2nd Change Order 03/22/2017MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
ORDER PROJECT TITLE: CHANGE
HVAC System Improvements
Stock • Jail Complex INITIATION 0
WT-11F ! ! . 1 ' i
in 7 • I. • I MF ! 111111111
• • • • • ' 1. ! ''.
Sea Tech is reuoesting_a 60 day no cost time -extension to their contract,dge to delays In the
procurement of the Electrical hardware. Electrical Submittal #5.6 submittQd on 12114!16 and
returned to the contractor on.1 &21/16 with the engineers comments. Sea Tech Re submitted on
ZQ201T-and returned to the Contractor on 2110!2(117 with the Engineers comments.
This chanae Order is 0.0% of the original contract price. .
Not valid until signed by Owner, Architect rapollcabie„1. and Contractor
ARCHITECT:
Date
CONTRACTOR: I
DIRECTOR PROJECT MANAGEMENT: /7 .3 } Z4 f
AM: FM
• i •: • •:• • ♦ r ; M-1 OR m
If Yes, explanation: Sea Tech is requesting a_60 day no cost time extension to their contract
due to delays in the procurement of the Electrical hardware. Electrical Submittal #5.6
submitted on 12/14/16 and returned to the contractor on 12/20/16 with the en ip neers
comments. Sea Tech Re submitted on 2/212017 and returned to the Contractor on
2/10/2017 with the Engineers comments.
•c r- • - r! • •' • Milli
s
mmmm�m MIN
I�I�N�i1.LLiiY
%¢aT¢Ch /No inc.
Re: CSO HVAC tag.!es
Subject: Time Extension
Sea Tech has every intention • accelerating the work progress to reduce the tinj
indicated on the project schedule. Please advise if you need additional information. I may
reached at (305) 872-0888.
UM=
Ryon LaCbapelle
Project Manager