8th Change Order 04/12/2017MONROE COUNTY /ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 8
East Martello Museum ADA Upgrades
INITIATION DATE: 3 -28 -2017
TO CONTRACTOR: CONTRACT DATE: 3/23/2016
Barracuda Builders of Key West, Inc.
6601 3"' avenue, Key West, FL 33040
The Contract is changed as follows:
The original ( Contract Sum (Guaranteed Maximum Price) .............. ....................$149,780.00
Net change by previously authorized Change Orders ....................... .....................$60,384.50
The ( Contract Sum) (Guaranteed Maximum Price) prior to this Change order was ... $210,164.50
The ( Contract Sum (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order ....... $60,000.00
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ...... $270,174.50
The Contract Time will be (increase (decreased) (unchanged) by ...................... Days
The date of Substantial Completion as of the date of this Change Order is........... 6/27/2017
Detailed description of change order and justification:
Change order to install ADA accessible ramp at the East Martello Sanchez Gallerv.
This change Order is 40% of the original contract price.
Not valid until signed by Owner. Architect (if applicable), and Contractor
I er, ss ciates Architects, P.A. Bar a ilders of Key West, Inc.
N �
yin Madok, Clerk
p
C] .
O ••
zz _
C) Cn cv
Y
cm Q VC O
w = z
o
Li C = E
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
Date: t r 7
MOI4 ROE COUNTY ATTORNEY'S OFFICE
OVf D A TO F0 M
t�a.tt
PATRICIA EABLES
ASSISTANT COUNTY ATTORNEY
DATE: i _ / S''-I 7
a
Change Order Attachment per Ordinance No. 004 -1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: ADA accessibility was not included in original drawings
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater).
Yes ® No ❑
If Yes, explanation as to why it is not subject for a calling for bids: Contractor is already on
site.
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
BARRACUDA
B U I L D E R S
OF KEY WEST. INC.
COVER LETTER
To: Monroe County BOCC
Attn: Chris Rivera
Email: rivera - chris @monroecounty- fl.sov
Chris,
Barracuda Builders of Key West, Inc.
5601 3rd Avenue, Key West, FL 33040
Florida License Number: CGC1521253
Ofc: (305) 396 -7752
Fax: (305) 396 -7832
Cell: (305) 747 -4637
Date: March 28, 2017
Proposal #: 17 -026a
Project: East Martello Museum
Sanchez Gallery ADA Upgrades
Per the East Martello Sanchez Gallery Ramp Information Bulletin #1 and the "East Martello Towers - Sanchez
Gallery ADA Upgrades" plans drawn by Bender & Associates Architects, p.a., dated March 4, 2017, please find
attached our REVISED Change Order Proposal for the Sanchez Gallery ADA Upgrades project. This scope will
be completed by June 27, 2017. Please review these items and let me know if there are any questions or
comments at this time.
Respectfully,
Bryan Wofsey
Barracuda Builders of Key West, Inc. - President
www.barracudabuilders.com 17 -026a East Martello Museum - Sanchez Gallery ADA Upgrades
2of5
Barracuda Builders of Key West, Inc.
BARRACUDA 5601 3rd Avenue, Key West, FL 33040
B U I L D E R S Florida License Number: CGC1521253
OF KEY WEST, INC.
Ofc: (305) 396 -7752
Fax: (305) 396 -7832
Cell: (305) 747 -4637
REVISED CHANGE ORDER PROPOSAL
To: Monroe County BOCC Date: March 28, 2017
Attn: Chris Rivera Proposal #: 17 -026a
Email: rivera- chris @monroecounty- fl.aov Project: East Martello Museum
Sanchez Gallery ADA Upgrades
Barracuda Builders of Key West, Inc. is pleased to quote the Sum of $60,000 to provide all supervision,
labor, materials, tools, equipment and cleanup for the above referenced project.
Per the East Martello Sanchez Gallery Ramp Information Bulletin #1 and the "East Martello Towers - Sanchez
Gallery ADA Upgrades" plans drawn by Bender & Associates Architects, p.a., dated March 4, 2017; the following
is a of the scope of work included in this proposal:
Demo
Furnish and Install Dust Barriers
Sanchez Gallery ADA Upgrades
Remove (2) Plywood Door and Frame .....................4
m x 8 hr x $ 45/ hr...................... ...............................
$1,440.00
Demolish Concrete Slabs ............ ...............................
4 m x 20 hr x $ 45/ hr.................... ...............................
$3,600.00
Remove Plywood Ramp .............. ...............................
4 m x 4 hr x$ 45/ hr...................... ...............................
$720.00
Remove Concrete Stairs ............... ..............................4
m x 8 hr x $ 45/ hr...................... ...............................
$1,440.00
Remove Exterior Door .................. ..............................4
m x 4 hr x $ 45/ hr...................... ...............................
$720.00
Haul (5) CY Fill Material .............. ...............................
4 m x 16 hr x $ 45/ hr.................... ...............................
$2,880.00
Disposal 20 CY Roll -off Dumpster .............................
2 x $ 650/ ea................................... ...............................
$1,300.00
Blades and Bits ............................. ...............................
$350+$150 .................................................................
$500.00
901b Jackhammer Rental ............. ...............................
$325 + $50 = $375 + 10% protection + tax.............
$445.00
Walk- Behind Saw Rental ............. ...............................
$255 + $505 + $48 = $808 + 10% protection + tax
$955.00
Plastic / 2x4x16 / Tapcons (Dust Barrier) ................
$100 + $50 + $ 50......................... ...............................
$200.00
Demo Subtotal
$14,200.00
Overhead & Profit 10%
Demo Total $15,620.00
Concrete Ramp / Landina / Railin
Install Expansion Joint ................. ...............................
4 m x 8 hr x$ 45/ hr...................... ...............................
$1,440.00
Grade, Prepare, and Compact Ramp .......................
4 m x 16 hr x $ 45/ hr.................... ...............................
$2,880.00
Compactor Rental (1 week) ........ ...............................
$295 + 10% protection + tax...... ...............................
$350.00
Expansion joint / Nails (100'+ 74') ...........................
5 rolls x $20 /roll + $50 nails....... ...............................
$150.00
#3 Bars/ Epoxy ............................ ...............................
3 x $6.50 /ea + $ 40....................... ...............................
$60.00
Welded Wire Mesh ....................... ..............................1
roll x $ 125/ ea............................ ...............................
$125.00
Form Sides / Landing ................... ...............................
4 m x 16 hr x $ 45/ hr.................... ...............................
$2,880.00
Pour and Finish Sides/ Landing . ...............................
6 m x 8 hr x $ 45/ hr...................... ...............................
$2,160.00
CONTINUES ON NEXT PAGE...
www.barracudabuilders.com 17 -026a East Martello Museum - Sanchez Gallery ADA Upgrades
3of5
Barracuda Builders of Key West, Inc.
BARRACUDA 5601 3rd Avenue, Key West, FL 33040
B U I L D E RS Florida License Number: CGC1521253
OF KEY WEST, INC.
Ofc: (305) 396 -7752
Fax: (305) 396 -7832
Cell: (305) 747 -4637
REVISED CHANGE ORDER PROPOSAL
To: Monroe County BOCC Date: March 28, 2017
Attn: Chris Rivera Proposal #: 17 -026a
Email: rivera- chris @monroecounty- fl.gov Project: East Martello Museum
Sanchez Gallery ADA Upgrades
Barracuda Builders of Key West, Inc. is pleased to quote the Sum of $60,000 to provide all supervision,
labor, materials, tools, equipment and cleanup for the above referenced project.
Per the East Martello Sanchez Gallery Ramp Information Bulletin #1 and the "East Martello Towers - Sanchez
Gallery ADA Upgrades" plans drawn by Bender & Associates Architects, p.a., dated March 4, 2017; the following
is a continuation of the scope of work included in this proposal:
Concrete RamD / Landine / Railine (Continued
4089PM (2 CY + 1 CY + 3 CY) ...... ...............................
8 cy x $220 /cy + $200 short load charge.................
$1,960.00
Pump Rental ................................. ...............................
2 pumps x $ 250/ ea...................... ...............................
$500.00
Form Ramp ................................... ...............................
4 m x 8 hr x$ 45/ hr...................... ...............................
$1,440.00
Pour and Finish Ramp ................. ...............................
6 m x 8 hr x $ 45/ hr...................... ...............................
$2,160.00
Blackply ......................................... ...............................
3 sheets x $ 40/ ea......................... ...............................
$120.00
2x4x16 ........................................... ...............................
8 x $ 11/ ea..................................... ...............................
$90.00
Concrete Washout ....................... ...............................
2 x $ 85/ ea..................................... ...............................
$170.00
Tapcons / Screws / Nails / Stakes / Caps ................
lump sum...................................... ...............................
$200.00
Aluminum Railing ......................... ...............................
CZ Craft quote.............................. ...............................
$2,880.00
Core Drill Rental (2 days) ............ ...............................
$200 + $160 = $360 + 10 %+ tax ..............................
$425.00
Grout (Anchor Cement) .............. ...............................
6 buckets x $ 25/ ea...................... ...............................
$150.00
Install Rails ..................................... ..............................4
m x 8 hr x $ 45/ hr...................... ...............................
$1,440.00
Concrete Ramp / Landing / Railing Subtotal
$21,580.00
Overhead & Profit
109
Entry Door with Shutter
Concrete Ramp / Landing / Railing Total $23,735.00
42" x 87" Entry Door ................... ............................... Overseas quote............................ ............................... $1,075.00
Omnia Mortise 12042 -US10B Exterior Lockset...... Decorplanet quote ....................... ............................... $505.00
Hinges / Threshold / Weatherstrip .......................... $65 + $80 + $ 20........................... ............................... $145.00
Jamb Molding/ Nails ................... ............................... lump sum...................................... ............................... $50.00
Prepare & Install Door / Hardware .......................... 3 m x 16 hr x $75 /hr (Summerland Glass) ............... $3,600.00
CONTINUES ON NEXT PAGE...
www.barracudabuilders.com 17 -026a East Martello Museum - Sanchez Gallery ADA Upgrades
4 of 5
Barracuda Builders of Key West, Inc.
40* BARRACUDA 5601 3rd Avenue, Key West, FL 33040
B U I L D E R S Florida License Number: CGC1521253
OF KEY WEST, INC.
Ofc: (305) 396-7752
Fax: (305) 396-7832
Cell: (305) 747 -4637
REVISED CHANGE ORDER PROPOSAL
To: Monroe County BOCC Date: March 28, 2017
Attn: Chris Rivera Proposal #: 17 -026a
Email: rivera - chris @monroecounty- fl.gov Project: East Martello Museum
Sanchez Gallery ADA Upgrades
Barracuda Builders of Key West, Inc. is pleased to quote the Sum of $60,000 to provide all supervision,
labor, materials, tools, equipment and cleanup for the above referenced project.
Per the East Martello Sanchez Gallery Ramp Information Bulletin #1 and the "East Martello Towers - Sanchez
Gallery ADA Upgrades" plans drawn by Bender & Associates Architects, p.a., dated March 4, 2017; the following
is a continuation of the scope of work included in this proposal:
Entry Door with Shutter (continued
Paint Supplies ............................ ............................... lump sum...................................... ............................... $75.00
Prime / Paint Door ....................... ............................... 2 m x 8 hr x $ 45/ hr...................... ............................... $720.00
Hurricane Shutter ........................ ............................... Hurricane Shutters of Key West quote.................... $555.00
Entry Door with Shutter Subtotal $6,725.00
Overhead & Profit 10%
Entry Door with Shutter Total $7,395.00
Door Operator and Electric
Stanley'Magic Force' and Push Plates (or equivalent) .................................................. ............................... $5,335.00
Install Operator / Plates ............... ..............................3 m x 8 hr x $ 75/ hr...................... ............................... $1,800.00
Backing / Tapcons / Screws ........ ............................... $50 +$50 +$50 .......................................................... $150.00
Electric Work and Fixtures .......... ............................... Check Electric quote.................... ............................... $4,940.00
Door Operator and Electric Subtotal $12,225.00
Overhead & Profit 10%
Door Operator and Electric Total $13,445.00
Permit / Permit Fees
Permit Prep / Pickup ................... ............................... 1 w x 6 hr x $ 50/ hr...................... ............................... $300.00
HARC .............................................. ............................... lump sum...................................... ............................... $150.00
Monroe County Building Permit ............................... $75,000 x 4%......................... ............................... $3,000.00
Permit / Permit Fees Subtotal $3,450.00
Overhead & Profit 10%
Permit/ Permit Fees Total $3,795.00
CONTINUES ON NEXT PAGE...
www.barracudabuilders.com 17 -026a East Martello Museum - Sanchez Gallery ADA Upgrades
5 of 5
Barracuda Builders of Key West, Inc.
BARRACUDA 5601 3rd Avenue, Key West, FL 33040
B U I L D E R S Florida License Number: CGC1521253
OF KEY WEST, INC.
Ofc: (305) 396 -7752
Fax: (305) 396 -7832
Cell: (305) 747 -4637
REVISED CHANGE ORDER PROPOSAL
To: Monroe County BOCC Date: March 28, 2017
Attn: Chris Rivera Proposal #: 17 -026a
Email: rivera- chris @monroecounty- fl.gov Project: East Martello Museum
Sanchez Gallery ADA Upgrades
Barracuda Builders of Key West, Inc. is pleased to quote the Sum of $60,000 to provide all supervision,
labor, materials, tools, equipment and cleanup for the above referenced project.
Per the East Martello Sanchez Gallery Ramp Information Bulletin #1 and the "East Martello Towers - Sanchez
Gallery ADA Upgrades" plans drawn by Bender & Associates Architects, p.a., dated March 4, 2017; the following
is a continuation of the scope of work included in this proposal:
Summary of Costs
Sanchez Gallery ADA Upgrades
Demo .................................................................................................................................... ............................... $15,620.00
Concrete Ramp / Landing / Railing ................................................................................... ............................... $23,735.00
EntryDoor with Shutter ..................................................................................................... ............................... $7,395.00
Door Operator and Electric ............................................................................................... ............................... $13,445.00
Permit/ Permit Fees ........................................................................................................... ............................... $3,795.00
Professional Courtesy as Discussed with Chris Rivera (Monroe County Project Management) .......... - $ 3,990.00
TOTAL $60,000.00
Note: Final Completion by June 27, 2017
Accepted by: (Authorized Signer)
Date:
Barracuda Builders of Key West
Bryan Wofsey, President
Date:
www.barracudabuilders.com 17 -026a East Martello Museum - Sanchez Gallery ADA Upgrades