9th Change Order 07/26/2017MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 9
The Redevelopment of Bernstein Park
INITIATION DATE: July 5, 2017
TO CONTRACTOR:
Burke Construction Group, Inc.
10145 NW 19"' St
Doraf FL 33172
The Contract is changed as follows:
CONTRACT DATE: April 20, 2016
The original (Contract Sum) (Guaranteed Maximum Price), _$7, 921,975.00
Net change by previously authorized Change Orders ........
The (Contract Surn) (Guaranteed Maximum Price) prior to this Change order was --- $7,737,574,08
The (Contract Sum) (Guaranteed Maximum Price) will be, (increased) (decreased)
(unchanged) by this Change Order ...... $70,949,03
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is
The Contract Time will be (increased) (decreased) (unchanged) by,. ....... ......49 Days
The date of Substantial Completion as of the date of this Change Order is., September 25, 2017
Detailed description of change order and justification,
Additional sewer lateral needed to be Installed than desicIned, Added 40 fiicq of new fence
contractor regraded plaound to improve dreinage. 7zxlerWed Curbs Under rooftop HVAC,
upgraded from, Be rr.-I Lida 419 crass to Seashore "Su Qrem Paspall um for fields- Inclusion of the
hood was not clear in the kitchen.
This Chancle Onlier is 0.9%, of the orictinal contract orice'.
Not valid until sinned by Owner. Archilect 0fE(Policable), and Contractor
ARCHITECT: J -71Z 401IL7
-William Horn P, Date
CONTRACTOR:
-4:-)�2Q_ Ful) 1�0 Date
77 y
y
DIRECTOR PROJECT MANAGEME 'f"4'
Da
, r:'A"C
'41, P�e' in ZWils�onCkris
COUNTYIASSISTANT ADMINISTRATOR:
Roman Gast si, [�ir _r, Christine Hurley Date
If Yes, explanation:
Contractor had to spread additional gravel by hand to raise playground grade. Kitchen Hood
required additional design. Contractor upgraded Field Turf to Seashore Paspalum.
If Yes, explanation of increase in price: Contractor had to revise sewer connection, and
kitchen hood required additional design,
111 1111 111 � i III
FIRMS
0 Change Order is correcting an error or omission in design document. Yes 7No E]
FAR,
Explain: Grading in childrens' areas was not compliant, manhole did not exist in right of
way.
Change OWNER x
Order
Request ARCHITECT
CONTRACTOR x
Am Document G710 FIELD U RKE
SUBCONTRACTOR Construction Group Inc.
PROJECT: Bernstein Park CHANGE ORDER NUMBER: 013
6751 5th Street DATE: 2/27/2017
Stock Island< Florida 33040 CONTIRRACTOR PROJECT: 1611
CONTRACTOR: Burke Construction Group, Inc.
10145 N.W 19th Street
Doral, Florida 33172
Prime Contract Change Order #013: New Sewer -® Connection
TO: Monroe County Engineering FROM: Burke Construction Group, Inc.
1100 Simonton Street 10145 NW 19th Street
Key West, Florida 33040 Miami Florida 33172
DATE CREATED: 2/27/2017 CREATED BY: Armando Silveira (Burke Construction Group,
Inc.)
CONTRACT STATUS: Pending - In Review REVISION: 1
DESIGNATED REVIEWER: Armando Silveira (Burke Construction REVIEWED BY:
Group, Inc.)
DUE DATE: REVIEW DATE:
INVOICED DATE: PAID DATE:
SCHEDULEIMPACT: 0 days EXECUTED: No
CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT- $ 19,265.63
DESCRIPTION:
Attached is the price to alter the sewer tie in connection from the original base bid to the new revised location provided by Perez Engineering, Sheet E-
5 Revision #4 dated 11110/16. Burning the connection process KWRU requested special order fittings to do the connections. Attached is the revised
actual cost for the work.
Please note that this Change Order Request does not include time since we do not know the time frame for this work to be permitted and approved by
KWRU or Monroe County. Burke Construction is reserving its rights to request additional time and/or compensation when all the unknown permitting
and approval issues are resolved.
ATTACHMENTS:
Change Order I Revised 06. 13.17 (002).pdf C-5.Rdf _Memo Siyle.pdf
•
Burke Construction Group, Inc. page 1 of 2 Printed On: 6122/ 2017 04 :19 PM
Change OWNER F—X
Request ARCHITECT
CONTRACTOR
AIA Document G710 FIELD U R K E
SUBCONTRACTOR Construction Group Inc.
OveFhead: 5.00% on all line item types
Proft 5.00% on all line Item types
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum would be changed by this Change Order in the amount of
The new contract sum including this Change Order will be
The Contract Time will be (increased) (decreased) (unchanged) by
The date of Substabtlal Completion as of the date of this Change Order therefore is
$ 7,921,975.00
($188,252.85)
$ 7,733,722.15
$ 19,265.63
$ 7,752,98778
0 days
Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount
for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime,
acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related
items prior to final settlement of this contract,
Bill Horn (Architect)
1100 Simonton Street
Key West Florida 33040
7-M
Burke Construction Group, Inc. page 2 of 2
L*-917XOMKMi1�11!1111111
10145 NW 19th Street
Miami Flond,3 33172
SIGNATURE DATE
Printed On: 6/22/ 2017 04 :19 PM
KEY IRON WORKS, INC.
555121' Avenue Key West, Florida 33040
Phone 305.294.0277 Fax 305.296.4460
Email
Armando L. Silveira
Burke Construction Group, Inc.
10145 MW 190' Street
Doral, Florida 33172
Office: 305,468.6604
Fax: 305.468.6654
Cell: 3053217862
E-mail:
RE: Bernstein Park, 5 1h Avenue, Sewer System — Change Order #1, Revised 06.13.17
Dear Mr. Armando L. Silveira:
Please find below a summary of costs related to charges in the location and methods of connecting the new
sewer lateral to the existing sewer main overflow on Fifth Street.
Schedule of Bid Documents:
1. Plans and Specifications by Perez Engineering, Sheet C-5 dated 11 .30.16 including revision dated
11.10.16.
rX-1r1jnVTMr6=
a. Original footage 217 Lft. of (4") four -inch PVC sewer piping
b. Revised footage 268 Lft.
c. Net Additional Piping Required 51 Lft at $ 75.00 Lft.
Additional Cost: $ 3,825.00
2. Connection to main overflow bypass line including materials, labor, trench safety and dewatering
related work
Additional Cost: $ 7,400.00
Burke Construction — Attn,, Arrnando L. Silveira
Project — Bernstein Park, Change Order #1 Revised 06, 13,77
3. Credit for 4" four -inch manhole tap/connection
Additional Cost: R; -1,000.00)
4. 8" Schedule 40 PVC pipe connection work -
a. (2 oft Stainless steel high pressure repair bands (Required by KWRU)
Additional Cost: 597A]
Additional Cost:
$
355.00
c, Remove FKAA approved bands and install stainless steel bands (As Required by KWRU)
i. Plumber 8 Hours at $ 115.00 per hour
$
920.00
it, Labor 8 Hours at $ 45.00 per hour
$
360.00
iii, Equipment rental JD-50 8 Hours at $ 135.00 per hour
$
1,080.00
Additional Cost:
$
2,360.00
d. Additional trench /pit safety installation and maintenance (2-week period)
i. Road plate rental (I of) 8' x 20' road plate at $ 375.00 per week
$
750.00
it. Road plate rental (2 of) 6' x 16' Road Plates at $300.00 per week $
1,200.00
iii. Courtesy Discount 10% of $ 1,950.00
$
195.00
iv. Equipment Rental JD-50 2 hours at $135.00 per hour
$
270.00
V. Labor (4 hr.) four hours (2) two men set and maintain at
$45.00 per hour
$
360.00
Additional Cost:
$
2,385,00
Subtotal: $ 15,922.01
Overhead/Prorit 10%: $ 1,592.20
to Additional Cost: $ 17,514.21
Sincerely
(Yfeve JR 3FevzoV4
Steve R. Henson, President
ENG I 222A
CGC 047345
Change
OWNER
x
Order
Request
ARCHITECT
CONTRACTOR
X
FIELD
AJA Document G710
SUBCONTRACTOR
PROJECT.
Bernstein Park
CHANGE ORDER NUMBER:
6751 5th Street
DATE:
Stock Island{ Florida 33040
CONTRACTOR PROJECT:
CONTRACTOR: Burke Construction Group, Inc.
10145 N.W. 19th Street
Doral, Florida 33172
1 ,401, B URINE
COI1StIAI(d0F1 GI -OUP inc.
021
6/21/2017
1611
-Prime Contract Change Order #021: Additional Aluminum Picket Fence
TO: Monroe County Engineering
FROM:
1100 Simonton Street
Key West, Florida 33040
DATE CREATED: 012112017
CREATED BY:
CONTRACT STATUS: Pending - In Review
REVISION:
DESIGNATED REVIEWER: Armando Silveira (Burke Construction
REVIEWED BY:
Group, Inc.)
Burke Construction Group, Inc.
10145 NW 19th Street
Miami Florida 33172
Armando Silveira (Burke Construction Group,
Inc.)
0
DUE DATE:
REVIEW DATE:
INVOICED DATE:
PAID DATE:
SCHEDULEIMPACT-
EXECUTED: No
CONTRACT FOR: 1:Redevelopment of Bernstein Park
TOTAL AMOUNT- $ 5,136.08
DESCRIPTION:
Provide and install aluminum picket fence between Maintenance Building
& Pond mounted in ground. Also additional cost to mount picket fence by
Entry Romp 2.
ATTACHMENTS:
F. I WIRWZ
Burke Construction Group, Inc. page 1 of 2 Printed On: 6/2312017 09 :05 AM
Change OWNER X
Order
Request ARCHITECT
CONTRACTOR X
AIA Document G710 FIELD
SUBCONTRACTOR Construction Group Inc.
LJ R K E
PCO # 021 : Additional Aluminum Picket Fence
The original (Contract Sum) $ 7,921,975.00
Net change by previously authorized Change orders ($188,252.85)
The contract sum prior to this Change Order was $ 7,733,722A5
The contract sum would be changed by this Change Order in the amount of $ 5"IX08
The new contract sum including this Change Order will be $ 7,738,85823
The Contract Time will be (increased) (decreased) (unchanged) by
The date of Substabtial Completion as of the date of this Change Order therefore is
Master Permit Issue Date: E� Contract Base Days: 330 Added Time Above:
Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount
for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime,
acceleration and or impact Costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related
items prior to final settlement of this contracL
awwm==
mo
1100 Simonton Street
Key West Florida 33040
ma
Burke Construction Group, Inc.
10 145 NW 19th Street
Miami Florida 33172
=I
Burke Construction Group, Inc, page 2 of 2 Printed On: 6/23/ 2017 09 :05 AM
Ultra Aluminum Mfg., Inc.
2124 Grand Commerce Drive
Howell, Michigan 48855
517-548-6755 Fax: 517-548-6756
Prepared By: Dan
Prepared for: BURKE CONSTRUCTION GROUP
10145 NW 19th STREET
DORAL, FL 33172
�1.0. Number: B. Park 72H
Quantity Description Quotation Color: Black
Quotation
325T—AA
Prepared On
6YI2017
UAF-200 - Flat Top Industrial, 4" Spacing,Fully Welded at each Cross Member,
Standard Bottom 145.90 875.40
6 72" H x 6'W, 3 Rails
5 Blank Posts - 4" Square x 8'x 125 Punched as Lines 85.20 426.00
2 Blank Posts - 4" Square x 8'x.125 Punched as Ends 85.20 170.40
7 Caps - 4" Square 0.00 0.00
I Paint - Spray Can Touch Up 12.00 12.00
40 Screws - #8 x 2 Hex Washer Tek Black 0.00 0.00
Notes Sub -Total: $1,483.80
Please ship with Other: $0.00
ULT# Tax: $0.00
Freight: $0.00
Total: $1,483.80
Quotation valid for 30 days from Date prepared.
Ultra Aluminum • Inc. Quotation
2124 Grand Commerce Drive
Howell, Michigan 48855 BUR0352 - Q532578A
517-548-6755 Fax: 517-548-6756 Prepared On
6/7/2017
Prepared By: Dan
Prepared for: BURKE CONSTRUCTION GROUP
10145 NW 19th STREET
DORAL, FL 33172
Quantity
Description Quotation Color: Black
Price
Amount
UAF-200 - Flat Top Industrial, 4" Spacing, Fully Welded at each Cross Member,
Standard Bottom
3
48" H x 6'W, 3 Rails
117.10
351.30
2
Line Posts - 3" Square x Tx .125 Cut to 51" with Welded Flanges
39.20
78.40
2
Blank Posts - 4" Square x 5'x .125 Cut to 51" with Welded Flanges End Punched
59.00
118.00
2
Caps - 3" Square
0.00
0.00
2
Caps - 4" Square
0.00
0.00
12
Screws - #8 x 1" Self Drilling (per Hundred)
0.00
0.00
2
Floor Flanges - 5" Welded Flange
1900
38.00
2
Floor Flanges - 6 " Welded Flange
75-00
150.00
24
Screws - #8 x 2 Hex Washer Tek Black
0.00
0.00
1
Paint - Spray Can Touch Up
12.00
12.00
Notes Sub -Total: $747.70
Please ship with ULT# Other: $0.00
2- 8" x 8" Tax: $0.00
Flanges Freight: KOO
Total: $747.70
Quotation valid for 30 days from Date prepared.
FENCE MASTERS, INC.
3550 N. W. 54TH STREET
MIAMI, FLORIDA 33142
DADE: (305) 635-7777 * BRONVARD (954) 463-3172 * FAX: (305) 635-7887
Rate: June 23, 2017 Name: Armando Gomez
Company: Burke Construction Group Job Name: Bernstein Park
Address: 10145 NW 19th St
City: Broad, FL 33172 Job Address: Stock Island
Phone: (305) 468-6604, Fax:
We propose, subject to acceptance by Fence Musters, Inc., (Teller) to perform work in accordance with quantities and sizes listed
below. Before erection is begun, put -chaser is to establish property line stakes and grade stakes and to remove all obstructions that
may interfere was erection. Purchaser is responsible for location es'any underground linaw. Fence plastery, Inc, is not responsible for
any damage to unmarked lines After the contract is executed and received by Fence ithusers, Inc., notice to proceed is to be provided
by purchaser at least 14 days prior to date ofcominencernme of the work-, In order to avoid unforeseen con fleets in contract language,
by signing this contract you are waiving any obligation on our part to sign any connotes or other document that you subsequently may
offer, provide, at- dernesed This contract will be the only contracifter this job and is binding on both parties.
Install Owners Material
3 — 6'x 4' High aluminum fence panels on top of wall (anchors by others) $1,935-00
6 — 6'x 6' High aluminum fence panels set in concrete footings (bag mix by FM) $ 675,00
Price complete $2,610,00
IMPORTANT PRICING NOTE:
Due to recent conditions beyond our control relating to raw steel material availability, this price is ,subject to change.
Actual price will be based on receipt date of executed contract and mill price increases if any.
Permit Costs are not included in this price, and if required, will be added as a Change Order to this contract
Subject to credit approval by Fence faicters, Inc Terms are net on billing Interest of I ti % per month will be charged on accounts Fast due Title to the property as
addricaccl by this proposal shall remain in the seller, Fence Masters, Inc until payment in full is received, pursuant,to the terms hereof This is a retain title contract
In the event the money due hereunder, at, anyportion thereof, has to be collected on demand sh"an satorney, or by suit, the purchaser agrees to
pay all costs eli"collection including interest at the highest legal rate and reasonable atterneyefeme
Approved SlAccepted: V6saceichasesps, Inc. (Seller) Approved (c Accepted by Purchaser:
Burke Construction Group
Fly
Signature
Signature
Robert S. Miller, Project Manager Armando Gomez,
Steel & Aluminum Picket Fence ** Chain Link ** Highway Guardrail ** Site Pollack; ** Access Control Systems
Since 1947
Change OWNER x
Order
Request ARCHITECT
CONTRACTOR x
AIA Document G710 FIELD BURKE
SUBCONTRACTOR C0115tructioll Groty Inc.
PROJECT. Bernstein Park CHANGE ORDER NUMBER: 022
6751 5th Street DATE: 6/21/2017
Stock Island{ Florida 33040 CONTRACTOR PROJECT#: 1611
CONTRACTOR: Burke Construction Group, Inc.
10145 N.W. 19th Street
Coral, Florida 33172
Prime Contract Change Order #022: Regrade Playground Area & Rebar in
Curb
TO: Monroe County Engineering FROM: Burke Construction Group, Inc.
1100 Simonton Street 10145 NW 19th Street
Key West, Florida 33040 Miami Florida 33172
DATE CREATED: 6121 /2017 CREATED BY: Armando Silveira (Burke Construction Group,
Inc.)
CONTRACT STATUS: Pending - In Review REVISION: 0
DESIGNATED REVIEWER: Armando Silveira (Burke Construction REVIEWED BY:
Group, Inc.)
DUE DATE: REVIEW DATE:
INVOICED DATE: PAID DATE:
SCHEDULEIMPACT- EXECUTED: No
CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT: $6,804.42
DESCRIPTION:
Cost to regrade playground area due to drainage issues caused by the different elevation issues. Due to playground equipment being installed, the
area had to be regraded by hand. Cost also includes the additional rebar in playground curb for additional reinforcement due to fence post being
attached to the curb.
ATTACHMENTS:
190,11MI1
Burke Construction Group, Inc. page 1 of 2 Printed On: 6/2112017 10 :08 AM
Change
OWNER
X
Order
Request
ARCHITECT
CONTRACTOR
X
FIELD
AIA Document G710
SUBCONTRACTOR
Pr`n id 1`199 • Panrarle Plavnrnirnei reran and add rahar to Pinvnrnund r-nrhs
j,'jj B URINE
Construction Group Inc.
#
Cost Code
Description
Type
Amount
1
03-350 - CONCRETE CURB SUPPORTING
Additional rebar at playground curb
Subcontractor
$ 985 40
PICKET FENCE AT PLAYGROUND
2
02-1 - SITEwORK
Provide 3 loads of 57 rock to regrade the play ground area due to drainage
'slues
Subcontractor
$ 2,100 00
Wheel barrel and hand grade playground area to regrade due to drainage issues
Subcontractor
$ 3,120 00
3
02-1 - SITEwORK
This work Look 3 men 4 days to complete at $32 50 per man noun-
4
03-350 - CONCRETE CURB SUPPORTING
Saw cut curb to place playground gate in new location due to drainage issues.
Subcontractor
$ 275,00
PICKET FENCE AT PLAYGROUND
Subtotal:
$6,480 40
Overhead : 2.50 % on all line item types
16201
Profit. 250% on all line Itan, types
16201
Grand Total:
$6,804.42
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum would be changed by this Change Order in the amount of
The new contract sum including this Change Order will be
The Contract Time will be (increased) (decreased) (unchanged) by
The date of Substantial Completion as of the date of this Change Order therefore is
Master Permit Issue Date: 8/18/2016 Contract Base Days: 330
r + l
$ 7,921,975.00
($188,252,85)
$ 7,733,722.15
$ 6,804A2
$ 7,740,526.57
Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount
for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime,
acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related
items prior to final settlement of this contract.
i
■
1
Y } 17MMIUMY...
1100 Simonton
Key West Florida 33040
10145 NW 19th Street
Miami Florida 33172
SIGNATURE DATE SIGNATURE DATE
page 2 of 2 Printed On: 6/21 / 2017 10 :08 A
Bella Construction of Key West, Inc.
CGC 1518284
35 Diamond Drive
Key West, FL 33040
Office (305) 292.9888
Fax (305) 292.9880
wil1@1 (: ur 1cf c tub a. I I a -con
MMEM�; 1 �-�
Date: May 4, 2017
To: Burke Construction
Change Order No.: 11
From: Bella Construction of Key West
Attn: Armando Sliveira Project Title: Bernstein Park
Additional Curb Work at Playground
Email! asInitiation Date: 10/26/2016
The Contract is changed as follows:
1 [Additional Reber for Playground Curb Construction
E=
I Total
M
Page 1 of 1
SLAZAR CONSTRUCTION & PLUMBING
11400 OVERSEAS IENY STE' 103
S LAZA R MARATHON, FL 33050
CONSTRUCTION PHONE: 305-735-4351
8 PLUMBING FAX: 305-735-4352
EMAIL: sales(asiazarccrostruction.com
License# CGC1522893 I License## CFC1429579 I License# CUC1225339
Name / Address
Job Site Address
BURKE CONSTRUCTION GROUP IC
10145 N. 19TH STREET
DORAL, FL 33172
BERNSTIN PARK
6751 5TH STREET
STOCK ISLAND, FL 33040
Qty
Description
Rate
Total
3
3/4" GRAVEL #57 ROCK, BY THE LOAD
700.00
2,100.00
I FIND THE ABOVE SATISFACTORY AND AGREE TO PAY FOR SAME ON PRESENTATION OF
STATEMENT AND FURTHER AGREE TO PAY REASONABLE CHARGES FOR COLLECTION
INCLUDING ATTORNEYS FEES IN THE EVENT OF MY DEFAULT, YOU ARE AUTHORIZED TO DO
THE WORK SPECIFIED. PAYMENT WILL BE MADE AS OUTLINED ABOVE.
Subtotal
$2,100.00
Sales Tax (7.5%) $0.00
Total $2,100.00
ACCEPTANCE SIGNATURE:
DATE:
Change OWNER X
Order
Request ARCHITECT
CONTRACTOR X
AIA Document G710 FIELD U R E
SUBCONTRACTOR Construction Group Inc.
PROJECT.- Bernstein Park CHANGE ORDER NUMBER: 024
6751 5th Street DATE: 7/14/2017
Stock Island< Florida 33040 CONTRRACTOR PROJECT: 1611
CONTRACTOR: Burke Construction Group, Inc.
10145 N.W. 19th Street
Doral, Florida 33172
Prime Contract Change Order #024: RTU Curb Extenders
TO: Monroe County Engineering FROM- Burke Construction Group, Inc.
1100 Simonton Street 10145 NW 19th Street
Key West, Florida 33040 Miami Florida 33172
DATE CREATED: 7/1412017 CREATED BY: Armando Silveira (Burke Construction Group,
Inc.)
CONTRACT STATUS: Pending - In Review REVISION: 0
DESIGNATED REVIEWER: Armando Silveira (Burke Construction REVIEWED BY:
Group, Inc.)
DUE DATE: REVIEW DATE:
INVOICED DATE: PAID DATE:
SCHEDULEIMPACT- EXECUTED: No
CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT- $6,699-00
DESCRIPTION:
Price is to supply and install curb extenders to 4 existing RTU's due to curbs not meeting minimum height above roof deck. Plans call for 14" curbs and
roofing material is over 8" height to comply with R value.
ATTACHMENTS:
POTENTIA1, CHANGE ORDERS ANT IS CHANGE ORDER:
141*0LIN1491
1� �01 � �z �'- - I �—
Burke Construction Group, Inc. page 1 of 2 Printed On: 7/14/ 2017 02 :15 PM
Change OWNER X
Order
Request ARCHITECT
CONTRACTOR X
AIA Document G710 FIELD BURKE
SUBCONTRACTOR Construction Group Inc.
The original (Contract Sum) $ 7,921,975.00
The contract sum prior to this Change Order was
The contract sum would be changed by this Change Order in the amount of
The new contract sum including this Change Order will be
The Contract Time will be (increased) (decreased) (unchanged) by
1 11 1 1 11s 1
Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any arnounit
for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime,
acceleration and or imgact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related
items prior to final settlement of this contract.
WEEM�Z
1100 Simonton Street
Key West Florida 33040
10145 NW 19th Street
Miami Florida 33172
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
Burke Construction Group, Inc, page 2 of 2 Printed On: 7114/ 2017 02 :15 PM
IMC
HUMM
10 • N.W. 1 • Street
■'i Florida 33172
Attn: Armando Silveira
Blanp,44inia. Bnuhnwp,
Bo,,� 2,03P
05
0 ff i c e, 910 4 4t, OjO
19,04) 29'1,4,10
Armando,
This change request is for curb extensions to raise the Roof Top Units. The roof elevations were
..............
HMPX*-WIM0E=
Kirk Nyberg
Islands Mechanical Contractor Inc
P 0 Box 2039
Middleburg, FL 32050-2039
Ph (904)406-6100
To:
Carrier Enterprise, LLC - FLA
29704 Network Place
Chicago, IL 60673-1297
Ship To: Attn: I - Bernstein Park
6751 5th Street
Stock Islands, FL 33040
rfflllllrel��
Delivery Date
IPurchase Order
Order : 0117151-0017
Date: 7/12/2017
Job: 01-17-151 KVV-HVAC Bernstein Park
Job
Cost
Code
Cat
Description
Quantity
to
Amount
including Tax
Tax
01-17-151
23-2130
M
Curb Extensions
1.00 Each
2,954,00
3,160.78
206,78
01-17-151
23-2130
M
Delivery
1.00 Each
99,00
105.93
6.93
Total: $3,266.71 $213.71
Islands Mechanical Contractor Inc
Carrier Enterprise, LLC
8691 Western Way
EQUIPMENT QUOTATION Jacksonville, FL 32256
%CE (P) 904-616-1022
(F) 904-239-5945
Attention: Quentin @ Islands Mechanical
Date: 07/12/2017
Job Name: Bernstein Park Curb Extenders
Quote Number: 7-4C30-504
We at Carrier Enterprise are pleased to quote the following equipment in accordance with attached terms and conditions.
Mark For I Qty I Model Number Description
RTU-2,4 2 CC345ACEXT14 14" curb extension for CC345
RTU-3 1 CCES36NDACEXT14 14" CURB EXTENSION FOR CCES36ND
RTU-1 1 CC812ACEXT14 14" curb extension for CC812
Total Net Sell Price excluding sales tax: $2,954
to — weeks for production.
NOTE. Some products in this quote are special order non -stock items. See special note 7 below.
EXCLUSIONS:
• Special coatings, vibration isolation, or extra fitters
• Hurricane tie downs brackets, restraints or wind load ratings
• Controls or thermostats of any kind unless specifically listed above
• In warranty labor or labor to install, assemble or mount accessories
• Any piping, refrigeration specialties, long line accessories ors ke detectors
• Electrical work, wiring, disconnects, convenience outlets, phase loss protection
• Unloading, storage, lifting or setting of equipment
• Curbs or curb adapters
FREIGHT TERMS:
Factory: Freight allowed from factory to first destination unless otherwise noted, Contact salesperson for jobsite shipment coordination costs
Carrier Florida Warehouse: Standard delivery —Add $ 99 - Timed jobsite delivery —Add $ 150
SPECIAL NOTES:
1. Above price is firm and will remain in effect for 30 days.
2. No taxes, permits, start-up, and or service are included in above proposal unless otherwise noted,
3. All orders subject to credit acceptance.
4. Compliance to local codes neither guaranteed nor implied
5. CE does not accept and will not be held liable for any flow down requirements from the owner or any higher tier contractor unless specifically agreed to
in writing.
6. Any work or material furnished at CE's expense, must have written authorization and approval from CE prior to furnishing such service or materials.
Immediately upon completion of such work, the approved price shall be invoiced for immediate processing of a credit memo and applied to your
account. Deductions from our invoices or back charges for unauthorized work or materials will not be accepted.
7. If any portion of an order for special order or configured products is canceled after order release, the buyer is subject to a cancellation charge up to
100%. All sales of non -stock items are final, returns will not be allowed (curb adapters, concentric diffusers, special order, etc)
8. Contractor to verify voltage.
9. At the point of delivery, the buyer is responsible for verifying that the product is correct as ordered (model numbers, voltage, etc.) before it is uncrated
and/or lifted into place.
We appreciate your consideration of this quotation and would like to thank you for your interest in Carrier Enterprise products and services. Should you have
any questions concerning the above quotation, please feel free to contact me personally.
Sincerely,
Louis Finklehoffe
Senior Commercial Sales Engineer
Carrier Enterprise — North Florida
Template Version: 1 7
T&C Revised. 3/28/2005 This quote is subject to attached terms and conditions Page 1 of 2
CARRIER ENTERPRISE, LLC ("CE")
TERMS AND CONDITIONS OF SALE
PAYMENT AND TAXES —Payment shall be Net 1011, prox, unless otherwise stated on invoice CE reserves the right to require cash payment or other alternative method of
payment poor to completion of work if CE determines, in its sole discretion, that Customer or Customer's assignee's financial condition at any time does not justify continuance
of the Net 101h prox payment terms In addition to the Agreement price, the Customer shall pay CE any applicable taxes or government charges that may be required in
connection with the service or material furnished under this Agreement
SHIPMENT — All shipments shall be F 0 B shipping point, freight prepaid and allowed to the job site Shipment dates quoted are approximate CE does not guarantee a
particular date for shipment or delivery
WORKING HOURS — All services performed under this Agreement including major repairs, are to be provided during CE's normal working hours unless otherwise agreed
RETURNS — No items will be accepted for return without prior written authorization Returned goods may be subject to a restocking charge Special order and non -stock
items cannot be returned
ADDITIONAL SERVICE — Services or parts requested by Customer in addition to those specified in this Agreement will be provided upon receipt of Customer's written
authorization and invoiced at CE's prevailing labor rates and parts charges Additional services or parts shall be supplied under the terms of this Agreement
EXCLUSIONS — CE is not responsible for items not normally subject to mechanical maintenance including but not limited to: duct work, casings, cabinets, fixtures, structural
supports, grillage, water piping, steam piping, drain piping, cooling swear fill, boiler tubes, boiler refractory, disconnect switches and circuit breakers CE is not responsible for
repairs, replacements, alterations, additions, adjustments, repairs by others, unscheduled calls or emergency calls, any of which may be necessitated by negligent operation,
abuse, misuse, prior improper maintenance, vandalism, obsolescence, building system design, damage due to freezing weather, chemical/electrochemical attack, corrosion,
erosion, deterioration due to unusual wear and tear, any damage related to the presence of mold, fungi, mildew, or bacteria, damage caused by power reductions or failures or
any other cause beyond CE's control CE is not responsible forthe identification, detection, abatement, encapsulating or removal of asbestos, products or materials containing
asbestos, similar hazardous substances, or mold, fungi, mildew, or bacteria. In the event that CE encounters any asbestos product or any hazardous material in the course of
performing its work, CE may suspend its work and remove its employees from the project, until such product or material, and any hazards connected with it are abated CE
shall receive an extension of time to complete its work and compensation for delays encountered as a result of such situation and its correction
CE shall not be required to perform tests, install any items of equipment or make modifications that may be recommended or directed by insurance companies, government,
state, municipal or other authority However, in the event any such recommendations occur, CE, at Its option, may submit a proposal for Customer's consideration in addition
to this Agreement CE shall not be required to repair or replace equipment that has not been properly maintained
WARRANTY — Carrier warrants that all equipment manufactured by Carrier Corporation All be free from defects in material and workmanship Carrier shall at its apron repair
of replace, F 0 B point of sale, any part determined to be defective within one (1 ) year from the date of initial operation or eighteen N 8) months from date of shipment,
whichever is earlier Carrier does not warrant products not manufactured by Carrier Corporation, but it does pass on to Customer any available manufacturer's warrarks, for
those products THIS WARRANTY IS GIVEN IN LIEU OF ALL OTHER WARRANTIES, EXPREaS IM PLjLD OR STLTU'rORY, VlICLUOING THE MPLIt_Q WARRANTIES
OF N1ERLU&NTAk& 1-tJESS _FC;RF _APART1r_ULAUL PZoREQ_L Carriers obligation to repair or replace any defective parts during the warranty period shall be
Customer's exclusive remedy Carder shall not be responsible for labor charges for removal or reinstallation of defective parts, for charges for transportation, handling and
shipping or refrigerant loss, or for repairs required as a consequence of faulty installation, misapplication, abuse, improper servicing, unauthorized alteration or improper
operation by persons other than Carrier
PROPRIETARY RIGHTS — During the term of this Agreement and in combination, with win x .rt ervicisq, OF may elect to install, attend to Customer equipment, or provide
portable devices (hardware and/or software) that shall remain the personal proprietary property of CE No devices installed, attached to real property or portable device(s)
shall become a fixture of the Customer locations Customer shall not acquire any interest, title or equity in any hardware, software, processes, and other intellectual or
proprietary rights to devices that are used in connection With providing service on Customer equipment
DELAYS — Delays caused by conditions beyond the reasonable control of either party shall not be the liability of either party to this Agreement
CUSTOMER RESPONSIBILITIES — Customer shall:
0 Provide safe and reasonable equipment access and a safe work environment
ar Permit access to Customers site, and use of building services including but not limited to: water, elevators, receiving dock facilities, electrical service and local telephone
service
Keep areas adjacent to equipment free of extraneous material, move any stock, fixtures, walls or partitions that may be necessary to perform the specified service
* Promptly notify CE of any unusual operating conditions
* Upon agreement of a timely mutual schedule, allow CE to stop and start equipment necessary to perform service
a Provide adequate water treatment
* Provide the daily routine equipment operation (if not part of this Agreement) including availability of routine equipment log readings
* Where CE's remote monitoring service is provided, provide Internet connection and access as required by CE
0 Operate the equipment properly and in accordance with instructions
0 Promptly address any issues that drive related to mold, fungi, mildew or bacteria
11 EQUIPMENT CONDITION A RECOMMENDED SERVICE — Upon the initial scheduled operating and/or initial annual stop inspection, should CE determine the need for
repairs or replacement, CE All provide Customer in writing an 'equipment condition' report including recommendations for corrections and the price for repairs in addition to
this Agreement In the event CE recommends certain services (that are not included herein or upon initial inspection) and if Customer does not elect to have such services
properly performed in a timely fashion, CE shall not be responsible for any equipment or control failures, operability or any long-term damage that may result CE at its option
All either continue to maintain equipment and/or controls to the best of its ability, without any responsibility, or remove such equipment from this Agreement, adjusting the
price accordingly
12 CUSTOMER TERMINATION — Customer shall have the right to terminate this Agreement for CE's non-performance provided CE fails to cure such non-performance within 30
days after having been given prior written notice of the non-performance Upon early termination or expiration of this Agreement, CE shall have five access to enter Customer
locations to disconnect and remove any CE personal proprietary property or devices as well as remove any and all CE owned parts, tools and personal property Additionally,
Customer agrees to pay CE for all incurred but unamortized service costs performed by CE including overheads and a reasonable profit
13 CE TERMINATION — CE reserves the right to discontinue its service any time payments have not been made as agreed or if alterations, additions or repairs are made to
equipment during the term of this Agreement by others without prior agreement between Customer and CE
14 LIMITATION OF LIABILITY — Under no circumstances shall CE be held liable for any incidental, special or consequential damages, including loss of revenue, loss of use of
equipment or facilities, or economic damages based on strict liability or negligence CIE shall be liable for damage to property, other than the equipment provided under this
Agreement, and to persons, to the extent that CE's negligent acts or omissions directly contributed to such injury or property damage CE's maximum liability for any reason
(except for personal injuries) shall consist of the refunding of all moneys paid by Customer to CE under this Agreement
15 WASTE DISPOSAL — Customer is wholly responsible for the removal and proper disposal of waste oil, refrigerant and any other material generated during the term of this
Agreement
16 CLAIMS — Any suits arising from the Performance or non-performance of this Agreement, whether based upon contract, negligence, strict liability or otherwise, shall be
brought within one (1) year from the date the claim arose
17 GOVERNMENT PROCUREMENTS — CE offers standard commercial items that may not comply with Government specifications CE does not comply with the Cost
Accounting Standards (CAS) or with the Federal Acquisition Regulations (FAR) In no event shall CE provide any Cost or Pricing Data in connection Win this Agreement or
subsequent modifications
18 SUPERSEDURE, ASSIGNMENT and MODIFICATION — This Agreement contains the complete and exclusive statement of the agreement between the parties and
supersedes all previous or contemporaneous, oral or written, statements Customer may assign this Agreement only with CE's prior written consent No modification to this
Aareament shall be binding unless in writina and sinned by both parties
Accepted By: Quote Date: 07/12/2017
Title:
Date:
*uote Number: 7-4C30-504
PO Number: Bernstein Park Roof Curbs
Job Name: Bernstein Park Curb Extenders
Template Version 1 7 Page 2 of 2
T&C Revised., 3128/2005
ELIE
ME
MIME
IMIME
MEM
EM
DIRECTPd— C119[jor. TOTALS
0- jllhT [7 -41 LABOR
sV , oAt 4Liirss 21a 221 a
MEW
()I R" T 0 -b—, Pc tors VO tA LS
M". •Date' la J.1 17
W—W.WN
. ` 1L �..�
,... .. i
f
..._ ..
i
I�.
I Ih..
.. ...
_
., tip-. � �.. ..
�1' ��
� '
wr �
i;�:•�
Change OWNER x
Order
Request ARCHITECT
CONTRACTOR x
AIA Document G710 FIELD BURKE
SUBCONTRACTOR Construction Group Inc.
PROJECT Bernstein Park CHANGE ORDER NUMBER: 025
6751 5th Street DATE: 7/17/2017
Stock Island{ Florida 33040 CONTIRRACTOR PROJECT* 1611
CONTRACTOR: Burke Construction Group, Inc.
10145 N.W. 19th Street
Dural, Florida 33172
Prime Contract Change Order #025: Supreme Paspalum Sod
TO: Monroe County Engineering FROl Burke Construction Group, Inc.
1100 Simonton Street 10145 NW 19th Street
Key West, Florida 33040 Miami Florida 33172
DATE CREATED: 7/17/2017 CREATED BY: Armando Silveira (Burke Construction Group,
Inc.)
CONTRACT STATUS: Pending - In Review REVISION: 0
DESIGNATED REVIEWER: Armando Silveira (Burke Construction REVIEWED BY -
Group, Inc.)
DUE DATE: REVIEW DATE:
INVOICED DATE: PAID DATE:
SCHEDULE IMPACT- 49 days EXECUTED: No
CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT- $29,800.00
DESCRIPTION:
Due to the rain fall in the past months, the 419 sod can no longer be harvested. We held back the delivery date for the Sod until we cleared up the
issue with the reclaimed water. Unfortunately, we had unusual amount of rain fall in June and July- The heavy rains have flooded the 419 fields and
have killed the sod. Therefore, we are recommending to go with the original Spec of Paspalum and reinstate the credit offered during bid time. We were
schedule to start installing sod on 6/12117 and we will not be able to harvest the new sod until 7/31/17. Therefore, we are requesting an additional 49
days due to this issue.
ATTACHMENTS:
Schedule Impact
[4111FLIMC]
02-936 - SPORTS FIELD SODDING
Supreme Paspalum sod upgrade
Subcontractor
Grand Total:
:M.1
Burke Construction Group, Inc. page 1 of 2 Printed On: 7/18/ 2017 11 :26 AM
Change OWNER X
Order
Request ARCHITECT
CONTRACTOR X
AM Document G710 FIELD U R KE
SUBCONTRACTOR Construction Group Inc.
The original (Contract Sum) $ 7,921,975.00
The contract sum prior to this Change Order was
The new contract sum including this Change Order will be
The Contract Time will be (increased) (decreased) (unchanged) by
The date of Substalatial Completion as of the date of this Change Order therefore is
Master Permit Issue Date: 8/18/2016 Contract Base Days:
($187,221.75)
$ 7,734,753.25
$ 29,800.00
$ 7,764,55325
49 days
for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime,
acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related
items prior to final settlement of this contract.
Affy, "mr"M=]
Burke Construction Group, Inc.
1100 Simonton Street
Key West Florida 33040
Burke Construction Group, Inc.
10145 NW 19th Street
Miami Florida 33172
SIGNATURE DATE SIGNATURE DATE
page 2 of 2 Printed On: 7/18/ 2017 11 :26 AM
I Et'P REA) GRASS
rruurx tir Y,ti wauu.Lv[+.iru.[.u.g1:k
...i �f •r.�alJi ri ral,r�ri A�['[r: i,nrrr :r:
tire.,. rrr�i.-i.:�•, ,.,,..., ..,. r. 11.. .r• �,
�i�l.,r nLrluy ..:,,r.,•, Jnl.,. �.� ii -,
r
[rrl¢v .oi . err„r.K, •. n. y �n.1t M• •.+ [
Ip yi[I�.',rVINIF
rlllrW tr+r.:r it {•r'Jn-'•':
q r..ls.r�[f.rr�_I.� •.•r
n�'mrd�uau Il � Y•) e
B it i of Ly llnKl h4v.�`uc�.M��51f 1 pl:a r: � ['{�
Sh[plxS'fa �!� -�.---
I'Vil e• nnrn[ ON 10! -
Owwor Vnun+a A.Wie.6-
VMFORMOAAMM
EO• DPW m
Hobe Smind, FL 330
,rl.ri[I rni1 rvr.••f [. 1AI •ti!,r [!e llr1,+. •1•a.+f'i..
SOUTHERN SEED C F2 IFICA' ION ASSOCIMION, INC.
[X). BOX 2619
ALIE3I.IM ALr 3683 I
Phone 334-921-7400 Fax 334- 901
i;IN;E2FI Ii;tlT NUMBER Z_ 41815
t l�. .€ss €l7is e€ ittct€tF� Ixl`3€t, t.11t4 Iu: nc rt 1 ^€ € i3 :,l eeteal ur1 ta�3�is ert€ti-
Catt€)1 s€ [r1 1r1rt1=> t';ir:
2, tic ed4Fn1 rrom Noximis Weeds
? t.,imi atactn M Gcu rEi kws
i cellily tite {lwinaliion 3 r"—'i de I : Ln.w ar€d meets tale S0111fic n rked t. urtilieation
f ssmiation. n,:. ;ta..t[ar& t�i 5 I rl•: 1 piupagated grass Certification
r+
r
:Llllh.nlrs•[U!L•:I[It'v•1n.iliti•- ��� �` 4'—+—"`
(s'Pl i, i:ietE it} E'33ftiiE:trv'Ifwts tii i:ii;:rt eit;(itii:?1";
I3Eli rt3 �"}( ?�. l)E.E4t* rely se34 ?;litj�{i:`3Fli
i�+'{�;tV.' ri; i.3iiei'i 'tV �.ri'i t5t•;.�
• _ ..' "ram: ��t 77 t �i '.s : •";y . mot,':- - y'
n`r -.... +'1Y^., ,�i.. �- 'f_. - i~ tl •f^ •..{•Y •. r-i .. rN9'{':".Siy "i4 Jri.. �':e "..1 P .,t : • f., '
wo
_ - •P.' _ 1' _ ',!•'• '+ ` fir"• +Y "• .i''•r'.•"•y: �•
�: l.7� i:.','r+; ���/ �'•_'if is
:r �,.
E. ..�yfrj�.� - ►r`r �.r-F _ i'1, 'c'i. .'i't';•' k
Ryy'�•
•�• rlfFl-►��"ri,'.�,'. ,i �- 5d'�r:L- � p�A'_ . . i' .!ti,� ;k: •-tits
,• ,fir. F.• �f-. �'•• _ � _• %' .n• .;,j•� �r�i.- o. .�. ;Y,-,r�^ ,�i� ,•. �'ri�•r7�.�,ji�i::..� •� •.
l: �_}'. •• Y.��,':i:•«.t' - •` } r, - r. .jy,. _++[•' ' "eK'r-'+,i+ r�. •?. yi,R'a;�w¢
•:.'.N'•T�'+'�"r'edh_�lpp
�- 7'• , .?,�-• ''., ! •4 ''i+sT=`�. .�•r=a� .7'r . -�t:: -y�'; . ' ..lye
=�;`ir yefr. '-Y� _ _ `*fir` �� "y. l' t ...i ti•Z��.. �:. .� ;�.';; �. .=.�'' '- •F��A y�r.�fF,^•"!. ^SL �;-.r •[- �. •1 �'.'r
.:7; :.�.' .r, , _ .'f�:�/.,i[.ti''�• y�'.i"r�F •'}.•�•'�•�.•t ,Y.��r, `�g •�� �yT� r��}'.e .�\..��� •r .:*�_=.' -
. ...��f''�rr �r�.F'F, �,: .,'Z.• ;r '�. .,�, �. `�-�;�� ';t:' k:sr!{•'•�_ cR•�:{� 'f.''���:• y4w �a.f •*'5;��:.+rs"�.
, l � . •.� •�i� . it _ - _ 4-
_ _
'j;'.
.��--.y..r-- -_- i.i-fir•.• � -
-�
-
� '- -
y�±'i��•'}:ire•-{ y-X
�:'♦
•,�.".-i�/•'
�.a^�`���• ..�'. _
-J.•'.e7A`�'n!1•+ti-1�;=.ie!.."Ad•>: ``+ii
,._. _. �'�i�:TK`'•- - r: ._ .rxf:.�.*
_
... ._ ._..
..L' ��'i� -� ',.'=?Y'1
- :.� .r=� . " � . iti•
-- 5----a - _a- �::_ s.
.,•fir -
-ti: .. ••,p:,•ar�. .-,._{ � ..
- .. '�{tar _ .i? ,,�y'•_
.. ' ... � � .. _ _ _.•'ae.�i�. .. '
;� ;..
- _ � -y' -
� J''
. _ . .. _ .. I
C' K
4 .
TWI
16
Vol
,•I.
_f •i��
_ � ,dal. y'�" - •.1/,
"� • .
lei
. -. '►'ice - !{
.. ._ ti _ �►� t•t Zz
l� N _ _ ry ! YIrL ■ .l `i ' i' a•.l •�1I • A �• - :7.• - - - - - "-
rF _ l` i � •f �' •1
11 1•i .T:, V�r �• r'•: Y.�.i^�+v L/ '��.'�:li'•'r•-1,.'l4 :� _ w•Rnrr.: _- S 4/ ? • i 1_ , f• r a/:'--'•. .: i, .. - -
:•
'l,•n� •:L-: ••a 4':ii � - � �ii:� L�r[Sv S1.. ; :L Z,�%�.. X�S:�1' -'l.k
:'1,, • _ _ �'�, is ��. . ; :� � -
. . ; - r�� yti� .,ti �- _ •-.[ of . .
!: wf c •'x~ ' d
16
' _ �1 • .. _ .• ., �#.:. .'lye -,ry.Y �4k I
.. ..- r. - -. - !.' '�ti ��. .s..a.i i, • -
' �• ; f :: F.
7W
.4 K-
k;j,
*may:-= . -.r :: ._
' _
.r,,••ii7•�:S
-. � -
. -
'��._.� •%f5 Wti .51` .'Y`�.• -_
y�.=r"...
••ry. '•'�'
_ - -
+1.� - _ •'S^_ - :i•Q' �•'.'�;R"'•ti."T'; :'ti.i'. h!�,�''j
..A�- ".-•`'•j -� g ��• gyp•
•.
^z,
jiF'�1"•Y_ w• ;SY�••- vr._
.y7S
-
�. r :{;
' � . _ + •_ ••.+"
... . 4A• ';yjRy -ti:
."t��..nf+�- :.�.
- f-e•
r -�:'`
_
i'��•d2�t.7 -.'i•_ ..r•,..r. :�•-- y3. -�`�''+...����, `+r��.. .•..- .� �:��.
.._... _ .. _ �{-�_ - � .,=.:�;_. .._.•�i�. -....ram-i:vr_, -.ar w ti��_:'�
ul
C'` � �„�. fir.• � .. ." � _ , . �_�_�� --_. _ .. -
;�2.y.r_ •ice •Ij�.. �' .:+Y' "-_ _ - ". - , ��' :: r;•: i'
Jr.; Ti
" �hWi t-*•'�i' i ��Yr .•��:S..�r.��. _ _ - .t.� .. Y� af. i.. ". � _
a.•'S •�.� � Llr . k �.1 Y.r�'yy;�''s+ �•�-+p y' = T y- �, :� • . � � • ... �w� ' ri"�a ��F'.S� � t .. ..C-=._-.
�; .�,,y�l� �'!,' .� ..rYQ! �7y.;Fv-S,{.�,�: N ~.ti �,. ..Y;•• ...'Y':�; qs`4- ti,� .}ii�.t� iti �4.i�i!
may" •* � ' _ y .�"•+y�`-0aI'j. .� �}.��_�:..�`•�'.'`•: JY;_ � 1. �'..LL .'y.,� '•�
2Zf�+�s"':M. *�•_~�...•�t•••_�'4►3:�r'L�c�At�"-�'f�l_:'rir���E�i�•�..:..d
=.�f � �,
�w � +=
-'�1
��
+'TIC: ��-.,,���y�-��y,��C
-- �� --
- -- _ . �-
�:.: - --
� : �m�_
Ir.� � '�Y
_ � �, _
fti��
'��.lf�
kT--1 F, wl t D -dk A S S ... SOUTHERN SEED CERTIFICATION ASSOCIATION, INC.
RO, BOX 20
AUBLAMAL36831
Oix,334-844-4901
Phone,)
CEKIVICATF NUMBPM 14 18 'll 5
k, tfl I Md
Kind rU--. f�• yA v rhe gras� 116% lvprcs-ca,,, has bo,(�r.
Lot Nur.,Iwt fr,)Yri Noxiom wcedIN
3. Lanitv:ool of (kniemfiOnS
MI. 14
'llu lillonmdPo pmj tj 1, tj€t,, t,€ 1 j• Soirk han Secd CurWicall(M
IN [I r,f t.nq 1111 gl I I Wilit V 9M_ &,qlkllllw'
stkipj-1 lo. I I u, 1 : V I f P, t �p 110
I lal, 4, t bw
Vidd a
umer Nome & AjjLj(QW
MM FWRIM (❑ is SSL'A I ym olwox mq'omciW
P.O. Dfawa M r'� Uo'v-
H* Soorid. FL 33475 MMMMMM=
Change OWNER x
Order
Request ARCHITECT
CONTRACTOR x
AIA Document G710 FIELD URKE
SUBCONTRACTOR CO!"IStli-LIC6011 GI'001) 111C,
PROJECT Bernstein Park CHANGE ORDER NUMBER: 026
6751 5th Street DATE: 711812017
Stock Island< Florida 33040 CONTIRRACTOR PROJECT#: 1611
CONTRACTOR: Burke Construction Group, Inc.
10145 N.W. 19th Street
Doral, Florida 33172
Prime Contract Change Order #026:
Kitchen Hood
TO:
Monroe County Engineering
FROM:
Burke Construction Group, Inc.
1100 Simonton Street
10145 NW 19th Street
Key West, Florida 33040
Miami Florida 33172
DATE CREATED:
7/ 18 /20117
CREATED BY:
Armando Silveira (Burke Construction Group,
Inc.)
CONTRACT STATUS:
Pending - In Review
REVISION:
0
DESIGNATED REVIEWER: Armando Silveira (Burke Construction
REVIEWED BY:
Group, Inc.)
DUE DATE:
REVIEW DATE:
INVOICED DATE:
PAID DATE:
SCHEDULEI MPACT:
EXECUTED:
No
CONTRACT FOR:
1:Redevelopment of Bernstein Park
TOTAL AMOUNT-
$3,243.90
DESCRIPTION:
Provide and install Kitchen Hood in Community Building Kitchen area. Cost
will be divided between owner and contractor as agreed in previous weekly
meeting see attached breakdown.
ATTACHMENTS:
Schedule Impact
Burke Construction Group, Inc. page 1 of 2 Printed On: 711912017 10:48 AM
OWNER X
ARCHITECT
CONTRACTOR X
FIELD
SUBCONTRACTOR
1,01 LJ RISE
Construction GrOLIP IHC-
11-460 - UNIT KITCHEN
11A60 - UNIT KITCHEN
11-460 - UNIT KITCHEN
15-500 - HVAC/PERMIT
Subcontractor
15-500 - HVACIPERMIT
15-500 - HVAC/PERMIT
Subcontractor
15-500 - HVACIPERMIT
Subcontractor
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum would be changed by this Change Order in the amount of
The new contract sum including this Change Order will be
The Contract Time will be (increased) (decreased) (unchanged) by
The date of Substabtial Completion as of the date of this Change Order therefore is
Master Permit Issue Date: [8/18/2016 1 Contract Base Days: 330
P-99piuiu.ric�
E
I'll, - —11.1 7JrnnTa7-nTaYKrA 5r,--a-rrip 1-777
for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime,
icceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related
items prior to final settlement of this contract.
Bill Horn (Architect)
915 Eaton Street
171-M
=311 IIIIZ'• # 10
1100 Simonton Street
Key West Florida 33040
10145 111 19th Street
Miami Florida 33172
SIGNATURE DATE SIGNATURE DATE
page 2 of 2 Printed On: 7/19/ 2017 10:48 AM
ji•
IMC
� ANDS MMMIANCAL CXONTRACIIOP
PRIEBME
10 145 N.W. I 91h Street
Doral, Flo%rida 33172
Armando,
LVI M
1-gal"No - a
ifimakyj . I . 0 , . I
3070 BI-midiing Boudevard RIO Bcox 2019
3201-� Kddehbuira �'orid,-,' 3 1 -,2068 M'eur. 3 ddl' g0
4 hcnAfA406,6100
*wwW- kMecha
Yongue-Johnnie
From: Armando Silveira <asilveira@bcgconstruction.net>
Sent Friday, July 21, 2017 8:14 AM
To: Yonque-Johnnie
Cc: Darren Whiteside, Mytnik-Ann; Knight -Cary
Subject: RE: Bernstein Change Order #9
Attachments: Capture.pdf
This work was done by Burke's site crew. The reason the change order is labeled "Subcontractor" is because Procure
ties the cost to what was originally entered in the accounting portion of Procure. The original type for Site work was
entered as "Subcontractor". If we change it to any other "type" it give us an warning that it was not part of our original
Accounting. Attached is the warning we get in the program so you can see. Since this is site work I need to label the
"type" as Subcontractor. Let me know if you have any other questions,
Armando L. Silveira
Project Manager
10145 N.W. 19th Street
Doral, Florida 33172
OFF: 305-468-6604
FAX: 305-468-6654
CELL: 305-322-7862
E-mail: 0s[Ivt-4a@LhcFconfu i rt (rn, pt:q
-----Original Message -----
From: Yongue-Johnnie -Gov.]
Sent: Friday, July 21, 2017 7:37 AM
To: Armando Silveira <.isilyeu.a
Cc: Darren Whiteside mytnik-Ann<lvl.V_1.1.iik-Aiti'iLziNtfiiitc-lrCoLiiily-rI_ Guv>;Kmght-
Cary<KmghLiCa�
Subject: FW: Bernstein Change Order #9
Armando,
Ann is asking if there is a backup proposal for the hand grading in the playground, the attached says it was done by a
subcontractor which means she wants to see their proposal for the work as was done for the rebar by bells and the
gravel by slavar. She wants the same for the saw cut the curb.
Johnnie Yongue
Project Manager
Monroe County Public Works & Engineering Division Project Management Department
Office: (305)292-4429
Cell: (305)504-4148
PLEASE NOTE: FLORIDA HAS A VERY BROAD RECORDS LAW. MOST WRITTEN COMMUNICATIONS TO OR FROM THE