3rd Change Order 09/05/2017MONROE COUNTY/FLORIDA KEYS MARATHON INTERNATIONAL AIRPORT CONTRACT CHANGE ORDER PROJECT TITLE: Marathon Airport New Storage Hangars TO CONTRACTOR: West Construction, Inc. 18 South Dixie Highway, Suite 4-5 Lake Worth, FL 33460 The Contract is changed as follows: CHANGE ORDER NO: 3 The original (Contract Sum) (Guaranteed Maximum Price).....................................................$1,798,035.00 Net change by previously authorized Change Orders............................................................. $1,340,329.00 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$3,138,364.00 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ...............$ 0.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ..... $3,138,364.00 The Contract Time will be (increased) (decreased) (unchanged) by ...................................... 28 days The date of Substantial Completion as of the date of this Change Order is .......................... August 31, 2017 e Detailed description of change order and justification: Time Extension Request - Fire Walls are taking extra time due to a special request by the Fire Inspector. West r Construction had to cut thru the roof insulation and install the drywall up to underneath the roof panel and seal with fire caulk. Proposed substantial completion date 8/31/2017 This change Order 0% of the original contract price. -*" Not valid until signed bV Owner Architect it a uca ontr r ARCHITECT: / Jacobs, I c. - Date CONTRACTOR: es ons uction nc. Date DIRECTOR OF AIRPORTS: aid raw Q Date BOARD OF COUNTY COMMISSIONERS: (SEAL) kon« Crcts%cs(- �"y Navrl�i5+roe Attest: By: Deputy Clerk Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ❑ No If Yes, explanation: • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: . • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: