Agenda Item Summary #2982
BULK ITEM: Yes DEPARTMENT: Sustainability
TIME APPROXIMATE: STAFF CONTACT: Rhonda Haag (305) 453 -8774
N/A
AGENDA ITEM WORDING: Approval to enter into a $99,596.10 Task Order #3 for
procurement and permitting services for the 4 canals for augmented aeration, under the on -call
contract with Amec Foster Wheeler, Inc. for Category B canal infrastructure engineering services,
which extends services authorized under Amendment No. 8 under a previous AMEC contract.
Remaining funds are carried over from Amendment No. 8 and no new funds are required.
ITEM BACKGROUND: The BOCC previously approved and funded Amendment No. 8 for
$99,956.10 under the AMEC contract for Design of the Demonstration Canals, for permitting and
procurement services for the 4 augmented aeration canals in Key Largo. The permitting and
procurement services were delayed until the funds for construction were finalized under the
Stewardship grant with DEP, to avoid expenditure of funds on design services before construction
funds were located. Therefore the services were not completed within the original time frame. The
new on -call Category B AMEC contract is now active, and this Task Order 3 will extend services
originally approved under the previous Amendment No. 8. Funds remaining under the old
Amendment No. 8 will be used to fund this Task Order #3, and no new funds are required. The work
performed shall not exceed a total of $99,956.10 for Amendment 8 and Task Order 3 combined and
shall be retroactive to March 15, 2017.
PREVIOUS RELEVANT BOCC ACTION:
08/17/16: Approval to advertise on call professional engineering services for the canal restoration
program, including Category A — Canal Master Plan Program Planning Services, Category B —Canal
Infrastructure Engineering Services for Projects and Category C — Environmental Engineering
Services.
11/22/16: Approval of Amendment No. 13 to the contract for Engineering, Design and Permitting
Services of the Demonstration Projects, with AMEC Foster Wheeler Environment and
Infrastructure, Inc. to provide Construction Engineering, Environmental Inspections And
Construction Administration Services in the amount of $88,612, related to Canal #83 muck removal,
backfilling and air curtain project in Key Largo, Monroe County, Florida.
12/14/16: Approval to negotiate on -call contracts with Amec Foster Wheeler, Inc. and Tetra Tech
Inc, the two highest ranked respondents for Category B - canal infrastructure engineering services.
03/15/17: Approval to enter into a $0 on -call contract with Amec Foster Wheeler, Inc. for Category
B canal infrastructure engineering services.
03/15/17: Approval to enter into a $21,499 Task Order 1 for CEI and construction administration
services for the 290 air curtain installation, under the on -call contract with Amec Foster Wheeler,
Inc. for Category B canal infrastructure engineering services.
03/15/17: Approval to enter into a $87,762 Task Order 2 for CEI and construction administration
services for the canal 83 muck removal / backfilling/ air curtain installation, under the on -call
contract with Amec Foster Wheeler, Inc. for Category B canal infrastructure engineering services.
CONTRACT /AGREEMENT CHANGES:
Task Order 3 - Augmented Aeration Procurement and Permitting Servcies
STAFF RECOMMENDATION: Approval
DOCUMENTATION:
AMEC Task Order 3 - Category B - Revised
FINANCIAL IMPACT:
Effective Date: March 15, 2017 Expiration Date: Upon completion of the Task Order
Dollar Value of Task Order 3: $99,956.10 Total Dollar Value of Contract: $208,857
Total Cost to County: NTE $99,956.10 Current Year Portion: NTE $99,856.10
Budgeted: Yes
Source of Funds: 304 Infrastructure Funds previously budgeted and carried over from Amendment
No. 8
CPI: No Indirect Costs:
Estimated Ongoing Costs Not Included in above dollar amounts: O &M Costs
Revenue Producing: No If yes, amount: N/A
Grant: No County Match: N/A
Insurance Required: Yes Additional Details:
03/15/17 304 -23000 - PHYSICAL ENVIRONMENT $21,499.00
REVIEWED BY:
Rhonda Haag
Completed
05/02/2017 3:38 PM
Pedro Mercado
Completed
05/02/2017 3:41 PM
Budget and Finance
Completed
05/02/2017 4:40 PM
Maria Slavik
Completed
05/02/2017 5:35 PM
Kathy Peters
Completed
05/02/2017 8:05 PM
Board of County Commissioners Pending 05/17/2017 9:00 AM
TASK ORDER #3 FOR CATERGORY B ON CALL PROFESSIONAL
ENGINEERING SERVICES FOR CANAL RESTORATION SERVICES
BETWEEN
MONROE COUNTY AND
AMEC FOSTER WHEELER ENVIRONMENT & INFRASTRUCTURE, INC.
FOR
AUGMENTED AERATION PROCUREMENT, DESIGN, AND PERMITTING
SERVICES CANAL #48, #59, #79, AND #80 IN KEY LARGO, MONROE
COUNTY, FLORIDA
In accordance with the Continuing Contract for On Call Professional Engineering
Services made and entered on the 15th day of March, 2017 between Monroe County,
hereinafter referred to as the "County" and Amec Foster Wheeler Environment &
Infrastructure, Inc. hereinafter referred to as "Consultant" where design services are
allowed if construction costs do not exceed $2,000,000.
All terms and conditions of the referenced Contract for On Call Professional Engineering
Services apply to the Task Order, unless the Task Order modifies an Article of the
Agreement of which will be specifically referenced in this Task Order and the
modification shall be precisely described.
These services provide a continuation of services under previously funded Amendment
#8 under the Contract for Engineering, Design, and Permitting Services.
No new funds are requested. All remaining funds from Amendment #8 are carried over
to this task order. This Task Order is effective retroactive to March 15, 2017 and shall
expire 60 days after the final deliverable to the County is submitted.
Article II Scope of Basic Services, Paragraph 2.1.1 is amended as follows:
Task 1: Procurement of Construction Contractor
The Consultant will complete the following tasks related to procurement of a construction
contractor for the in -place muck aeration project with the option to include a
supplemental technology such as use of microbes:
Conduct a Responsibility Review of the Proposals
Consult with and provide technical support and assistance to the County as
required.
Task 2: Permitting
The Consultant will review the selected in -situ aeration contractor's design plans and
prepare a preliminary design package that can be utilized for permitting. The preliminary
design plans will include an existing site plan, proposed site plan, erosion and sediment
control plans, and construction details.
Augmented Aeration Procurement, Design, And
Permitting Services Canal #48, #59, #79, And #80 Projects
Amec Foster Wheeler Environment & Infrastructure, Inc.
May 17, 2017
Page 1 of 2
1sel 03WV - a ;eo SOAS Ilex -u0 JeUeo : Z96Z) POSIAOU - a AJOBG;e:D - E JGPJO )iSe_L:D3WV :;UGwt4:)e;;V
The Consultant will coordinate and hold pre-application permitting meetings with the
South Florida Water Management District {S MD), USACE, Florida Keys National
Marine Sanctuary (FKNMS) and Monroe County using the preliminary design plans.
The Consultant will incorporate any required agency comments into a final design plan
set to be utilized by the contractor for construction.
The total for services to be paid under this Task Order 3 and AS combined remains the
same Amendment No. 8 from the previous Contract for Engineering, Design and
Permitting Services and will not exceed Ninety Nine Thousand Five Hundred Ninety Six
Dollars and Ten Cents ($99,596 , 10).
IN WITNESS WHEREOF, each party caused the Task Order to be executed by its duly
authorized representative.
m9ifflow
Signature ' Date
Title
ATTEST: KEVI AROS, CLERK
bat6
C
BOARD OF COUNTY COMMISSIONERS
OF MONROE COUNTY, FLORIDA
By by:
Deputy Clerk Mayor/Chairman
Date:
Augmented Aeration Procurement, Design, And
Pe Ming Services Canal #48, #59, #79, And #80 Projects
Amec Faster Wheeler Environmcnt & InfraLtructure, Inc.
May 17, 2017
Page 2 of 2
EXHIBIT A
CONSULTANT'S PROPOSAL
May 1, 2017 4*
amec
Rhonda Haag foster
Monroe County Sustainability /Projects Director
102050 Overseas Highway, Ste. 246 wheeler
Key Largo, Florida 33037
Re: Scope of Work Related to Augmented Aeration Procurement, Design, and Permitting
Services Canal #48, #59, #79, And #80 In Key Largo, Monroe County, Florida
Dear Ms. Haag:
AMEC Foster Wheeler assisted the County in selecting four canal sites for implementation of the
alternative canal restoration technology of Augmented Aeration. These canals are:
• Canal #48 Key Largo located adjacent to Sound Drive
• Canal #59 in Key Largo located between Waterways and Harbor Drives
• Canal #79 Key Largo located adjacent to Mockingbird Road
• Canal #80 Key Largo located between Mockingbird and Heron Roads.
Details of the proposed scope of services are provided below. A cost estimate to perform these
services under Amec Foster Wheeler's existing contract rate schedule is also included.
SCOPE OF SERVICES
Task 1: Procurement of Construction Contractor including Canal #59, #48, #79 and #80
Amec Foster Wheeler will complete the following tasks related to procurement of a construction
contractor for the augmented aeration projects with the option to include a supplemental
technology such as use of microbes:
• Conduct a Responsibility Review of the Proposals
• Consult with and provide technical support and assistance to the County as required.
Task 2: Permitting
Amec Foster Wheeler will review the selected in -situ aeration contractor's design plans and
prepare a preliminary design package that can be utilized for permitting. The preliminary design
plans will include an existing site plan, proposed site plan, erosion and sediment control plans,
and construction details.
Amec Foster Wheeler will coordinate and hold pre - application permitting meetings with the
South Florida Water Management District (SFWMD), USACE, Florida Keys National Marine
Sanctuary (FKNMS) and Monroe County using the preliminary design plans.
11 Page
Packet Pg. 2622
Scope of Work for Augmented Aeration
Procurement, Design, and Permitting
Services Canal #48, #59, #79, And #80
In Key Largo, Monroe County, Florida
Amec Foster Wheeler will incorporate comments received during the pre - application meetings
to complete and submit local, state, and federal permit applications as required, using the final
design plans. Permit applications will be submitted to the following agencies:
• SFWMD
• USACE
• FKNMS
• Monroe County.
Amec Foster Wheeler will respond to up to two Requests for Additional Information (RAI) for
each permit application. If there is a major permitting issue related to the Contractors
supplemental technology that requires more extensive additional information responses,
Monroe County will be contacted to determine how to proceed. Monroe County will pay the
required permit application and permit fees, except for those from Monroe Counties.
Amec Foster Wheeler will incorporate any required agency comments into a final design plan
set to be utilized by the contractor for construction.
COST ESTIMATE
The total for services to be paid under this Task Order 3 and A8 combined remains the same
Amendment No. 8 from the previous Contract for Engineering, Design and Permitting Services
and will not exceed Ninety Nine Thousand Five Hundred Ninety Six Dollars and Ten Cents
($99,596.10).
CLOSING
Amec Foster Wheeler appreciates the opportunity to assist Monroe County with this exciting project.
Should you have any questions regarding this proposal or need additional information, please contact
Greg Corning at (314) 920 -8359 or via email at gLeq.corning@amecfw.com
Sincerely
Amec Foster Wheeler Environment & Infrastructure, Inc.
Ricardo Fraxedas, PE
Chief Engineer
Direct Tel: + 1 305 525 0079
Direct Fax: + 1 305 826 1799
E -mail: ricardo.fraxedas @amecfw.com
c
"-
Greg Inning, PE
Technical Professi nal III - Engineer
Direct Tel: + 1 314 920 8359
Direct Fax: + 1 305 826 1799
E -mail: gLeg.coming @amecfw.com
Attachments: Amec Foster Wheeler Rate Schedule
21Page
Packet Pg. 2623
Amec Foster Wheeler Environment & Infrastructure, Inc.
2017 Schedule of Fees
I. Personnel
A. Professional (Engineer, Geologist, Scientist and Project Management)
Staff I
$71.00 /hour
Staff 11
$77.00 /hour
Project
$86.00 /hour
Senior
$109.00 /hour
Principal /Project Manager
$155.00 /hour
Senior Principal /Senior Project Manager
$159.00 /hour
Chief Engineer /Scientist
$194.00 /hour
B. Technical Services (Engineering and Science)
Technician I
$45.00 /hour
Technician II
$55.00 /hour
Senior Technician I
$60.00 /hour
Senior Technician II
$70.00 /hour
Project Administrator /Project
Coordinator /Subcontract Administrator /Project
Accountant
$75.00 /hour
Technical Writer /Document Production
$ 78.00 /hour
CADD /Draftsperson (includes PC /CAD) I
$66.00 /hour
CADD /Draftsperson (includes PC /CAD) II
$101.00.hour
Admin I
$40.00 /hour
Admin II
$52.00 /hour
C. Surveying Services
Field Surveyor I
$43.00 /hour
Field Surveyor II
$47.00 /hour
Survey Technician I
$67.00 /hour
Survey Technician II
$72.00 /hour
Survey Chief
$75.00 /hour
D. Information Management
Software Engineer
$92.00 /hour
Data Technician
$132.00 /hour
Senior Software Engineer
$162.00 /hour
Business Analyst
$132.00 /hour
E. Contract Labor
From time to time, Amec Foster Wheeler retains outside Professional and Technical labor on a
temporary basis to meet peak workload demands. Such contract labor will be charged at 10% markup.
II. Expenses
A. Travel Expenses
Transportation: Company pickup truck /personal vehicle, per mile — current allowable rate per
County and Florida State Statutes
a. Common carrier or car rental multiplies by (to be the amounts authorized by Section
112.062, Florida Statutes
2. Per Diem Expenses: direct expenses in accordance with Florida State Statutes
B. Disposal of Hazardous Waste Samples
Samples of waste will be disposed by permitted methods after a determination is made that the waste is
defined by RCRA to be hazardous. Due to the requirements for some hazardous assessments, disposal
and invoicing of incurred expenses may take place after invoicing of the originally contracted work.
C. Equipment / Other Expenses
(Does not include personnel)
Digital Field Documentation Equipment (cameras,
$75.00 /day (min 2 days
water level & measuring tape, GPS units, etc.)
Geophysical Equipment (GPR Equipment)
$1,000.00 /day (min 2 days)
Underwater Camera Equipment /Video up to 50
$1,900.00 /day
feet depth and low turbidity
Environmental Monitoring & Sampling
$100.00 to $450.00 /day
Equipment (dust, OVA, Air monitoring, Noise
Depending upon the equipment and scale
Meter, Light Meter)
required
Special equipment or supplies, permits, shipping
Actual cost x 1.15
charges, special printing or other items not
customarily provided by Amec
D. Communications
In -house costs for long distance phone, telex, telecopier, postage — project labor charges x 5%
III. Subcontract