utility Supt Foreman Skilled Semi Skilled Common Trainee Contractor(s) Equipment (Active or Idle) Contractor / Sub # Equipment ID Description # Pieces # Used Total Hours Used 1 - DNH Excavator 1 1 9.00 1 - DNH Loader 1 1 9.00 1 - DNH Dump Truck 1 1 9.00 1 - DNH Water Truck 1 1 4.00 2 - Sub #1 Excavator 1 1 9.00 2 - Sub #1 Loader 1 1 9.00 2 - Sub #1 Skid Loader 1 1 9.00 2 - Sub #1 Dump Truck 1 1 9.00 STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION DAILY REPORT OF CONSTRUCTION Toa.o+au carlsraucraN oe og P,y, 3 or a Date: Contract ID: 07/12/2016 Lake Surprise Drainage Imp. Estimated Work Performed Contractor i Sub line Item p Pay Item Code Location Time (AM/PM) Installed Beginning End Qty. Units D. N. Higgins 13 - INLETS DT BOT TYPE F >10' Lake Surprise Blvd (S -74, Top Only) 0.3 EA EFFECTS OF WEATHER ON MAJOR WORK ITEMS (CHECK CONTROLLING ITEMS): Major and/or Controlling Work Items I Portion of Work Affected (No Effect, Less than 50 of Day, More than 50 of Day, No Work al Day) u«.. a <, -,,, •:..: one Direct Labor Detailed Work Breakdown Summary Lake Surprise Drainage Improvements Modification to 5 -31 Tuesday, July 12, 2016 Classification Hours Extended Rate Burden Adjusted Rate Total Supervisor 0 $ 32.00 33.39% $ 42.68 $ - Crew Foreman 4 $ 40.00 33.39% $ 53.36 $ 213.42 Operator 4 $ 21.00 33.39% $ 28.01 $ 112.05 Labor (two each) 8 $ 15.00 33.39% $ 20.01 $ 160.07 Direct Labor Total Material and Eauioment Item 1D 544K Loader - 2015 Cat 336 D 2014 Supervisor Truck 3/4 ton - Blue Book FHWA rate Material and Equipment Total Subcontractor Item Subcontractor Total Cost Summary Q uantit y Unit Price Extended 4 HR $ 54.18 $ 216.72 4 HR $ 130.92 $ 523.68 4 HR $ 20.57 $ 82.28 S - S - Q uantity Rate (1) = = => $ 485.54 Total $ 216.72 $ 523.68 $ 82.28 S - 5 - S - (2) = = => $ 822.68 Tota (3) ___> $ - Total Cost (1) + (2) + (3) $ 1,308.22 Markup @ 10% $ 130.82 Subtotal $ 1,439.04 Bond Premium @ 1.5% $ 21.59 Sales Tax $ Total $ 1,460.63 t 7 , EquipmentWatch- wivw.equi pme n twa tchcom All prices shown in US$ Rental Rate Blue Book® Deere 544K 4- WdArtiadatedWieel Loaders Size [:lass: 150. 174 HP Weight: 28,263 lbs. April 17, 2017 1 will '- t Configuration for 544K Bucket Capacity - Heaped 3 cu yd Net Horsepower 167 hp Power Mode Diesel Operator Protection EROPS Blue Book Rates " FH4VA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Rate Element Allocation Element Percentage Ownership Costs Depreciation (ownership) 42% EstiuratedOpernting FHWA Rate" 38% $1,939.90/mo CFC (ownership) 8:n $408.40 /ma costs 12% $612.60/mo Monthly Weekly Dally Hourly Hourly Hourly Published Rates $5,105.00 $1,430.00 $360.00 $54.00 $26.65 $55.66 Adjustments Region (Florida ($250.15) ($70.07) ($17.64) ($2.65) DOT: 95.1 %) Model ear ($9.71) ($2.72) ($0.68) ($0.10) (2015:99,8%) Ownership (100 %) - Operating (100 %) Total: $4,845.14 $1,357.21 $341.68 $51.25 $26.65 $54.18 Rate Element Allocation Element Percentage Value Depreciation (ownership) 42% $2,144.10/mo Overhaul (ownership) 38% $1,939.90/mo CFC (ownership) 8:n $408.40 /ma indirect (ownership) 12% $612.60/mo Fuel (operating) @2.36 47% $12.61/hr Revised Date: 2nd Ha1f2016 The equipment represented in this report has been exclusively prepared for MA I'M EW DELUCA (mattd@dnhiggins.com) All material herein 0 2003 -2017 Penton All rights reserved. EquipmentWatch. www.equipmentwatchcom All prices shown in US$ Rental Rate Blue Book@ April 17, 2017 Caterpillar 336D L(disc.2014) < Crawler Mounted Hydraulic Excavators Size Class: 33.1 - 40.0 D1Tons \'eight: 80,464 lbs. Configuration for 336D L (disc. 2014) Bucket Capacity - Heaped 1.56 cu yd Operating Weight 36.5 mt Net Horsepower 266 hp Power Mode Diesel Blue Book Rates '• FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operatingcost. Ownership Costs Rate Element Allocation Estimated Operating Costs Hourly $64.70 $64.70 FH\VA Rate" Hourly $133.25 $130.92 Element Monthly Weekly Dally Hourly PubiishedRates $12,065.00 $3,380.00 $845.00 $125.00 Adjustments $844.55/mo Indirect (ownership) 7% $84455/mo Region (Florida ($410.21) ($114.92) (S28.73) ($4.25) DOT: 96.6%) Model Year (2014: 100%) Ownership (10096) - Operating (100%) Total: $11,654.79 $3,265.08 $816.27 $120.75 Rate Element Allocation Estimated Operating Costs Hourly $64.70 $64.70 FH\VA Rate" Hourly $133.25 $130.92 Element Percentage Value Depreciation (ownership) 37% $4,464.05/mo Overhaul (ownership) 49% $5,911 A5 CFC (ownership) 7% $844.55/mo Indirect (ownership) 7% $84455/mo Fuel (operating) @ 2.36 41% $26.56 11ir Revised Date: 2nd Half 2016 The equipment represented in this report has been exclusively prepared for MATTHEW DELUCA (mattd @dnhiggins.com) All material herein Q 2003 -2017 Penton All rights reserved. EquipmentWatch- wwiv.equipmen uvatchcnm All prices shown in US$ Rental Rate Blue Book® Miscellaneous 4X23/4 285 CREW GAS On- Highway Ught Duty Trucks Size Gass: 200 - 299 HP Weight: N/A April 17, 2017 Configuration for 4X2 3/4 285 CREW GAS Power Mode Gasoline Horsepower 2115 Ton Rating 3/4 Axle Configuration 4X2 Cab Type Crew Blue Book Rates " FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost. Rate Element Allocation Element Percentage Ownership Costs Depreciation (ownership) 57% Estimated Operating FHWA Rate" 28% $225A0 /mo CFC (onmersWp) 5% $40.251mo Costs 10% $8050 /mo Monthly Weekly Daily Hourly Hourly Hourly Published Rates $805.00 $225.00 $56.00 $8.00 $16.20 $20.77 Adjustments Region (Florida ($24.96) ($6.98) ($1.74) ($0.25) DOT:96.9:0) Model Year (S10.14) (S2.83) ($0.71) ($0.10) (2015:98.7%) Ownership (100'0) - - - Operating (100%) Total: $769.90 $215.19 $53.55 $7.65 $16.201 $20.57 Rate Element Allocation Element Percentage Value Depreciation (ownership) 57% $458.85/mo Overharil (ownership) 28% $225A0 /mo CFC (onmersWp) 5% $40.251mo Indirect (ownership) 10% $8050 /mo Fuel (operating) @ 234 78% $12.671hr Revised Date: 2nd Ha1f2016 The equipment represented in this report has been exclusively prepared for MATTHEW DELUCA (mattd @dnhiggins.coin) All material herein @ 2003 -2017 Penton All rights reserved.