05th Change Order 05/31/2017MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 5
HVAC System Improvements
Stock Island Jail Complex INITIATION DATE: May 30,2017
11:411-LiALM-1 all Ir-l-A-ItTWO M1 It
11,7_7101'sM
M-11
�ea Tech Is LgMesting a 90 day no cost time extension duetpaeveral delays -in the insLallation of
Chiller #1 -We hay-q alpg Included in 1h@ contract CQ# 03, tereplac-ement of the Chiller towers
Fans Gearg and -Hout;Ings. Thi§ rk can nob e scheduled with thg Eubcontractor unt1l June 8L
2017,
This change
Order is 0.0% of the original contract Price.
N
NFAWM
�B
FZIFJ§ ,T� w R 'loIV
If Yes, explanation: Sea Tech is recluesting a 90 day no cost time extension dwe to serval
delays in the installation of Chiller #1. We Have also included in the contract CO# 03, the
replac omet oft Chiller towers Fans Gears and Housings. This work cannot be
spheduled with the -subcontractor until June 8, 2017.
4 Z 0 1 1 :r * 0 -=IW
I
912=1 MT Fil F 1 11 Ill 1! 111 a : - 4 0 66
'A I I 1--1 11:11 to] ill � I ill !I �!i ill
e aTea h oo*�
Re: MCSO HVAC Upgrades
Subject: Time Extension
ram W M I M- Om 57
Sea Tech is requesting a ninety (90) day no cost time extension to our contract. There
have been several delays in the installation of Chiller #1. We have also included in the contrac)
CO#03 — Replace the housing, gears and fans in the existing cooling towers, this work cannot be
scheduled with the subcontractor until 8JUN2017 and resulted in extending the overall duration
at the detention center. These delays will result in a substantial completion date of 18AUG2017.
Sea Tech has every intention of accelerating the work progress to reduce the time
indicated on the project schedule. Please advise if you need additional information. .1 may be
reached at (305) 872-0888.
Sincerely,
Ryon LaChapelle
Project Manager