Item EFKAA
Advances to date
Expenditures to date
Cudjoe Status
March 2016
(Snapshot at March 17, 2016)
Finance Status
(Since AUG 2012)
$157.2 million
$146.0 million
Advance Balance on hand $ 11.2 million
CURRENT STATUS REPORT FOR CUDJOE REGIONAL WASTEWATER PROGRAM
1. Inner Islands' Collection
System
2. Outer Islands' Collection
System
3. Advanced Wastewater
Treatment Facility
4. Public Information
5. On -Site Systems
(As of March 15, 2016)
Work continues on the master pump stations for Summerland
Key.
Action: FDEP approved Upper Sugarloaf and Cudjoe Keys
collection systems for operation. System connections being
installed and inspected on Cudjoe Key and Upper Sugarloaf
Key.
Layne has completed collection system piping on Lower
Sugarloaf, Ramrod and Little Torch. Work has been certified
and cleared for service. Collection system work on Big Pine
Key continues.
Action: Continue transmission work along US1, collection
system completions on Big Pine Key. Notices for collection
systems connections to system being mailed.
Facility now in operation. Mobilization of deep well work
complete. Shallow wells are currently in service.
Action: Complete dual zone monitoring well for deep well
system.
FKAA workshops continue. Summerland Key workshop on
March 16th.
Action: Hold Summerland workshop and prepare website
updates and conduct field meetings with residents.
r_.-
Met with EPA representatives on March 15L to discuss grant
project for on -site systems.
Action: Provide grant modification to EPA for adding on -site
systems in Key Largo and to increase project timeline. Work
on demonstration project of passive system on USFWS
federal property, Big Pine Key.