3rd Change Order 10/06/2016MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECTTITLE: CHANGE ORDER
SR 4A Little Torch Boat Ramp Repairs
1200 Truman Ave, Key West, FL 33040 INITIATION DATE: September 19, 201
TO CONTRACTOR:
it
The original (Guaranteed Maximum Price) .................................... ... _.$112,525.00
Net change by previously authorized Change Orders .............. .............................. $18,803.00
The (Q2akagL_SMm_) (Guaranteed Maximum Price) prior to this Change order was............ $131,328.00
The (Contract Sum) (Guaranteed Maximum Price) will 96in eased) (decreased)
'f(Uffghgo ) by this Change Order ...... $0
The new (g2njgLcL$yM) (Guaranteed Maximum PrIce)6cluding this Change Order is ...... $131,328.00
The Contract Time will be Cincrease A (decreased) (unchanged) by .............................. 25 Days
The date of Substantial Completion as of the date of this Change Order is ..............October 14, 2016
Contractor is requesting a no cost time extension. Delays in deliveu of the coffer damn due -to
winds from tropical disturbance L99 delayed dewatering of th"r rnp. Damage- to the ramp during
installation of the coffer dam will reguire pqrmitted repairs.
This change Order is no cost and 0% of the original contract grim.
Not valid until sian2d by Owner, Architect fif applicablel, and Contractor
UERM991
1122 12016
Kei s, P.A. Date
CONTRACTOR: [
Se Te the Florida keys, —Inc. to Date
�
Dir. PROJECT MANAGEMENT: 10
Doug Spos Date
COUNTY/DEPUTY ADMINISTRATOR:
Wornlff&A"'tnty Ac11"T"sF1aTo—r Date
Kevin Wilson
Christine Hurley
Change Order was not included in the original contract specifications. Yes E No
Z' I I 11i III 1::: 11 111 11, 11 ill
Em�
Project architect approves the change order. Yes Z No F-1
k a
X
MEMMUMMUMM
r-97
I 100 Simonton St
Key West, FL 33040
Re: Repairs to Little Torch Boat Ramp
Subject: Time Extension
Dear Mr. Knight,
Sea Tech is requesting a Twenty Five our contract.
There have been delays in the procurement and installation of the cof'[e We made changes
to the cofferdam and submitted a change order on 14JUL2016, which was approved on
I AUG2016. Upon approval we ordered the cofferdam to be installed and had a scheduled date of
I SEP2016. The ordered sheet piles were the sheet
piles arrived on 9SEP2016. The cofferdam was then installed the following business day
12SEP2016; this resulted in an Eight (8) day delay. Once we were able to dewater, the
engineering department found substantial damage to a portion of the boat ramp as a result of
SeaTech lifting the slab during the installation of the cofferdam. This resulted in replacement of
a 12' x 15' section of the concrete boat ramp. This work needed engineered drawings and
pen-nitting. This will result in another Seventeen (17) days delay. This will give us a substantial
completion date of 140CT2016.
Sea Tech has every intention of accelerating the work progress to reduce the time
indicated on the project schedule. Please advise if you need additional information. I may be
reached at (305) 872-0888.
Sincerely,
Ryonl Z aChape&e,- 91/
you LaChapelle
Project Manager
r1r) ff:ffITjK*j;Y_I WiTINIIIIII J
07MMMOTIMT-76 =-
From: County Administrator/Assistant County Administrator/Acting County
Administrator
According to Ordinance 026-1998 adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners at least 24 hours prior to approval, assuming they are within the
Administrator's prescribed limits. Change orders not within the Administrator's authority
are placed on the BOCC agenda.
t01547-01b
n!y Administraff-r-
Signature
County Administrator/Assistant County Administrator/Acting County
Administrator
A