Item C21'
CM
ounty of onroe
BOARD OF COUNTY COMMISSIONERS
Mayor Heather Carruthers, District 3
Mayor Pro Tem George Neugent, District 2
TheFloridaKeys
Danny L. Kolhage, District 1
David Rice, District 4
Sylvia J. Murphy, District 5
County Commission Meeting
May 18, 2016
Agenda Item Number: C.21
Agenda Item Summary #1646
BULK ITEM: DEPARTMENT:
Yes Project Management / Facilities
TIME APPROXIMATE:STAFF CONTACT:
Johnnie Yongue (305) 292-4429
None
AGENDA ITEM WORDING:
Approval to advertise a request for proposals for repairs and
improvements to the Stock Island Fire Station HVAC system. The repair project will be funded by
the one cent infrastructure sales tax.
ITEM BACKGROUND:
Due to a mistake in the roof insulation system, condensation forms in the
fire station dorm rooms when the AC temperature is turned down by occupants. An independent
engineer analyzed the conditions and recommended installation of two de-humidifiers in the building
attic. Work includes repairs to air conditioning in other locations of the building which were not
adjusted for different uses or modified to accommodate changes in the original design. The engineer
estimates costs for repairs at $40,000.00.
PREVIOUS RELEVANT BOCC ACTION:
On October 17, 2012, the BOCC awarded the
contract for construction of the Stock Island Fire Station to Burke Construction.
CONTRACT/AGREEMENT CHANGES:
N/A
STAFF RECOMMENDATION:
Approval to advertise RFP.
DOCUMENTATION:
RFP for HVAC Repairs SIFS
FINANCIAL IMPACT:
Effective Date: May 18, 2016
Expiration Date: N/A
Total Dollar Value of Contract: Cost to advertise $1,000.00
Total Cost to County: $1,000.00
4EGOIX4K
'
Current Year Portion: $1,000.00
Budgeted:
No
Source of Funds: 314
CPI: N/A
Indirect Costs: None
Estimated Ongoing Costs Not Included in above dollar amounts: None
Revenue Producing: No If yes, amount:
Grant:
No
County Match
: 0.00
Insurance Required:
No
Additional Details:
Cost for Advertising $1,000.00
05/18/16 314-24006 · GEN GOV PROJECTS FUND 31 $1,000.00
REVIEWED BY:
Doug Sposito Completed 05/03/2016 8:31 AM
Chris Ambrosio Completed 05/03/2016 8:56 AM
Budget and Finance Completed 05/03/2016 10:38 AM
Maria Slavik Completed 05/03/2016 11:28 AM
Kathy Peters Completed 05/03/2016 11:40 AM
Board of County Commissioners Pending 05/18/2016 9:00 AM
4EGOIX4K
'E
13263)'3928=
&3%6(3*'3928='311-77-32)67
6)59)78*36463437%07*36
783'/-70%2(*-6)78%8-326)4%-67
783'/-70%2(*0
2321%2(%836=4VIFMH'SRJIVIRGI1EG(SREPH%ZI
will be held on site at Stock
(%8)1328,EQ
Island on at .
BOARD OF COUNTY COMMISSIONERS
Mayor Heather Carruthers, District 3
Mayor Pro Tem George Neugent, District 2
Danny Kolhage, District 1
David Rice, District 4
Sylvia Murphy, District 5
COUNTY ADMINISTRATOR
Roman Gastesi
Clerk of the Circuit Court Assistant County Administrator
Amy Heavilin Kevin G. Wilson P. E.
1E]
PREPARED BY:
Monroe County Project Management Department
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
SECTION 00030
NOTICE OF CALLING FOR PROPOSALS .................................................................................... 6
SECTION 00100
INSTRUCTIONS TO PROPOSERS .............................................................................................. 7
SECTION 00110
PROPOSAL FORM ................................................................................................................ 20
SECTION 00120
INSURANCE REQUIREMENTS AND FORMS ............................................................................ 29
SECTION 00163
PRE-PROPOSAL SUBSTITUTIONS .......................................................................................... 41
SECTION 00230
SITE SURVEY ........................................................................................................................ 46
SECTION 00300
SCOPE OF WORK ................................................................................................................. 47
SECTION 00350
MILESTONE SCHEDULE/LIQUIDATED DAMAGES ................................................................... 49
SECTION 00500
AGREEMENT ........................................................................................................................ 51
SECTION 00750
GENERAL CONDITIONS OF THE CONTRACT ........................................................................... 67
SECTION 00970
PROJECT SAFETY AND HEALTH PLAN .................................................................................. 101
SECTION 00980
TABLE OF CONTENTS Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
CONTRACTOR QUALITY CONTROL PLAN ............................................................................. 115
SECTION 00990
SPECIAL CONDITIONS ........................................................................................................ 120
SECTION 01010
SUMMARY OF THE WORK .................................................................................................. 121
SECTION 01015
..................................................................................... 124
SECTION 01027
APPLICATION FOR PAYMENT ............................................................................................. 125
SECTION 01030
ALTERNATES ...................................................................................................................... 135
SECTION 01040
PROJECT COORDINATION .................................................................................................. 136
SECTION 01045
CUTTING AND PATCHING ................................................................................................... 140
SECTION 01050
FIELD ENGINEERING ........................................................................................................... 144
SECTION 01200
PROJECT MEETINGS ........................................................................................................... 147
SECTION 01301
SUBMITTALS ...................................................................................................................... 150
SECTION 01310
PROGRESS SCHEDULES ...................................................................................................... 154
SECTION 01370
TABLE OF CONTENTS Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
SCHEDULE OF VALUES ....................................................................................................... 156
SECTION 01385
DAILY CONSTRUCTION REPORTS ........................................................................................ 158
SECTION 01395
REQUEST FOR INFORMATION (RFI) .................................................................................... 160
SECTION 01400
QUALITY CONTROL ............................................................................................................ 162
SECTION 01410
TESTING LABORATORY SERVICES ....................................................................................... 166
SECTION 01421
REFERENCE STANDARDS AND DEFINITIONS ....................................................................... 169
SECTION 01500
TEMPORARY FACILITIES ..................................................................................................... 175
SECTION 01520
CONSTRUCTION AIDS ........................................................................................................ 177
SECTION 01550
ACCESS ROADS AND PARKING AREAS ................................................................................ 179
SECTION 01560
TEMPORARY CONTROLS .................................................................................................... 180
SECTION 01590
FIELD OFFICES AND SHEDS ................................................................................................. 182
SECTION 01595
CONSTRUCTION CLEANING ................................................................................................ 183
SECTION 01600
TABLE OF CONTENTS Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
MATERIAL AND EQUIPMENT .............................................................................................. 185
SECTION 01630
POST-CONTRACT SUBSTITUTIONS ...................................................................................... 187
SECTION 01640
PRODUCT HANDLING ......................................................................................................... 191
SECTION 01700
CONTRACT CLOSEOUT ....................................................................................................... 193
SECTION 01710
FINAL CLEANING ................................................................................................................ 196
SECTION 01720
PROJECT RECORD DOCUMENTS ......................................................................................... 198
SECTION 01730
OPERATION AND MAINTENANCE DATA ............................................................................. 201
SECTION 01740
WARRANTIES .................................................................................................................... 204
TABLE OF CONTENTS Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
238-')3*'%00-2+*36463437%07
NOTICE OF REQUEST FOR COMPETITIVE SOLICITATIONS
238-')-7,)6)&=+-:)2that on (%8)EX8-1)EXthe Monroe County Purchasing
Office will receive and open sealed responses for the following:
.3&2%1)
HSMX8LMWSRILEWXLI[VSRKIVSSQ
RYQFIVSRMXERHMXOIITWWLS[SMRKYTMRHVEJXW3RGIHVEJXIHVIMRWIVXMRXS
GSQTPIXI6*4
Requirements for submission and the selection criteria may be requested from
DemandStar by Onvia at www.demandstar.com OR www.monroecountybids.comor call
toll-free at 1-800-711-1712. The Public Record is available at the Monroe County
Purchasing Office located at The Gato Building, 1100 Simonton Street; Room 2-213,
Key West, Florida.
All Responses must be sealed and must be submitted to the Monroe County
Purchasing Office.
4YFPMGEXMSRHEXIW
'MXM^IR(EXI
/I]RSXIV(EXI
6ITSVXIV(EXI
End of Section 00030
NOTICE OF CALLING FOR PROPOSALS 00030-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
-27869'8-32783463437)67
To be considered, Proposals must be made in accordance with these Instructions to Proposers.
%68-'0)
DEFINITIONS
1.1 Terms used in these Instructions to Proposers, which are defined in the General
Conditions, shall have the same meanings or definitions as assigned to them in the
General Conditions.
%4VSTSWEP&MHSV6IWTSRWI
1.2 is a complete and properly signed proposal to do the
Work for the sums stated therein, including any Owner Options or Alternates stipulated
therein, and submitted in accordance with the Proposal Documents. In Request for
%HHIRHE
1.3 are written or graphic instruments issued by the Owner, its agents, employees
or consultants prior to the receipt of Proposals, which modify or interpret the Proposal
Documents by additions, deletions, clarifications, or corrections.
%PPS[ERGI
1.4
Allowance, payments will be made to the vendor for the specified service or project. If
the contractor is responsible for making payments, he will be reimbursed for the
payments to the vendor via presentation of invoices in his monthly payment application.
Allowance includes labor, materials, installation, permits, etc.
%PXIVREXI4VSTSWEP
1.5 (or Alternate) is an amount stated in the Proposal to be added to or
deducted from the amount of the Base Proposal if the corresponding change in the
Work, as described in the Proposal Documents, is accepted.
%VGLMXIGX)RKMRIIV
1.6 is the Architect or Engineer hired by the County to design the
project
&EWI4VSTSWEP
1.7 is the sum stated in the Proposal for which the Proposer offers to
perform the Work described in the Proposal Documents as the base, to which may be
added or from which Work may be deleted for sums stated in Alternate Proposal or
Owner Option Proposals.
4VSTSWIV
1.8 is a person or entity who submits a Proposal.
4VSTSWEP(SGYQIRXW
1.9 include the Notice of Calling for Proposal, Instructions to
Proposers, Proposal, Pre-Proposal Substitutions, Scope of Work, Milestone Schedule
and other sample Proposal and contract forms and the proposed Contract Documents
including any addenda issued prior to receipt of Proposals. The Contract Documents
consist of this Agreement, Conditions of the Contract (General, Supplementary and
other Conditions), Drawings, Specifications, Proposal Documents, Addenda issued prior
to execution of this Agreement, together with the response to RFP and all required
insurance documentation, and Modifications issued after execution of this Agreement.
The Contract represents the entire and integrated agreement between the parties hereto
and supersedes prior negotiations, representations or agreements, either written or oral.
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
An enumeration of the Contract Documents, other than Modifications, appears in Article
9. In the event of a discrepancy between the documents, precedence shall be
determined by the order of the documents as just listed.
0SGEP&YWMRIWW
1.10 means, as specifically defined in Monroe County Code Section 2-
349(b), the vendor has a valid receipt of the business tax paid as issued by Monroe
County Tax Collector at least one year prior to the notice of request for bids or proposals
for the business to provide the goods, services or construction to be purchased, and a
physical business address located within Monroe County from which the vendor
operates or performs business on a day-to-day basis that is a substantial component of
the goods or services being offered to Monroe County. The physical business address
must be registered with the Florida Department of State as its principal place of business
for at least one year prior to the notice of request for bids or proposals. Post Office
Boxes are not verifiable and shall not be used for the purpose of establishing a physical
address.
3[RIV
1.11 is synonymous
1.12 means to comply fully with the specified or implied requirements.
1.13
used, this shall mean the purchase and complete installation, and all purchasing
requirements and procedures, as per the specified or implied requirements.
7YFFMHHIV
1.14 is a person or entity who submits a bid to a Proposer for materials or labor
for a portion of the Work.
1.15 means an amount stated in the Proposal as a price per unit of
measurement for materials or services as described in the Proposal Documents or in the
proposed contract documents. Unit prices shall apply to change orders.
%68-'0)
COPIES OF PROPOSAL DOCUMENTS
2.1 Proposers may obtain complete sets of the Proposal Documents from DemandStar by
Onvia at www.demandstar.com or www.monroecountybids.com, or call toll-free at 1-800-
711-1712.
2.2 Proposers shall use complete sets of Proposal Documents in preparing Proposals.
Neither the Owner nor Project Management, nor their agents, nor the Architect/Engineer
assumes any responsibility for errors or misinterpretations resulting from the use of
incomplete sets of Proposal Documents.
2.3 Submitted Proposals MUST include an Insurance Agent Statement and a completed
Insurance Checklist, and all forms and requirements as called for in the Request for
Proposals. Failure to include all necessary forms and licenses will result in a non-
responsive proposal.
%68-'0)
EXAMINATION OF PROPOSAL DOCUMENTS AND SITE
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
3.1 Before Submitting a Proposal:
3.1.1 Each Proposer shall thoroughly examine all the Proposal Documents.
3.1.2 Each Proposer shall visit the site to familiarize himself with local conditions that may in
%232
any manner affect the cost, progress, or performance of the Work. There is
1%2(%836=4VIFMH'SRJIVIRGI1EG(SREPH%ZI
will be held on site at Stock
(%8)1328,EQ
Island on at .
3.1.3 Ignorance on the part of the Proposer shall in no way relieve him of the
obligations and responsibilities assumed under this Proposal.
3.1.4 Should a Proposer find discrepancies, ambiguities in, or omissions from the Proposal
Documents, or should he be in doubt as to their meaning, he shall at once notify the
Owner, in writing by e-mail to Johnnie Yongue, Yongue-johnnie@monroecounty-fl.gov.
3.2 The lands upon which the Work is to be performed, right-of-ways for access thereto and
other lands designated for use by the Contractors in performing the Work are identified
in the General Requirements or Drawings.
3.3 Each Proposer shall study and carefully correlate his observations with the Proposal
Documents.
3.4 The submission of a Proposal will constitute a representation by the Proposer that he
has complied with every requirement of Article 3 and that the Proposal Documents are
sufficient in scope and detail to indicate and convey understanding of all terms and
conditions for performance of the Work.
%68-'0)
INTERPRETATION AND CORRECTION OF PROPOSAL DOCUMENTS
4.1 Proposers and Sub-proposers shall promptly notify the Director of Project Management
in writing of any ambiguity, inconsistency or error that they may discover upon
examination of the Proposal Documents or of the site and local conditions.
4.2 Proposers and Sub-proposers requiring clarification or interpretation of the Proposal
Documents shall submit their questions in writing to the Director of Project Management
no later than ten (10) business days prior to the date for receipt of Proposals (see 3.1.4).
Any answer, interpretation, correction or change of the Proposal Documents will be
accomplished by Addenda. Copies of Addenda will be made available for inspection at
DemandStar by Onvia at www.demandstar.com or www.monroecountybids.com or call
toll-free at 1-800-711-1712. Interpretations, corrections, or changes of the Proposal
Documents made in any other manner will not be binding, and Proposers shall not rely
upon such interpretations, corrections, and changes. Oral and other interpretations or
clarifications will be without legal effect
%68-'0)
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
PROPOSAL PROCEDURE
*361%2(78=0)3*463437%0
5.1.1 The Proposal shall be submitted on the forms included in Section 00110 of these
Proposal Documents with the exception of the Proposal Bond, which may be
submitted in alternate forms as described in Section 5.3.1 of these Instructions to
Proposers. Each of the forms in Section 00110 must be properly filled out,
executed, and submitted as the Proposal.
5.1.2 All blanks on the Proposal Form shall be filled in with ink or by typewriter.
5.1.3 Where so indicated on the Proposal Form, sums shall be expressed in both
words and figures, and in case of discrepancy between the two, the amount
written in words shall govern. Failure to comply shall constitute a non-responsive
proposal.
5.1.4 Any interlineation, alteration, or erasure must be initialed by the signer of the
Proposal.
5.1.5 All requested Alternates shall be proposed. If no change in the Base Proposal is
required, enter "No Change". Failure to comply shall constitute a non-responsive
proposal.
5.1.6 All requested Allowances shall be proposed. Failure to comply shall constitute a
non-responsive proposal.
5.1.7
(Monroe County or State) as part of the Proposal.
%(()2(%
5.2.1 Each Proposer shall ascertain prior to submitting his Proposal that he has
received all Addenda issued, and he shall acknowledge their receipt in his
Proposal. However, in case any Proposer fails to acknowledge receipt of such
addenda, his Proposal will nevertheless be construed as if it had been received
and acknowledged, and the submission of the Proposal will constitute
acknowledgement of receipt of the addenda. It is the responsibility of each
Proposer to verify that he has received all addenda issued before Proposals are
opened.
5.2.2 No Addenda will be issued later than five (5) business days prior to the date for
receipt of Proposals except for an Addendum withdrawing the request for
Proposals or one which includes postponement of the date for receipt of
Proposals.
5.2.3 Copies of Addenda will be made available for inspection wherever Proposal
Documents are on file for that purpose. See Article 4.2 above.
463437%07)'96-8=
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
5.3.1 Each proposal shall be accompanied by a Proposal Security in the amount equal
from a surety insurer authorized to do business in Florida as a surety or any
method permitted in §255.051, Florida Statutes and as amended (certified check,
the security is in the form of a check or draft, it shall be made payable to Monroe
County BOCC.
5.3.2 The Proposal surety constitutes a pledge by the Proposer that the Proposer will
enter into a Contract with the Owner on the terms stated in his Proposal and the
solicitation documents. Bid securities may remain in the custody of the County
OMB for up to 90 days from the bid opening date or until forfeited or released.
The bid security of the successful bidder shall be returned to the bidder after (a)
the bidder executes the contract, (b) deliveres a good and sufficient performance
bond, payment bond, and required proof if insurance as may be required in the
contract documents, and (c) commences performance of the contract. If after the
Board of County Commissioners accepts the bid to a competitive solicitation the
successful bidder refuses or is unable to execute the contract to provide the
required contract bonds or proof of insurance, or commence performance, the
County may annul the Notice of Award, and the bid security will be forfeited to,
and become the property of, the County as liquated damages for the Co
loss of bargain.
5.3.3 The proposal security of any Proposer may be retained by the County set forth in
section 5.3.2 above, or for up to 90 days from the date when all Proposals have
been rejected.
7',)(90-2+1%243;)66)59-6)1)287%2(4)61-87
5.4.1 The overall schedule for construction is shown in the Proposal Documents
"Milestone Schedule" at Section 00350.
5.4.2 The Contractor will be required to provide adequate manpower and equipment in
order to meet the requirements of the schedule.
5.4.3 Proposer shall determine all permits, impact fees, inspections, testing and survey
(and fees required by same) required by Federal, State, Municipal or Utility
bodies having jurisdiction over the project. Proposer shall include in his
proposal the cost of all such permits, impact fees, inspections, testing, and
surveys for the project site/building. The Contractor shall be required to secure
all such permits, impact fees, inspections, testing, surveys, and to provide all
installation, permitting, required for the execution of this Contract. The Countywill
assess Countybuilding permitand Countyimpactfees The Contractor shall be
responsible for any and all building permit costs or impact fees required for the
substantial completion of this project.
5.4.4 The Contractor shall be responsible to secure and pay for all testing services of
an independent testing laboratory to perform specified inspections and testing as
indicated in Technical Specification Sections and as required by the contract or
governing authorities. Contractor shall include the cost of all inspection and
testing fees in his bid proposal.
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
79&1-77-323*463437%07
5.5.1 Proposals shall be submitted to Monroe County at the designated location not
later than the time and date for receipt of Proposals indicated in the Notice of
Calling for Proposals, or any extension thereof made by Addendum. Proposals
received after the time and date for receipt of Proposals will be returned
unopened.
5.5.2 Two signed (2) originals and two (2) copies one (1) saved electronically tabbed
and indexed in Adobe Acrobat file (.PDF) format delivered on a downloadable
CD/DVD of the proposal setting forth all proposal documents (total equals five)
are to be submitted. Place the proposal security in its own separate envelope,
Both envelopes are to be inserted in one larger envelope. If the Proposal is
hand-delivered, the envelope shall be filled out as follows:
1. In the upper left hand corner, place the Proposer's name and address.
2. In the center of the envelope, put the following:
1SRVSI'SYRX]4YVGLEWMRK(ITEVXQIRX
7MQSRXSR7XVIIX6SSQ
/I];IWX*0
3. In the lower left hand corner, put the following:
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
(%8)8-1)
(%=1328,
3:00pm
If the Proposal is sent by mail or courier, the sealed envelope shall be enclosed
in a separate mailing envelope with the notation "SEALED PROPOSAL
ENCLOSED" on the face thereof, and then address the mailing envelope in the
conventional manner.
5.5.3 The Proposer shall assume full responsibility for timely delivery at the location
designated for receipt of Proposals.
5.5.4 Oral, telephonic, telegraphic, faxed, and emailed Proposals are invalid and will
not receive consideration.
13(-*-'%8-32%2(;-8,(6%;%03*463437%07
5.6.1 A Proposal may not be modified, withdrawn, or canceled by the Proposer during
the stipulated time period following the time and date designated for the receipt
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
of Proposals, except as provided in paragraph 5.7 Right to Claim Error in
PROPOSAL, and each Proposer so agrees in submitting his Proposal.
5.6.2 Prior to the time and date designated for receipt of Proposals, any Proposal
submitted may be modified by delivery to Monroe County Purchasing
Department of a complete Proposal as modified. All envelopes shall be marked
proposal.
5.6.3 Proposals may be withdrawn prior to the time and date designated for the receipt
of Proposals. Withdrawn Proposals may be resubmitted up to the time
designated for the receipt of Proposals provided that they are then fully in
conformance with these Instructions to Proposers.
5.6.4 Proposal Security shall be in an amount equal to 5% of the of the modified
proposal price. See Article 5.3.1 for description of the form of the proposal
security
5.6.5 Conditional, modified, or qualified proposals will be rejected. Proposers are to
comply with the instructions on the proposal forms, and not make any changes
thereto.
6-+,883'0%-1)6636-2463437%0
5.7.1 Each Proposer's original work papers, documents, and materials used in
preparation of the proposal shall be enclosed in an envelope and marked clearly
as to contents, must be received by Monroe County Purchasing Department no
later than 24 hours after the time and date for receipt of Proposals, or any
extension thereof made by Addendum. Proposers who fail to submit their
original work papers, documents, and materials used in the preparation of the
proposal, as provided herein, waive all rights to claim error in the Proposal.
5.7.2 Owner will review documents submitted within the designated time frame for the
5.7.3 Following review of the Proposer's claim at the election of the owner the Owner
may:
a. Allow the Proposer to withdraw the Proposal and the Owner retains the
Proposal Security.
b. Allow the Proposer to withdraw the Proposal and the Owner returns the
Proposal Security.
c. Allow the Proposer to enter into contract for the proposed Work at the
original Proposal price.
%68-'0)
CONSIDERATION OF PROPOSALS
34)2-2+3*463437%07
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
6.1.1 The properly identified Proposals received on time will be opened at the Monroe
County Purchasing Department. The public is permitted to be present.
6.1.2 Any Proposal not received by the Purchasing Department on or before the
deadline for receipt of proposals designated in the Notice of Calling for Proposals
will be returned unopened.
463437%07836)1%-234)2
6.2.1 All Proposals shall remain open and valid for ninety (90) days after the date
designated for receipt of Proposals.
6.2.2 The Owner may, at his sole discretion, release any Proposal and return the
Proposal Security before the ninety (90) days has elapsed.
%;%6(3*'3286%'8
6.3.1 The Owner reserves the right to reject any and all proposals, or any part of a
proposal. The Owner reserves the right to waive variations from the
specifications that do not render the proposal non-conforming. The Owner retains
the right to disregard non-conformities, non-responsive proposals or conditional
proposals in the best interest of the County.
6.3.2 In evaluating Proposals, the Owner shall consider the qualifications of the
proposers and whether or not the Proposals comply with the prescribed
requirements in the Proposal Documents.
6.3.3 The Owner shall have the right to accept alternates in any order or combination
and to determine the low proposer on the basis of the sum of the Base Proposal
plus Alternates selected by the Owner. The Owner reserves the right to reject
any or all Alternates in the selection process as is deemed necessary to keep the
project within budget.
6.3.4 The Owner may consider the qualifications and experience of subcontractors
and/or other entities (including those who are to furnish materials, or equipment
fabricated to a special design) proposed for each of the principal portions of the
Work as identified in the Proposal Documents. Proposers shall submit their
listing of subcontractors. A Proposed Subcontractor Listing Form supplied by the
Owner is to be completed for this purpose.
6.3.5 Where legally acceptable the Owner shall consider preference to local
businesses in making a purchase or awarding a contract who meet the
criteria for a local business as defined by Section 2-349 of the Monroe County
Code.
6.3.6 Individuals or firms which meet all the criteria in Section 2-349 of the Monroe
County Code and are a conforming and responsible proposer shall receive local
preference and shall be given an amount not to exceed two and one half percent
(2.5%) of the lowest nonlocal responsive and responsible proposer. Total
proposal price shall include the base proposal and all alternatives or options to
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
the base proposal which are part of the proposal and being recommended for
award by the appropriate authority.
6.3.7 If the Local Business subcontracts 50% or more of the goods, services or
2-349 of the Monroe County Code, an additional two and one half percent (2.5%)
preference will be given of the lowest nonlocal responsive and responsible
proposer.
6.3.8 The application of local preference may be waived upon written recommendation
by the Owner and approval by the Monroe County Board of County
Commissioners at the time of Award of Contract. Waiver of the application of the
local preference is based upon analysis of the marketplace and in consideration
of the special or unique quality of goods, services, or professional services
sought to be purchased by the Owner.
6.3.9 The Owner may conduct such investigations, as he deems necessary to assist in
the evaluation of any Proposal and to establish the responsibility, qualifications,
and financial ability of the Proposers, proposed subcontractors, and other
persons or organizations to do the Work in accordance with the Contract
Documents to the Owner's satisfaction within the prescribed time.
6.3.10 The Owner reserves the right to reject the Proposal of any Proposer who does
not pass any such evaluation to its satisfaction.
6.3.11 If the Contract is awarded, it will be awarded to the lowest, conforming
responsible, responsive Proposer, with consideration to local businesses.
6.3.12 If the Contract is to be awarded, the Owner will issue the Notice of Award to the
successful Proposer within ninety (90) days after the date of receipt of proposals.
The Owner reserves the right to return all Proposals, not make any awards, and
cancel the Project.
6.3.13 The Owner is tax exempt and reserves the right to purchase directly various
construction materials and equipment that may be a part of the Contract. If the
Owner elects to make a particular purchase, the Owner will, via a Purchase
Contract, purchase the materials and equipment, and the Contractor shall assist
the Owner in the preparation of these Purchase Contracts, including providing to
the Owner appropriate tax credits. The Contractor agrees that the amount of the
purchase and the appropriate tax credit will be the subject of a deductive change
order in recognition of the fact that the purchase and taxes were computed into
the contractors costs.
6.3.14 The contract may require a public construction bond equal to the contract cost if
deemed necessary by the Director of Project Management. The bond must be
issued by an A rated surety company doing business in the State of Florida.
)<)'98-323*'3286%'8
6.4.1 The contract shall be put in final form by Project Management and given to the
Contractor for signature. The Contractor shall sign and deliver all four originals of
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
the Contract Agreement to Project Management within ten days after receipt of a
contract from Project Management. All other Contract Documents such as
Insurance Certificates are to be provided to Project Management within fourteen
days after approval of the contract by the Board of County Commissioners. A
Notice to Proceed will be issued to the Contractor after approval of the contract
by the BOCC and upon satisfactory compliance with these provisions. In no
event shall the failure of the Contractor to provide satisfactory Insurance
Certificates within the stipulated time be cause for an extension of the contract
time. Project Management will return one fully executed copy of the Contract
Agreement to the Contractor with all other Contract Documents attached upon
receipt from the Owner.
2)<803;)78
'32*361-2+6)74327-&0)463437)6
In the event the Contractor is given Notice of Award in 6.3 above and fails to
execute and deliver all contract documents required in 6.4 above, the Owner may
exercise its right to retain the proposal bond and award the contract to the next
lowest conforming responsible responsive proposer.
%68-'0)
74)'-%00)+%06)59-6)1)287
7.1 Each Proposer, before submitting the Proposal, shall familiarize itself with all Federal,
State, and local laws, ordinances, permit fees, impact fees, rules and regulations that
may apply to the Work or that may in any manner affect the cost, progress, or
performance of the Work. Monroe County requires its buildings to conform to Florida
Green Building Coalition standards.
7.2 A person or affiliate who has been placed on the convicted vendor list following a
conviction for public entity crime may not submit a proposal on a contract to provide any
goods or services to a public entity, may not submit a proposal on a contract with a
public entity for the construction or repair of a public building or public work, may not
submit proposals on leases of real property to public entity, may not be awarded or
perform work as a contractor, supplier, subcontractor, or consultant under a contract with
any public entity, and may not transact business with any public entity in excess of the
threshold amount provided in Section 287.017, Florida Statutes for CATEGORY TWO
for a period of 36 months from the date of being placed on the convicted vendor list.
End of Section 00100
INSTRUCTIONS TO PROPOSERS 00100-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463437%0*361
The Proposal shall be submitted on the forms included in this section of the Proposal
Documents as previously instructed herein.
-XIQ(IWGVMTXMSR4EKIW
1. Proposal Form 20-21
2. Bid Bond (Proposal Security) 22
3. Non-Collusion Affidavit 23
4. Lobbying and Conflict of Interest Clause 24
5. Drug-Free Workplace Form 25
6. Local Preference Form 26
7. Public Entity Crime Statement 27
8. Subcontractor Listing Form 28
9. Insurance Requirements and Checklist 30-34
10. Workers Compensation a 35
11. General Liability 36
12. Vehicle Liability 37
13. 38-39
14. 40
Contractor License
Current Copy to Be Submitted with Proposal
Subcontractor Licenses to Be Submitted Prior to
Award of Notice to Proceed
16. In order to determine if the persons or entity submitting proposals are responsible, all
Proposals for contracts to be awarded under this section must contain the following
information:
A.
general partnership, a list of the general partners; or, if a limited liability company, a
list of its members; if a solely owned proprietorship, names(s) of owner(s). A copy of
documentation demonstrating that the entity is a legally viable entity shall be
attached.
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. A list of the officers and directors of the entity.
C. Relevant Experience: The number of years the person or entity has been operating
and, if different, the number of years it has been providing the service, goods, or
construction services called for in the proposal specifications (include a list of similar
projects).
D. The number of years the person or entity has operated under its present name and
any prior names.
E. Answers to the following questions regarding claims and suits:
a. Has the person or entity ever failed to complete work or provide the goods for
which it has contracted? (If yes, provide details of the job, including where the
job was located and the name of the owner.)
b. Are there any judgments, claims, arbitration proceeding or suits pending or
outstanding against the person, principal of the entity, or entity, or its officers,
directors, or general partners (this specifically includes any present or prior
entities in which the person, principal, entity, officer, director or general
partner of the proposing entity has been involved as a person, principal, entity,
officer, director or general partner in the last five (5) years)? (If yes, provide
details, include enough information about the judgment, claim, arbitration or
suit so that the Owner will able to obtain a copy of the judgment or claim or
locate the suit by location and case number.)
c. Has the person, principal of the entity, entity, or its officers, major
shareholders or directors within the last five (5) years, been a party to any law
suits or arbitrations with regard to a contract for services, goods or
construction services similar to those requested in the specifications with
private or public entities? This specifically includes any present or prior
entities in which the person, principal, entity, officer, director or general
partner of the proposing entity has been involved as a person, principal, entity,
officer, director or general partner in the last five (5) years. (If yes, provide
details, include enough information about the judgment, claim, arbitration or
suit so that the Owner will able to obtain a copy of the judgment or claim or
locate the suit by location and case number.)
d. Has the person, principal of the entity, or its officers, owners, partners, major
shareholders or directors, ever initiated litigation against the County or been
sued by the County in connection with a contract to provide services, goods or
construction services? This specifically includes any present or prior entities in
which the person, principal, entity, officer, director or general partner of the
proposing entity has been involved as a person, principal, entity, officer,
director or general partner. (If yes, provide details, include enough information
about the judgment, claim, arbitration or suit so that the Owner will able to
obtain a copy of the judgment or claim or locate the suit by location and case
number.)
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
e. Whether, within the last five (5) years, the Owner, an officer, general partner,
controlling shareholder or major creditor of the person or entity was an officer,
general partner, controlling shareholder or major creditor of any other entity
that failed to perform services or furnish goods similar to those sought in the
request for bids;
f. Customer references (minimum of three), including name, current address
and current telephone number;
Credit References (minimum of three), including name, current address
and current telephone number;
g. Financial statements for the prior three years. Please provide in a separate
one (1) original copy.
submit in order to prequalify for bidding or for responding to a bid for a road or
any other public works project is exempt from s. 119.07(1) and s.24(a), Art. 1
of the State Constit
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463437%0*361
463437%08313263)'3928=&3%6(3*'3928='311-77-32)67
GS496',%7-2+()4%681)28
7-132832786))8
6331
/)=;)78*036-(%
463437%0*631
The undersigned, having carefully examined the Work and reference Drawings, Specifications,
Proposal, and Addenda thereto and other Contract Documents for the construction of:
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
and having carefully examined the site where the Work is to be performed, having become
familiar with all local conditions including labor affecting the cost thereof, and having familiarized
himself with material availability, Federal, State, and Local laws, ordinances, rules and
regulations affecting performance of the Work, does hereby propose to furnish all labor,
mechanics, superintendents, tools, material, equipment, transportation services, and all
incidentals necessary to perform and complete said Work and work incidental hereto, in a
workman-like manner, in conformance with said Drawings, Specifications, and other Contract
Documents including Addenda issued thereto.
The undersigned further certifies that he has personally inspected the actual location of where
the Work is to be performed, together with the local sources of supply and that he understands
the conditions under which the Work is to be performed. The successful proposer shall assume
the risk of any and all costs and delays arising from the existence of any subsurface or other
latent physical condition which could be reasonably anticipated by reference to documentary
information provided and made available, and from inspection and examination of the site.
8LI&EWI4VSTSWEPWLEPPFIJYVRMWLIHFIPS[MR[SVHWERHRYQFIVW-JXLIVIMWER
MRGSRWMWXIRG]FIX[IIRXLIX[SXLI4VSTSWEPMR[SVHWWLEPPGSRXVSP
Dollars.
(Total Base Proposal- words)
$________________________________________________________________________
(Total Base Proposal numbers)
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
I acknowledge Alternates as follows:
2SRI
I acknowledge receipt of Addenda No.(s)
No.____Dated__________________
No.____Dated__________________
No.____Dated__________________
No.____Dated__________________
Proposer, states by his check mark in the blank beside the form and by his signature that he
has provided the following forms (located in Section 00110):
a. Proposal Form ____
b. Proposal Security (Bid Bond) ____
c. Non-Collusion Affidavit ____
d. Lobbying and Conflict of Interest Clause ____
e. Drug-Free Workplace Form ____
f. Subcontractor Listing Form ____
g. Indemnification Statement ____
h. Insurance Agents Statement (signed by agent) ____
i. Local Preference Form and requirements (if applicable) ____
In addition, Proposer states that he has in, and
'LIGOQEVOMXIQWEFSZIEWEVIQMRHIVXLEXXLI]
Monroe County Occupational License.
EVIMRGPYHIH
Mailing Address:
Phone Number:
Date: Signed:
(Name)
(Title)
Witness: (Seal)
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
&-(
463437%0
&32(
KNOW ALL MEN BY THESE PRESENTS, that we
(Here insert name and address or legal title of Contractor)
as Principal, hereinafter called the Principal, and
(Here insert full name and address or legal title of Surety)
a corporation duly organized under the laws of the State of as Surety, hereinafter called the
Surety, are held and firmly bound unto
(Here insert full name and address or legal title of Owner)
as Obligee, hereinafter called the Obligee, in the sum of Dollars ($), for the payment of which
sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs,
executors, administrators, successors and assigns, jointly and severally, firmly by these
presents.
WHEREAS, the Principal has submitted a bid for
(Here insert full name, address and description of project)
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal shall enter into a
Contract with the Obligee in accordance with the terms of such bid, and give such bond or
bonds as may be specified in the bidding or Contract Documents with good and sufficient surety
for the faithful performance of such Contract and for the prompt payment of labor and material
furnished in the prosecution thereof, or in the event of the failure of the Principal to enter such
Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not
to exceed the penalty hereof between the amount specified in said bid and such larger amount
for which the Obligee may in good faith contact with another party to perform the Work covered
by said bid, then this obligation shall be null and void, otherwise to remain in full force and
effect. Any action instituted by a claimant under this bond must be in accordance with the
notice and time limitations provisions in Section 255.05(2), Florida Statutes.
___________________________________
(Principal) (Seal)
_____________________________
(Witness)
________________________________________
(Title)
________________________________________
(Surety) (Seal)
______________________________
(Witness)
________________________________________
(Title
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
232'30097-32%**-(%:-8
I, of the city
according to law on my oath, and under penalty of perjury, depose and say that:
1. I am
of the firm of
the proposer making the Proposal for the project described in the notice for calling for proposals
for:
and that I executed the said proposal with full authority to do so;
2. The prices in this proposal have been arrived at independently without collusion, consultation,
communication or agreement for the purpose of restricting competition, as to any matter relating to
such prices with any other proposer or with any competitor;
3. Unless otherwise required by law, the prices which have been quoted in this proposal have not
been knowingly disclosed by the proposer and will not knowingly be disclosed by the proposer prior
to proposal opening, directly or indirectly, to any other proposer or to any competitor; and
4. No attempt has been made or will be made by the proposer to induce any other person, partnership
or corporation to submit, or not to submit, a proposal for the purpose of restricting competition; and
5. The statements contained in this affidavit are true and correct, and made with full knowledge that
said project.
(Signature of Proposer) (Date)
STATE OF:
COUNTY OF:
PERSONALLY APPEARED BEFORE ME, the undersigned authority,
who, after first being sworn by me, (name of individual signing) affixed his/her signature in the space provided above
on this day of , 20_____.
NOTARY PUBLIC
My commission expires:
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
03&&=-2+%2('32*0-'83*-28)6)78'0%97)
7;36278%8)1)2892()636(-2%2')23
13263)'3928=*036-(%
ETHICS CLAUSE
" "
(Company)
"... warrants that he/it has not employed, retained or otherwise had act on his/its behalf any former County
officer or employee in violation of Section 2 of Ordinance No. 010-1990 or any County officer or employee in violation
of Section 3 of Ordinance No. 010-1990. For breach or violation of this provision the County may, in its discretion,
terminate this contract without liability and may also, in its discretion, deduct from the contract or purchase price, or
otherwise recover, the full amount of any fee, commission, percentage, gift, or consideration paid to the former
County officer or employee".
(Signature)
Date:
STATE OF:
COUNTY OF:
Subscribed and sworn to (or affirmed) before me on (date)
by (name of affiant). He/She is personally known to me
or has produced as identification. (Type of
identification)
NOTARY PUBLIC
My commission expires:
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
(69+*6));36/40%')*361
The undersigned vendor in accordance with Florida Statute 287.087 hereby certifies that:
(Name of Business)
1. Publishes a statement notifying employees that the unlawful manufacture, distribution,
dispensing, possession, or use of a controlled substance is prohibited in the workplace and
specifying the actions that will be taken against employees for violations of such prohibition.
2.
policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and
employee assistance programs, and the penalties that may be imposed upon employees for
drug abuse violations.
3. Gives each employee engaged in providing the commodities or contractual services that
are under proposal a copy of the statement specified in subsection (1).
4. In the statement specified in subsection (1), notifies the employees that, as a condition
of working on the commodities or contractual services that are under proposal, the employee
will abide by the terms of the statement and will notify the employer of any conviction of, or plea
of guilty or nolo contendere to, any violation of Chapter 893 (Florida Statutes) or of any
controlled substance law of the United States or any state, for a violation occurring in the
workplace no later than five (5) days after such conviction.
5. Imposes a sanction on, or require the satisfactory participation in a drug abuse
employee who is so convicted.
6. Makes a good faith effort to continue to maintain a drug-free workplace through
implementation of this section.
As the person authorized to sign the statement, I certify that this firm complies fully with the
above requirements.
Pro
Date
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
03'%046)*)6)2')*361
A. Vendors claiming a local preference according to 3VHMRERGI, as amended by 3VHMRERGI2S
, must complete this form.
Name of Bidder/Responder______________________________ Date: ______________
1. Does the vendor have a valid receipt for the business tax paid to the Monroe County Tax Collector
dated at least one year prior to the notice of request for bids or proposals? __________ (Please furnish
copy.)
2. Does the vendor have a physical business address located within Monroe County from which the
vendor operates or performs business on a day to day basis that is a substantial component of the goods
or services being offered to Monroe County?_______________
(The physical business address must be registered as its principal place of business with the Florida
Department of State for at least one year prior to the notice of request for bid or proposal.)
List Address: ____________________________________________________________
Telephone Number: _______________________________________________________
B. Does the vendor/prime contractor intend to subcontract 50% or more of the goods, services or
construction to local businesses meeting the criteria above as to licensing and location? ____________
If yes, please provide:
1. Copy of Receipt of the business tax paid to the Monroe County Tax Collector by the subcontractor
dated at least one year prior to the notice or request for bid or proposal.
he subcontractor
operates:
(The physical business address must be registered as its principal place of business with the Florida
Department of State for at least one year prior to the notice of request for bids or proposals)
__________________________________________ Tel. Number _____________________
Address
_________________________________________ Print Name:______________________
Signature and Title of Authorized Signatory for
Bidder/Responder
STATE OF ____________________
COUNTY OF ___________________
On this _____ day of _____________________, 20_____, before me, the undersigned notary public,
personally appeared _____________________________, known to me to be the person whose name is
subscribed above or who produced ______________________as identification, and acknowledged that
he/she is the person who executed the above Local Preference Form for the purposes therein contained.
My commission expires: _________________ _____________________________
Print Name_____________________________________________________________
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
PUBLIC ENTITY CRIME STATEMENT
public entity crime may not submit a bid on a contract to provide any goods or services to a public
entity, may not submit a bid on a contract with a public entity for the construction or repair of a
public building or public work, may not submit bids on leases of real property to public entity, may
not be awarded or perform work as a contractor, supplier, subcontractor, or CONTRACTOR under a
contract with any public entity, and may not transact business with any public entity in excess of the
threshold amount provided in Section 287.017, Florida Statutes, for CATEGORY TWO for a period
I have read the above and state that neither _______________________________________
vendor list within the last 36
months.
________________________________
(Signature)
Date: ___________________________
STATE OF: _____________________
COUNTY OF: _____________________
Subscribed and sworn to (or affirmed) before me on the ______ day of _______________________,
20____, by __________________________________(name of affiant). He/She is personally known
to me or has produced _____________________________________________ (type of
identification) as identification.
My Commission Expires: ____________
____________________________________
NOTARY PUBLIC
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
79&'3286%'8360-78-2+*361
Division
Subcontractor Contact Person Ph # w/area Fax: Cell: Address
code
End of Section 00110
PROPOSAL FORM 00110-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
SECTION 00120
INSURANCE REQUIREMENTS AND FORMS
MONROE COUNTY, FLORIDA RISK MANAGEMENT POLICY AND
PROCEDURES
General Insurance
Requirements for
Construction Contractors and Subcontractors
Prior to the commencement of work governed by this contract (including the pre-staging
of personnel and material), the Contractor shall obtain, at his/her own expense, insurance
as specified in the attached schedules, which are made part of this contract. The
Contractor will ensure that the insurance obtained will extend protection to all Sub-
Contractors engaged by the Contractor. As an alternative the Contractor may require all
Subcontractors to obtain insurance consistent with the attached schedules.
The Contractor will not be permitted to commence work governed by this contract
(including pre-staging of personnel and material) until satisfactory evidence of the
required insurance has been furnished to the County as specified below. Delays in the
commencement of work, resulting from the failure of the Contractor to provide
satisfactory evidence of the required insurance, shall not extend deadlines specified in this
contract and any penalties and failure to perform assessments shall be imposed as if the
work commenced on the specified date and time, except for the Contractor's failure to
provide satisfactory evidence.
The Contractor shall maintain the required insurance throughout the entire term of this
contract and any extensions specified in any attached schedules. Failure to comply with
this provision may result in the immediate suspension of all work until the required
insurance has been reinstated or replaced. Delays in the completion of work resulting
from the failure of the Contractor to maintain the required insurance shall not extend
deadlines specified in this contract and any penalties and failure to perform assessments
shall be imposed as if the work had not been suspended, except for the Contractor's
failure to maintain the required insurance.
The Contractor will be held responsible for all deductibles and self insured retentions that
policies.
The Contractor shall provide, to the County, as satisfactory evidence of the required
insurance, either:
Certificate of
Insurance or
A Certified copy of the actual insurance policy.
The County, at its sole option, has the right to request a certified copy of any or all
INSURANCE REQUIRMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
insurance policies required by this contract.
All insurance policies must specify that they are not subject to cancellation, non-renewal,
material change, or reduction in coverage unless a minimum of thirty (30) days prior
notification is given to the County by the insurer.
The acceptance and/or approval of the Contractor's insurance shall not be construed as
relieving the Contractor from any liability or obligation assumed under this contract or
imposed by law.
The Monroe County Board of County Commissioners, its employees and officials will be
included as "Additional Insured" on all policies, except for Workers' Compensation.
In addition, the County will be named as an Additional Insured and Loss Payee on all
policies covering County-owned property.
Any deviations from these General Insurance Requirements must be requested in writing
Request for Waiver of Insurance
on the County prepared form entitled "
Requirements
" and approved by Monroe County Risk Management.
INSURANCE REQUIRMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
MONROE COUNTY, FLORIDA
INSURANCE CHECKLIST
FOR
VENDORS SUBMITTING PROPOSALS
FOR WORK
To assist in the development of your proposal, the insurance coverages marked with an "X" will
be required in the event an award is made to your firm. Please review this form with your
insurance agent and have him/her sign it in the place provided. It is also required that the bidder
sign the form and submit it with each proposal.
WORKERS' COMPENSATION
AND
EMPLOYERS' LIABILITY
X Workers' Compensation Statutory Limits
Bodily Injury by Accident/Bodily
Injury by Disease, policy
limits/Bodily Injury by Disease
each employee
WC1 X Employers Liability $100,000/$500,000/$100,000
WC2 Employers Liability $500,000/$500,000/$500,000
WC3 Employers Liability $1,000,000/$1,000,000/$1,000,000
WCUSLH US Longshoremen & $1,000,000
Harbor Workers Act
WCJA Federal Jones Act $1,000,000
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
GENERAL LIABILITY
As a minimum, the required general liability coverages will include:
Premises Operations Products and Completed Operations
Blanket Contractual Personal Injury
Required Limits:
GL1 X____
$300,000 Combined Single Limit
GL2
$500,000 Combined Single Limit
GL3
$1,000,000 Combined Single Limit
$2,000,000 Combined Single Limit
GL4
GL5 $3,000,000 Combined Single Limit
GL6 $4,000,000 Combined Single Limit
GL7 $5,000,000 Combined Single Limit
Required Endorsement:
GLLIQ Liquor Liability
GLS Security Services
All endorsements are required to have the same limits as the basic policy.
INSCKLST
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
VEHICLE LIABILITY
As a minimum, coverage should extend to liability for: Owned; Non-owned; and Hired Vehicles
Required Limits:
VL1 X $50,000 per Person: $100,000 per Occurrence
$25,000 Property Damage
or
$100,000 Combined Single Limit
(The use of VL1 should be limited to special projects that involve
Risk
Management must approve the use of this form).
VL2 $200,000 per Person; $300,000 per Occurrence
$200,000 Property Damage
or
$300,000 Combined Single Limit
VL3 $500,000 per Person; $1,000,000 per Occurrence
$100,000 Property Damage
or
$1,000,000 Combined Single Limit
VL4 $5,000,000 Combined Single Limit
MISCELLANEOUS COVERAGES
BR1 _ Builders' Limits equal to the
Risk Full Replacement Value of the completed
project.
CL1 Cyber Liability $1,000,000
MVC Motor Truck Limits equal to the maximum
Cargo value of any one shipment.
PRO1 Professional $ 300,000 per Occurrence/$ 500,000Agg.
PRO2 Liability $ 500,000 per Occurrence/$1,000,000 Agg.
PRO3 $1,000,000 per Occurrence/$2,000,000 Agg.
POL1 Pollution $ 500,000 per Occurrence/$1,000,000Agg.
POL2 Liability $1,000,000 per Occurrence/$2,000,000 Agg.
POL3 $3,000,000 per Occurrence/$6,000,000Agg.
POL4 $5,000,000 per Occurrence/$10,000,000 Agg.
ED1 Employee $ 10,000
ED2 Dishonesty $100,000
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
GK1 Garage $ 300,000 ($ 25,000 per Veh)
GK2 Keepers $ 500,000 ($100,000 per Veh)
GK3 $1,000,000 ($250,000 per Veh)
MED1 Medical $ 300,000/$ 750,000 Agg.
MED2 Professional $ 500,000/$ 1,000,000 Agg.
MED3 $1,000,000/$ 3,000,000 Agg.
MED4 $5,000,000/$10,000,000 Agg.
IF Installation Maximum value of Equipment
Floater Installed
VLP1 Hazardous $ 300,000 (Requires MCS-90)
VLP2 Cargo $ 500,000 (Requires MCS-90)
VLP3 Transporter $1,000,000 (Requires MCS-90)
BLL Bailee Liab. Maximum Value of County Propertythat
posession.
HKL1 Hangarkeepers$ 300,000
HKL2 Liability $ 500,000
HKL3 $ 1,000,000
HKL4 $ 5,000,000
AIR1 Aircraft $ 1,000,000
AIR2 Liability $ 5,000,000
AIR3 $50,000,000
AEO1 Architects Errors $ 250,000 per Occurrence/$ 500,000 Agg.
AEO2 & Omissions $ 500,000 per Occurrence/$1,000,000 Agg.
AEO3 $ 1,000,000 per Occurrence/$3,000,000 Agg.
AEO4 $ 3,000,000 per Occurrence/$5,000,000Agg.
ARP All Risk Property Full Replacement Value of Structure
EO1 Engineers Errors $ 250,000 per Occurrence/$ 500,000 Agg.
EO2 & Omissions $ 500,000 per Occurrence/$1,000,000 Agg.
EO3 $ 1,000,000 per Occurrence/$2,000,000 Agg.
EO4 $ 5,000,000 per Occurrence/$10,000,000 Agg.
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
;36/)67'314)27%8-32
-2796%2')6)59-6)1)287
*36
'3286%'87XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
&)8;))2
13263)'3928=*036-(%
%2(
CCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC
Prior to the commencement of work governed by this contract, the Contractor shall
obtain Workers' Compensation Insurance with limits sufficient to respond to the
applicable state statutes and the requirements of Florida Statute 440.
In addition, the Contractor shall obtain Employers' Liability Insurance with limits of not
less than:
$100,000 Bodily Injury by Accident
$100,000 Bodily Injury by Disease, policy limits
$100,000 Bodily Injury by Disease, each employee
Coverage shall be maintained throughout the entire term of the contract.
Coverage shall be provided by a company or companies authorized to transact
business in the state of Florida.
If the Contractor has been approved by the Florida's Department of Labor, as an
authorized self-insurer, the County shall recognize and honor the Contractor's status.
The Contractor may be required to submit a Letter of Authorization issued by the
Department of Labor and a Certificate of Insurance, providing details on the Contractor's
Excess Insurance Program.
If the Contractor participates in a self-insurance fund, a Certificate of Insurance will be
required. In addition, the Contractor may be required to submit updated financial
statements from the fund upon request from the County.
;'
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
+)2)6%00-%&-0-8=
-2796%2')6)59-6)1)287
*36
'3286%'87XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
&)8;))2
13263)'3928=*036-(%
%2(
CCCCCCCCCCCCCCCCCCCCCCCCCCCCCC
Prior to the commencement of work governed by this contract, the Contractor shall
obtain General Liability Insurance. Coverage shall be maintained throughout the life of
the contract and include, as a minimum:
Premises Operations
Products and Completed Operations
Blanket Contractual Liability
Personal Injury Liability
The minimum limits acceptable shall be:
$300,000 Combined Single Limit
An Occurrence Form policy is preferred. If coverage is provided on a Claims Made
policy, its provisions should include coverage for claims filed on or after the effective
date of this contract. In addition, the period for which claims may be reported should
extend for a minimum of twelve (12) months following the acceptance of work by the
County.
The Monroe County Board of County Commissioners shall be named as Additional
Insured on all policies issued to satisfy the above requirements.
+0
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
:),-'0)0-%&-0-8=
-2796%2')6)59-6)1)287
*36
'SRXVEGX7XSGO-WPERH*MVI7XEXMSR6ITEMVW
&)8;))2
13263)'3928=*036-(%
%2(
CCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC
Recognizing that the work governed by this contract requires the use of vehicles, the
Contractor, prior to the commencement of work, shall obtain Vehicle Liability Insurance.
Coverage shall be maintained throughout the life of the contract and include, as a
minimum, liability coverage for:
Owned, Non-Owned, and Hired Vehicles
The minimum limits acceptable shall be:
$100,000 Combined Single Limit (CSL)
If split limits are provided, the minimum limits acceptable shall be:
$50,000 per Person
$100,000 per Occurrence
$25,000 Property Damage
The Monroe County Board of County Commissioners shall be named as Additional
Insured on all policies issued to satisfy the above requirements.
:0
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
INSURANCE REQUIREMENTS
Compensation Statutory Limits
Employers Liability $100,000 Bodily Injury by Accident
$500,000
Bodily Injury by Disease Policy Limits
$100,000
Bodily Injury by Disease, each employee
General Liability, including $300,000 Combined Single Limit
Premises Operations
Products and Completed Operations
Blanket Contractual Liability
Personal Injury Liability
Vehicle Liability (Owned, non-owned, and hired vehicles) $100,000 Combined Single Limit
If split limits are preferred:
$50,000 per Person
$100,000 per Occurrence
$25,000 Property Damage
Public Construction bond may be required by the Director Of Project Management. Bond must
be issued by an A rated surety company doing business in the State of Florida.
,SPH,EVQPIWWERH-RHIQRMJMGEXMSR
. Notwithstanding any minimum insurance requirements
prescribed elsewhere in this agreement, Contractor shall defend, indemnify and hold the
officers and employees harmless from and
against (i) any claims, actions or causes of action, (ii) any litigation, administrative proceedings,
appellate proceedings, or other proceedings relating to any type of injury (including death), loss,
damage, fine, penalty or business interruption, and (iii) any costs or expenses that may be
asserted against, initiated with respect to, or sustained by, any indemnified party by reason of,
or in connection with, (A) any activity of Contractor or any of its employees, agents, contractors
or other invitees during the term of this Agreement, (B) the negligence or recklessness,
intentional wrongful misconduct, errors or other wrongful act or omission of Contractor or any of
its employees, agents, sub-contractors or other invitees, or (C) Contractor's default in respect of
any of the obligations that it undertakes under the terms of this Agreement, except to the extent
the claims, actions, causes of action, litigation, proceedings, costs or expenses arise from the
intentional or sole negligent acts or omissions of the COUNTY or any of its employees, agents,
contractors or invitees (other than Contractor). Insofar as the claims, actions, causes of action,
litigation, proceedings, costs or expenses relate to events or circumstances that occur during
the term of this Agreement, this section will survive the expiration of the term of this Agreement
or any earlier termination of this Agreement.
In the event that the completion of the project (to include the work of others) is delayed or
suspended as a result of the Contractor s failure to purchase or maintain the required insurance,
the Contractor shall indemnify the County from any and all increased expenses resulting from
such delay. Should any claims be asserted against the County by virtue of any deficiency or
ambiguity in the plans and specifications provided by the Contractor, the Contractor agrees and
warrants that the Contractor shall hold the County harmless and shall indemnify it from all
losses occurring thereby and s
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The first ten dollars ($10.00) of remuneration paid to the Contractor is for the indemnification
provided for the above.
The extent of liability is in no way limited to, reduced, or lessened by the insurance requirements
contained elsewhere within this AGREEMENT.
PROPOSER'S STATEMENT
I understand the insurance that will be mandatory if awarded the contract and will comply in full
with all the requirements. I fully accept the indemnification and hold harmless as set out on page
00110-12 of this proposal.
PROPOSER Signature
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
INSURANCE AGENT'S STATEMENT
I have reviewed the above requirements with the proposer named above. The following
deductibles apply to the corresponding policy.
POLICY DEDUCTIBLES
Liability policies are Occurrence Claims Made
Insurance Agency Signature
End of Section 00120
INSURANCE REQUIREMENTS AND FORMS 00120-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
46)463437%079&78-898-327
PART 1 - GENERAL
1.1 Document includes
A. Pre-Proposal Substitutions
1.2 PROPOSER'S OPTIONS
A. For products specified only by reference standard, select product meeting that
standard, by any manufacturer.
B. For products specified by naming several products or manufacturers, select one
of the products and manufacturers named which complies with the Technical
Specifications.
C. For Products specified by naming several products or manufacturers and stating
"or equivalent", "or equal", or "Project Management approved equivalent", or
similar wording, submit a request for substitutions, for any product or
manufacturer which is not specifically named for review and approval by Owner
and Architect.
D. For products specified by naming only one product/manufacturer, there is no
option and no substitution will be allowed.
1.3 SUBSTITUTIONS
A. Base Proposal shall be in accordance with the Contract Documents.
1. Substitutions for products may be made during the proposal process by
submitting completed substitution request form and substantiating product
data/literature a minimum of ten calendar days prior to the Proposal Date
to Project Management.
2. Project Management will consider requests utilizing this section from the
Proposer for substitution of products in place of those specified.
3. Those submitted 15 calendar days prior to Proposal Date will be included
in an addendum if acceptable.
4. Substitution requests may be submitted utilizing a facsimile machine
(FAX) if substitution request forms and substantiating data are submitted.
PRE-PROPOSAL SUBSTITUTIONS 00163-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. Submit separate request for each substitution. Support each request with:
1. Complete data substantiating compliance of proposed substitution with
requirements stated in Contract Documents:
a. Product identification, including manufacturer's name and
address.
b. Manufacturer's literature, identifying:
1) Product description.
2) Reference standards.
3) Performance and test data.
c. Samples, as applicable.
d. Name and address of similar projects on which product has been
used and date of each installation.
2. Itemized comparison of the proposed substitution with product specified,
listing significant variations.
3. Data relating to changes in construction schedule.
4. All effects of substitution on separate contracts.
5. List of changes required in other work or products.
6. Designation of required license fees or royalties.
7. Designation of availability of maintenance services, sources of
replacement materials.
C. Substitutions will not be considered for acceptance when:
1. Acceptance will require substantial revision of Contract Documents.
2. In the judgment of the Owner, the substitution does not include adequate
information necessary for a complete evaluation.
D. The Owner will determine the acceptability of any proposed substitution.
1.4 PROPOSER'S REPRESENTATION
A. In making formal request for substitution the Proposer represents that:
1. He has investigated proposed product and has determined that it is
equivalent to, or superior in all respects to that specified.
2. He will provide same warranties or bonds for substitution as for product
specified.
3. He will coordinate installation of accepted substitution into the Work, and
will make such changes as may be required for the Work to be complete
in all respects.
4. He waives claims for additional costs caused by substitution which may
subsequently become apparent.
5. Cost data is complete and includes related costs under his Contract, but
not:
a. Costs under separate contracts.
b. Architect/Engineer's costs for redesign or revision of Contract
Documents.
PRE-PROPOSAL SUBSTITUTIONS 00163-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
6. Cost data need not be submitted, if request is for inclusion in an
addendum.
1.5
A. Review requests for substitutions with reasonable promptness.
B. Issue an addendum to identify accepted substitutions.
C. Substitution requests that are not approved will be returned to the party
submitting the request.
1.6 SUBSTITUTION REQUEST FORM
A. The form is attached to this Section.
B. Substitutions will be considered only when the attached form is completed and
included with the submittal with all required back-up data.
PRE-PROPOSAL SUBSTITUTIONS 00163-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
79&78-898-32*361
TO: Project Management
PH: FAX:
We hereby submit for your consideration the following product instead of the specified item for the above project:
Drawing No. Drawing Name Spec Sec. Spec Name Paragraph Specified Item
Proposed Substitution:
Attach complete information on changes to Drawings and/or Specifications which proposed substitution will require
for its proper installation.
Submit with request necessary samples and substantiating data to prove equal quality and performance to that which
is specified. Clearly mark manufacturer's literature to indicate equality in performance.
The undersigned certifies that the function, appearance and quality are of equal performance and assumes liability for
equal performance, equal design and compatibility with adjacent materials.
Submitted By:
Signature Title
Firm
Address
City / State / Zip Code
Telephone Date
Signature shall be by person having authority to legally bind his firm to the above terms. Failure to provide legally
binding signature will result in retraction of approval.
For use by Project Management: ___ Approved __ Approved as noted ____ Not Approved
Rec'd too late Insufficient data received
By Date
PRE-PROPOSAL SUBSTITUTIONS 00163-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Fill in Blanks Below:
A. Does the substitution affect dimensions shown on Drawings?
Yes No If yes, clearly indicate changes:
B. Will the undersigned pay for changes to the building design, including engineering and detailing costs
caused by the requested substitution?
Yes No If no, fully explain:
C. What effect does substitution have on other Contracts or other trades?
D. What effect does substitution have on construction schedule?
E. Manufacturer's warranties of the proposed and specified items are:
Same Different. Explain:
F. Reason for Request:
G. Itemized comparison of specified item(s) with the proposed substitution; list significant variations:
H. Designation of maintenance services and sources: (Attach additional sheets if required.)
End of Section 00163
PRE-PROPOSAL SUBSTITUTIONS 00163-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
7-8)796:)=
A. The Plat of Survey and other survey data, are available in the Office of Project
Management for review, and are for the general information of the proposer. The data
contained was prepared by the Owner for the Architect's use for the design of the
project, and neither the Owner nor the Architect, nor Project Management make any
representation, guarantee of warranty as to the accuracy or completeness of data
indicated, expressed or implied.
B. Proposers shall visit the site; make their own investigations, assumptions and
conclusions as to the nature and extent of existing surface and overhead conditions
affecting the work. Neither the Owner nor the Architect, nor Project Management will be
responsible for additional type or extent of work required to be performed under the
Contract due to any assumptions or conclusions by the successful proposer based upon
the survey information provided.
End of Section 00230
SITE SURVEY 00230 - Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
7'34)3*;36/
+)2)6%07'34)
Provide all labor, supervision, materials, supplies, equipment, tools,
transportation, and protection for the proper execution and completion of all the
work in accordance with the Contract Documents. The Work shall include but
not be limited to that shown on the Drawings and detailed in the Technical
Specifications included in this Proposal Package.
7'34)3*;36/
The Scope of Work shall include, all work shown and listed in the Project
Drawings. The Contractor is required to provide a complete job as contemplated
by the drawings and specifications, which are a part of this bid package.
The Contractor shall furnish all labor, supervision, materials, power, tools,
equipment, supplies and any other means of construction necessary or proper for
performing and completing the Scope of Work, unless otherwise specifically
stated.
Contractor is to:
1. Provide and install complete 2 space dehumidifiers as indicated on these
plans including all supports, electric power, and condensate drain system.
2. Provide and install electrical control and power for the dehumidifiers, service
recepticles, lighting in attic for service, and new circuit breakers, conduit and
conductors as detailed on the electrical plans.
3. Provide and make accessible attic access and maintenance space in the
existing attic.
4. Pickup County Permit Submitted by owner #16102478
5. Clean up space during and after installation.
6. Coordinate access installation with fire chief and Monroe County Project
Manager.
7. Re-insulate existing supply duct work on first floor as shown.
8. Install new return air duct on first floor as shown.
9. Provide and install new door sweeps, thresholds and seals.
The Contractor shall be responsible for complying with regulations, approvals,
and permitting by the: 1SRVSI'SYRX]&YMPHMRK(ITX*MVI1EVWLEPPER]
SXLIVTIVQMXXMRKSVVIKYPEXSV]EKIRGMIWEWETTPMGEFPI
-28)283*8,)74)'-*-'%8-327
A. The intent of these specifications is to describe the materials and methods
of construction required for the performance of the work. In general, it is
intended that the drawings shall delineate the detailed extent of the work.
Drawings, specifications, and contract documents are complimentary, and
what is required by one shall be as binding as if required by all.
SCOPE OF WORK 00300-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
74)'-%0463:-7-327
The following Special Provisions are intended to clarify the scope of work, or
highlight features of the work, or modify, change, add to, or delete from the
General Scope of this Proposal Package.
1. All licenses required in order to perform the scope of work in the specified
location, shall be procured and maintained by the contractor and his
subcontractors. Contractor shall submit copies to Project Management
2. Provide, replace, and maintain any safety rails and barricades as
necessary during the process of work, or during deliveries of materials or
equipment.
3. Contractor is to review Division 1 General Requirements for additional
responsibilities required in order to perform this Work.
4. If in the event of conflicting, or overlapping requirements in any area of the
proposal documents, technical specifications, or drawings, the most
stringent condition shall be proposed and constructed. Notify Project
Management in any event, in order to not compromise the Owner's right to
make appropriate decisions.
5. Contractor shall maintain As-Built Drawings, (Record Drawings per
Section 01720), of his work progression.
6. The Contractor shall not store materials, tools or debris inside the building
without written permission. Contractor shall provide suitable storage
container, and be responsible for disposal off-site of all debris and trash.
7. The Contractor shall coordinate with representative on available
hours for Job Site access. Job site will have limited 8:00AM -5:00PM work
hours. Contractor will need to schedule work shifts typically from 8:00AM-
5:00PM weekly. Any change to agreed upon schedule must be obtained
in writing with a minimum of 72 hrs advanced notice.
8. Coordination of each days works shall be done in advance with approval
from County. All spaces interior and exterior shall be cleaned and
returned to normal each work period.
End of Section 00300
SCOPE OF WORK 00300-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
1-0)7832)7',)(90)0-59-(%8)((%1%+)7
This section contains the project milestone schedule. The contractor is required to
determine his proposed schedule to meet these milestone dates.
The Contractor is to note the following special milestone dates.
.......................................... DATE
2. Pre- ....................................... DATE
....................................... .DATE
4. BOCC Award Date ....................................... DATE
5. Notice to Proceed & Pre-Construction Meeting (Anticipated) ............................. DATE
........................................ DATE
The Contractor shall commence performance of this Contract within ten (10) calendar
days after the date of issuance to the Contractor by Owner of the Notice to Proceed.
Once commenced, Contractor shall diligently continue performance until completion of
the Project. The Contractor shall accomplish Substantial Completion of the Project
within WM\X] () calender days. Contractor shall accomplish Final Completion of the
Project within thirty (30) calendar days thereafter.
certified in writing by Project Management, the Project is at a level of completion in strict
compliance with this Contract such that the Owner or its designee can enjoy beneficial
use or occupancy and can use or operate it in all respects for its intended purpose.
Partial use or occupancy of the Project shall not result in the Project being deemed
substantially complete and such partial use or occupancy shall not be evidence of
point at which, as certified in writing by Project Management, that the Project is 100%
complete and in conformance with the Contract.
0-59-(%8)((%1%+)7
'SRHMXMSRW9RHIV;LMGL0MUYMHEXIH(EQEKIWEVI-QTSWIHThe time or times
stipulated in the contract for completion of the work of the contract or of specified
phases of the contract shall be the calendar date or dates listed in the milestone
schedule.
Liquidated damages will be based on the Substantial Completion Date for all work,
modified by all approved extensions in time as set forth by the Director of Project
MILESTONE SCHEDULE 00350-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
liquidated damages
table below shall be utilized to determine the amount of liquidated
damages.
FIRST SECOND 31ST DAY &
CONTRACT AMOUNT 15 DAYS 15 DAYS THEREAFTER
Under $50,000.00 $50.00/Day $100.00/Day $250.00/Day
$50,000.00-99,999.00 100.00/Day 200.00/Day 750.00/Day
$100,000.00-499,999.00 200.00/Day 500.00/Day 2,000.00/Day
$500,000.00 and Up 500.00/Day 1,000.00/Day 3,500.00/Day
8LI'SRXVEG
3[RIVWLEPPFIERI\XIRWMSRSJXMQISRXLI'SRXVEGX
End of Section 00350
MILESTONE SCHEDULE 00350-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
%+6))1)28
%KVIIQRX
e
RX
Between Owner and Contractor
Between Owner and ContractorBetween Owner and Contractor
Between Owner and Contractor
;LIVIXLIFEWMWSJTE]QIRXMWE78-490%8)(791
XLIFEWMWSJTE]QIRXMWE78-490%8)(791XLIFEWMWSJTE]QIRXMWE78-490%8)(791
XLIFEWMWSJTE]QIRXMWE78-490%8)(791
AGREEMENT
[VMXISYXXLIHEXI
Made as of the
[VMXISYXXLIHEXI
BETWEEN the Owner: Monroe County Board of County Commissioners
BETWEEN the Owner:Monroe County Board of County Commissioners
500 Whitehead Street
Whitehead Street
500
Key West, Florida 33040
Key West, Florida 33040
And the Contractor: CONTRACTOR
Andthe Contractor:the Contractor:CONTRACTOR
ADDRESS
ADDRESSADDRESS
ADDRESS
ADDRESS
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
For the following Project:
he followin
For tg Project:g Project:
Scope of the Work
Scope of the Work
1. 4VSNIGX3ZIVZMI[
4VSNIGX3ZIVZMI[
Contractor is to:
Contractor is to:
1. Provide and install complete 2 space dehumidifiers as indicated on these
plans including all supports, electric power, and condensate drain system.
2. Provide and install electrical control and power for the dehumidifiers, service
recepticles, lighting in attic for service, and new circuit breakers, conduit and
conductors as detailed on the electrical plans.
3. Provide and make accessible attic access and maintenance space in the
existing attic.
4. Pickup County Permit Submitted by owner #16102478
5. Clean up space during and after installation.
6. Coordinate access installation with fire chief and Monroe County Project
Manager.
7. Re-insulate existing supply duct work on first floor as shown.
8. Install new return air duct on first floor as shown.
9. Provide and install new door sweeps, thresholds and seals.
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The Contractor shall be responsible for complying with regulations, approvals,
The Contractor shall be responsible for complying with regulations, approvals, The Contractor shall be responsible for complying with regulations, approvals,
and permitting by the: 1SRVSI'SYRX]&YMPHMRK(ITX*MVI1EVWLEPPER]
1SRVSI'SYRX]&YMPHMRK(ITX*MVI1EVWLEPPER]1SRVSI'SYRX]&YMPHMRK(ITX*MVI1EVWLEPPER]
1SRVSI'SYRX]&YMPHMRK(ITX*MVI1EVWLEPPER]
SXLIVTIVQMXXMRKSVVIKYPEXSV]EKIRGMIWEWETTPMGEFPI
SXLIVTIVQMXXMRKSVVIKYPEXSV]EKIRGMIWEWETTPMGEFPISXLIVTIVQMXXMRKSVVIKYPEXSV]EKIRGMIWEWETTPMGEFPI
2. +IRIVEP4VSNIGX-RXIRXERH7GSTI
4VSNIGX-RXIRXERH7GSTI
Provide all labor, supervision, engineering, materials, supplies, equipment, tools,
Provide all labor, supervision, engineering, materials, supplies, equipment, tools, Provide all labor, supervision, engineering, materials, supplies, equipment, tools, Provide all labor,
supervision, engineering, materials, supplies, equipment, tools,
transportation, surveying, layout, and protection for the proper execution and completion
transportation, surveying, layout, and protection for the proper execution and completion transportation, surveying, layout, and protection for the proper execution and completion
of all the work in accordance with the Contract Documents. The Work shall includebut
of all the work in accordance with the Contract Documents. The Work shall includeof all the work in accordance with the Contract Documents. The Work shall include
not be limited to that shown on the Drawings and detailed in the Technical
not be limited to that shown on the Drawings and detailed in the Technical not be limited to that shown on the Drawings and detailed in the Technical
Specifications if any included in this Contract.
Specifications if any included in this Contract.
Specifications if any included in this Contract.
3. +IRIVEP6IUYMVIQIRXW
+IRIVEP6IUYMVIQIRXW+IRIVEP6IUYMVIQIRXW
A. Construction work times shall be limited to: 8:00 am to 5:00 pm Mon-Fri
Construction work times shall be limited Construction work times shall be limited
B. Contractor needs to be aware of weather and location and plan accordingly.
B.Contractor needs to be aware of weather and location and plan accordingly.aware of weather and location and plan accordingly.
Contractor needs to be
C. Contractor needs to be aware of the facility, its vendors and staff with unusual
C.Contractor needs to be aware Contractor needs to be aware of the facility, its vendors
schedules and plan accordingly. Coordination of each days works shall be done
schedules and plan accordingly. Coordination of each days works shall be done schedules and plan accordingly. Coordination of each days works shall be done
in advance with approval from County. All spaces interior and exterior shall be
in advance with approval from County. All sin advance with approval from County. All s
cleaned and returned to normal work period/ day.
cleaned and returned to normal cleaned and returned to normal
D. The Scope of Work shall include, but not be limited to, all work shown and listed
The Scope of Work shall include, but not be limited to, all work shown and listed The Scope of Work shall include, but not be limited to, all work shown and listed
The Scope of Work shall include, but not be limited to, all work shown and listed
in the Project Drawings. The Contractor is required to provide a complete job as
in the Project Drawings. The Contractor is required to provide a complete job as
contemplated by the drawings and specifications, which are a part of this bid
plated by the drawings and specifications, which are a part of this bid
contem
package. The Contractor shall furnish all labor, supervision, materials, power,
package. The Contractor shall furnish all labor, supervision, materials, power,
tools, equipment, supplies and any other means of construction necessary or
proper for performing and completing the Scope of Work, unless otherwise
specifically stated.
E. SPECIAL PROVISIONS
The following Special Provisions are intended to clarify the scope of work, or
highlight features of the work, or modify, change, add to, or delete from the General
Scope of this Proposal Package.
1. All licenses required in order to perform the scope of work in the specified
location, shall be procured and maintained by the contractor and his
subcontractors. Contractor shall submit copies to Project Management
all accompany proposal.
2. Provide, replace, and maintain any safety rails and barricades as
necessary during the process of work, or during deliveries of materials or
equipment.
3. Contractor is to review Division 1 General Requirements for additional
responsibilities required in order to perform this Work.
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
4. If in the event of conflicting, or overlapping requirements in any area of the
If in the event of conflicting, or overlapping requirements in any area of the If in the event of conflicting, or overlapping requirements in any area of the
proposal documents, technical specifications, or drawings, the most
proposal documents, technical specifications, or drawings, the proposal documents, technical specifications, or drawings, the
most
stringent condition shall be proposed and constructed. Notify Project
. Notify Project
stringent condition shall be proposed and constrstringent condition shall be proposed and constructed
Management in any event, in order to not compromise the Owner's right to
Management in any event, in order to not compromise the Owner's right to Management in any event, in order to not compromise the Owner's right to Management in any event, in order to
not compromise the Owner's right to
make appropriate decisions.
5. Contractor shall maintain As-Built Drawings, (Record Drawings per
Contractor shall maintain , (Record Drawings per , (Record Drawings per
Built Drawings
As
Section 01720), of his work progression.
Section 01720), of his work progression. Section 01720), of his work progression.
6. The Contractor shall not store materials, tools or debris inside the building
shall not store materials, tools or debrisnot store materials, tools or debris
The Contractor
with out written permission. Contractor shall provide suitable storage
with out written permission. Contractor shall provide suitable storage with out written permission. Contractor shall provide suitable storage
container, and be responsible for disposal off-site of all debris and trash.
container, and be responsible for disposal offcontainer, and be responsible for disposal offsite of all debris and trash.
-
7. The Contractor shall coordinate with representative on available
The Contractor shall coordinate with The Contractor shall coordinate with
hours for Job Site access. Job site will have limited 8:00 AM -5:00PM
hours for Job Site
Job sitewill have
access.
work hours. Contractor will need to schedule work shifts typically from
work hours. Contractor will need to schedule work shifts typically from work hours. Contractor will need to schedule work shifts typically from
8:00 AM- 5:00PM weekly. Any change to agreed upon schedule must be
AM5:00PM weekly. Any change to agreed upon schedule must be PM weekly. Any change to agreed upon schedule must be
-
obtained in writing with a minimum of 72 hrs advanced notice.
obtainedin writing with a minimum of 72 hrs advanced notice.in writing with a minimum of 72 hrs advanced notice.
8. Coordination of each days works shall be done in advance with approval
Coordination of each days works shall be done in advance with approval
Coordination of each days works shall be done in advance with approval
from County. All spaces interior and exterior shall be cleaned and
from County. All spaces interior and exterior shall be cleaned and from County. All spaces interior and exterior shall be cleaned and
returned to normal each work period.
returned to normreturned to norm
al
%68-'0)
8LI'SRXVEGX(SGYQIRXW
'SRXVEGX(SGYQIRXW
The Contract Documents consist of this Agreement, Conditions of the Contract (General,
Supplementary and other Conditions), Drawings, Specifications, Proposal Documents, Addenda
issued prior to execution of this Agreement, together with the response to RFP and all required
insurance documentation, and Modifications issued after execution of this Agreement. The
Contract represents the entire and integrated agreement between the parties hereto and
supersedes prior negotiations, representations or agreements, either written or oral. An
enumeration of the Contract Documents, other than Modifications, appears in Article 9. In the
event of a discrepancy between the documents, precedence shall be determined by the order of
the documents as just listed.
%68-'0)
8LI;SVOSJXLMW'SRXVEGX
The Contractor shall execute the entire Work described in the Contract Documents, except to
the extent specifically indicated in the Contract Documents to be the responsibility of others, or
as follows
CCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC
%68-'0)
(EXISJ'SQQIRGIQIRXERH7YFWXERXMEP'SQTPIXMSR
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
3.1 The date of commencement is the date to be fixed in a notice to proceed issued by the
The date of commencement is the date to be fixed in a notice to proceed issued by the The date of commencement is the date to be fixed in a notice to proceed issued by the
Owner.
WM\X]
The Contractor shall achieve Substantial Completion of the entire Work not later than
Substantial Completion of the entire Work not later thanSubstantial Completion of the entire Work not later thanWM\X]
calendar days after the date of commencement or issuance of a Notice to Proceed. The time or
calendar days after the date of commencement or issuance of a Notice to Proceed. calendar days after the date of commencement or issuance of a Notice to Proceed.
The time or
times stipulated in the contract for completion of the work of the contract or of specified phases
stipulated in the contract for completionof the work of the contract or of specified phases of the work of the contract or of specified phases
of the contract shall be the calendar date or dates listed in the milestone schedule.
of the contract shall be the calendar date or dates listed in the milestone schedule.of the contract shall be the calendar date or dates listed in the milestone schedule.
of the contract shall be the calendar date or dates listed in the milestone schedule.
Liquidated damages will be based on the Substantial Completion Date for all work, modified by
Liquidated damages will be based on the Substantial Completion Date for all work, modified by Liquidated damages will be based on the Substantial Completion Date for all work, modified
by Liquidated damages will be based on the Substantial Completion Date for all work, modified by
all approved extensions in time as set forth by
in time as set forth by
of approval on the Certificate of Substantial Completion. The liquidated damages table below
of approval on the Certificate of Substantial Completion. The liquidated damages table below of approval on the Certificate of Substantial Completion. The liquidated damages table
below
shall be utilized to determine the amount of liquidated damages.
shall be utilized to determine the amount of liquidated damages.shall be utilized to determine the amount of liquidated damages.
FIRST SECOND 31ST DAY &
FIRSTSECONDSECOND
CONTRACT AMOUNT 15 DAYS 15 DAYS THEREAFTER
CONTRACT AMOUNT15 DAYS15 DAYS
Under $50,000.00 $50.00/Day $100.00/Day $250.00/Day
Under $50,000.00$50.00/Day$100.00/Day
$50,000.00-99,999.00 100.00/Day 200.00/Day 750.00/Day
99,999.00100.00/Day
$100,000.00-499,999.00 200.00/Day 500.00/Day 2,000.00/Day
200.00/Day
499,999.00
200.00/Day
$500,000.00 and Up 500.00/Day 1,000.00/Day 3,500.00/Day
$500,000.00 and Up
500.00/Day500.00/Day
$500,000.00 and Up
3[RIVWLEPPFIERI\XIRWMSRSJXMQISRXLI'SRXVEGX
3[RIVWLEPPFIERI\XIRWMSRSJXMQISRXLI'SRXVEGX3[RIVWLEPPFIERI\XIRWMSRSJXMQISRXLI'SRXVEGX3[RIVWLEPPFIERI\XIRWMSRSJXMQISRXLI'SRXVEGX
%68-'0)
%68-'0)
'SRXVEGX7YQ
'SRXVEGX7YQ
4.1
the Contract the Contract Sum of
the Contract the Contract Sum of
______________________________________________________________________/100
______________________________________________________________________/
Dollars ($__________), subject to additions and deductions as provided in the Contract
Documents.
4.2 The Contract Sum is based upon the following alternates, if any, which are described in
the Contract Documents and are hereby accepted by the Owner:
(State the numbers or other identification of accepted alternates. If decisions on other
rnates. If decisions on other
alternates are to be made by the Owner subsequent to the execution of this Agreement. Attach
alternates are to be made by the Owner subsequent to the execution of this Agreement. Attach
a schedule of such other alternates showing the amount for each and the date until which that
a schedule of such other alternates showing the amount for each and the date until which that
amount is valid.)
%PXIVREXI
No Alternates Specified
4.3 Unit prices, if any, are as follows:
%68-'0)
%68-'0)
4VSKVIWW4E]QIRXW
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
5.1 Based upon Applications for Payment submitted by the Contractor to the Director of
Project Management, and upon approval for payment issued by the Director of Project
Management and Architect, the Owner shall make progress payments on account of the
Contract Sum to the contractor as provided below and elsewhere in the Contract Documents.
5.2 The period covered by each Application for payment shall be one calendar month ending
on the last day of the month, or as follows:
5.3 Payment will be made by the Owner in accordance with the Florida Local Government
Prompt Payment Act, section 218.735, Florida Statutes.
5.4 Each Application for Payment shall be based upon the Schedule of Values submitted by
the Contractor in accordance with the Contract Documents. The Schedule of Values shall
allocate the entire Contract Sum among the various portions of the Work and be prepared in
such form and supported by such data to substantiate its accuracy as the Director of Project
Management may require. This schedule, unless objected to by the Director of Project
Management
5.5 Applications for Payment shall indicate the percentage of completion of each portion of
the Work as of the end of the period covered by the Application for Payment.
5.6 Subject to the provisions of the Contract Documents, the amount of each progress
payment shall be computed as follows:
5.6.1 Take that portion of the Contract Sum properly allocable to completed Work as
determined by multiplying the percentage completion of each portion of the Work by the share
of the total Contract Sum allocated to that portion of the Work in the Schedule of Values, less
retainage of Ten Percent 10%. Pending final determination of cost to the owner of changes in
the Work, amounts not in dispute may be included in Applications for Payment. The amount of
credit to be allowed by the Contractor to the Owner for a deletion or change which results in a
net decrease in the Contract Sum shall be the net cost to the Owner, less Overhead, Profit and
Documented Costs incurred prior to the change Request, as indicated in the corresponding line
item in the Approved Schedule of Values for that line item as confirmed by the Director of
item in the Approved Schedule of Values for that line item as confirmed by the D
Project Management. When both additions and credits covering related Work or substitutions
When both additions and credits covering related Work or substitutions
are involved in a change the allowance for overhead and profit shall be figured on the basis of
all be figured on the basis of
net increase, if any, with respect to that change.
5.6.2 Add that portion of the Contract Sum properly allocable to materials and equipment
Add that portion of the Contract Sum properly allocable to materials and equipment
delivered and suitably stored at the site for subsequent incorporation in the completed
delivered and suitably stored at the site for subsequent incorporation in the comple
construction (or, if approved in advance by the Owner, suitably stored off the site at a location
construction (or, if approved in advance by the Owner, suitably stored off the site at a location
construction (or, if approved in advance by the Owner, suitably stored off the site at a location
agreed upon in writing), less retainage;
5.6.3 Subtract the aggregate of previous payments made by the Owner; and
Subtract the aggregate of previous payments made by the Owner; and
Subtract the aggregate of previous payments made by the Owner; and
5.6.4 Subtract amounts, if any, for which the Director of Project Management has withheld or
Director of Project ManagementDirector of Project Management
which the has withheld or has withheld or
nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
for Payment as provided in Paragraph 9.5 of the General for Payment as provided in Paragraph 9.5 of the General C
onditions.onditions.
AGREEMENT 00500-Page of
00500
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
5.7 Retainage of 10% will be withheld in accordance with section 218.735 (8(b), Florida
Statutes.
5.8 Reduction or limitation of retainage, if any, shall be as follows:
discretion of and upon the approval of the Director of Project Management.
%68-'0)
*MREP4E]QIRX
Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the
Owner to the Contractor when (1) the Contract has been fully performed by the Contractor
ponsibility to correct nonconforming Work as provided in
Subparagraph 12.2.2 of the General Conditions and to satisfy other requirements, if any, which
necessarily survive final payment, and (2) a final approval for payment has been issued by the
Director of Project Management. Such final payment shall be made by the Owner not more
than 20 days after the issuance of the final approval for payment. The following documents
(samples in section 1027) are required for Final Payment:
(1) Application and Certificate for Payment
(2) Continuation Sheet
(3) Certificate of Substantial Completion
(4)
(5)
(6) Final Release of Lien
(7) Contractor shall provide two (2) hard copies in tabulated divided binders and
one (1) saved electronically tabbed and indexed in Adobe Acrobat file (.PDF)
format delivered on a downloadable CD/DVD of all the following but not limited
to:
A. Project Record Documents (As Built Documents).
B. Operating and maintenance data, instructions to the Owner's personnel.
B. Operating and maintenance data, instructions to the Owner's personnel.
C. Warranties, bond and guarantees.
D. Keys and keying schedule.
E. Spare parts and maintenance materials.
E. Spare parts and maintenance materials.
F. Electronic copies of approved submittals
ies of approved submittalsies of approved submittals
G. Evidence of payment and final release of liens and consent of surety to final
Evidence of payment and final release of liens and consent of surety to final Evidence of payment and final release of liens and consent of surety to final Evidence of payment and final
release of liens and consent of surety to final
release (includes final release from all utilities and utility companies).
release (includes final release from all utilities and utility companies).release (includes final release from all utilities and utility companies).
release (includes final release from all utilities and utility companies).
%68-'0)
%68-'0)
1MWGIPPERISYW4VSZMWMSRW
1MWGIPPERISYW4VSZMWMSRW
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7.1 Where reference is made in this Agreement to a provision of the General Conditions or
another Contract Document, the reference refers to that provision as amended or supplemented
by other provisions of the Contract Documents.
7.2 Payment shall be made according to the Florida Local Government Prompt Payment Act
and Monroe County Code.
7.3 Temporary facilities and services: As described in Article 34 of the General Conditions
7.4
upon an annual appropriation by the Board of County Commissioners.
7.5 A person or affiliate who has been placed on the convicted vendor list following a
conviction for public entity crime may not submit a bid on a contract to provide any goods or
services to a public entity, may not submit a proposal on a contract with a public entity for the
construction or repair of a public building or public work, may not submit proposals on leases of
real property to public entity, may not be awarded or perform work as contractor, supplier,
subcontractor, or consultant under a contract with any public entity, and may not transact
business with any public entity in excess of the threshold amount provided in Section 287.017,
for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted
vendor list.
7.6 The following items are included in this contract:
a) Contractor shall maintain all books, records, and documents directly pertinent to
performance under this Agreement in accordance with generally accepted accounting principles
consistently applied. Each party to this Agreement or their authorized representatives shall
have reasonable and timely access to such records of each other party to this Agreement for
public records purposes during the term of the Agreement and for four years following the
termination of this Agreement. If an auditor employed by the County or Clerk determines that
monies paid to Contractor pursuant to this Agreement were spent for purposes not authorized
by this Agreement, the Contractor shall repay the monies together with interest calculated
pursuant to Sec. 55.03, FS, running from the date the monies were paid to Contractor.
b) Governing Law, Venue, Interpretation, Costs, and Fees: This Agreement shall be
Governing Law, Venue, Interpretation, Costs, and Fees: This Agreement shall be
governed by and construed in accordance with the laws of the State of Florida applicable to
governed by and construed in accordance with the laws of the State of Florida applicable to
contracts made and to be performed entirely in the State. In the event that any cause of action
In the event that any cause of action
or administrative proceeding is instituted for the enforcement or interpretation of this Agreement,
or administrative proceeding is instituted for the enforcement or interpretation of this Agreement,
the County and Contractor agree that venue shall lie in the appropriate court or before the
lie in the appropriate court or before the
appropriate administrative body in Monroe County, Florida. The Parties waive their rights to trial
The Parties waive their rights to trial
by jury. The County and Contractor agree that, in the event of conflicting interpretations of the
by jury. The County and Contractor agree that, in the event of conflicting interpretations of the
terms or a term of this Agreement by or between any of them the issue shall be submitted to
shall be submitted to
terms or a term of this Agreement by or between any of them the issue
mediation prior to the institution of any other administrative or legal proceeding, pursuant to
mediation prior to the institution of any other administrative or legal proceeding, pursuant to mediation prior to the institution of any other administrative or legal proceeding, pursuant
to
Section XVI of this agreement.
c) Severability. If any term, covenant, condition or provision of this Agreement (or the
Severability. If any term, covenant, condition or provision of this Agreement (or the Severability. If any term, covenant, condition or provision of this Agreement (or the Severability.
If any term, covenant, condition or provision of this Agreement (or the
application thereof to any circumstance or person) shall be declared invalid or unenforceable to
thereof to any circumstance or person) shall be declared invalid or unenforceable to thereof to any circumstance or person) shall be declared invalid or unenforceable to thereof to any
circumstance or person) shall be declared invalid or unenforceable to
any extent by a court of competent jurisdiction, the remaining terms, covenants, conditions and
any extent by a court of competent jurisdiction, the remaining terms, covenants, conditions and any extent by a court of competent jurisdiction, the remaining terms, covenants, conditions
and
provisions of this Agreement, shall not be affected thereby; and each remaining term, covenant,
provisions of this Agreement, shall not be affected thereby; and each remaiprovisions of this Agreement, shall not be affected thereby; and each remai
ning term, covenant,
provisions of this Agreement, shall not be affected thereby; and each remai
condition and provision of this Agreement shall be valid and shall be enforceable to the fullest
condition and provision of this Agreement shall be valid and shall be enforceable to the fullest condition and provision of this Agreement shall be valid and shall be enforceable to
the fullest condition and provision of this Agreement shall be valid and shall be enforceable to the fullest
extent permitted by law unless the enforcement of the remaining terms, covenants, conditions
extent permitted by law unless the enforcement of the remaining terms, covenants, conditions extent permitted by law unless the enforcement of the remaining terms, covenants, conditions
extent permitted by law unless the enforcement of the remaining terms, covenants, conditions
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
and provisions of this Agreement would prevent the accomplishment of the original intent of this
Agreement. The County and Contractor agree to reform the Agreement to replace any stricken
provision with a valid provision that comes as close as possible to the intent of the stricken
provision.
d) Contractor agree that in the event any
cause of action or administrative proceeding is initiated or defended by any party relative to the
enforcement or interpretation of this Agreement, the prevailing party shall be entitled to
-prevailing party, and
e) Binding Effect. The terms, covenants, conditions, and provisions of this Agreement
shall bind and inure to the benefit of the County and Contractor and their respective legal
representatives, successors, and assigns.
f) Authority. Each party represents and warrants to the other that the execution,
delivery and performance of this Agreement have been duly authorized by all necessary County
and corporate action, as required by law. Each party agrees that it has had ample opportunity to
submit this Contract to legal counsel of its choice and enters into this agreement freely,
voluntarily and with advise of counsel.
g) Claims for Federal or State Aid. Contractor and County agree that each shall be, and
is, empowered to apply for, seek, and obtain federal and state funds to further the purpose of
this Agreement; provided that all applications, requests, grant proposals, and funding
solicitations shall be approved by each party prior to submission.
h) Adjudication of Disputes or Disagreements. County and Contractor agree that all
disputes and disagreements shall be attempted to be resolved by meet and confer sessions
between representatives of each of the parties. If the issue or issues are still not resolved to the
satisfaction of the parties, then any party shall have the right to seek such relief or remedy as
may be provided by this Agreement or by Florida law. This Agreement is not subject to
arbitration.
i) Cooperation. In the event any administrative or legal proceeding is instituted against
either party relating to the formation, execution, performance, or breach of this Agreement,
County and Contractor agree to participate, to the extent required by the other party, in all
proceedings, hearings, processes, meetings, and other activities related to the substance of this
Agreement or provision of the services under this Agreement. County and Contractor
nder this Agreement. County and
specifically agree that no party to this Agreement shall be required to enter into any arbitration
specifically agree that no party to this Agreement shall be required to enter into any arbitration
proceedings related to this Agreement.
j) Nondiscrimination. County and Contractor agree that there will be no discrimination
agree that there will be no discrimination
against any person, and it is expressly understood that upon a determination by a court of
against any person, and it is expressly understood that upon a determination by a court of
competent jurisdiction that discrimination has occurred, this Agreement automatically terminates
competent jurisdiction that discrimination has occurred, this Agreement automatically terminates
without any further action on the part of any party, effective the date of the court order. County
, effective the date of the court order. County , effective the date of the court order. County
or Contractor agree to comply with all Federal and Florida statutes, and all local ordinances, as
agree to comply with all Federal and Florida statutes, and all local ordinances, as agree to comply with all Federal and Florida statutes, and all local ordinances, as
applicable, relating to nondiscrimination. These include but are not limited to: 1) Title VI of the
applicable, relating to nondiscrimination. These include but are not limited to: 1) Title VI of the applicable, relating to nondiscrimination. These include but are not limited to:
1) Title VI of the
Civil Rights Act of 1964 (PL 88-352) which prohibits discrimination on the basis of race, color or
352) which prohibits discrimination on the basis of race, color or 352) which prohibits discrimination on the basis of race, color or
352) which prohibits discrimination on the basis of race, color or
national origin; 2) Title IX of the Education Amendment of 1972, as amended (20 USC ss. 1681-
national origin; 2) Title IX of the Education Amendment of 1972, as amended (20 USC ss. f 1972, as amended (20 USC ss.
1681
f 1972, as amended (20 USC ss.
1683, and 1685-1686), which prohibits discrimination on the basis of sex; 3) Section 504 of the
1686), which prohibits discrimination on the basis of se1686), which prohibits discrimination on the basis of sex; 3) Section 504 of the x; 3) Section 504 of the
Rehabilitation Act of 1973, as amended (20 USC s. 794), which prohibits discrimination on the
Rehabilitation Act of 1973, as amended (20 USC s. 794), which prohibits discrimination on the Rehabilitation Act of 1973, as amended (20 USC s. 794), which prohibits discrimination on
the
AGREEMENT 00500-Page of
00500
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
basis of handicaps; 4) The Age Discrimination Act of 1975, as amended (42 USC ss. 6101-
6107) which prohibits discrimination on the basis of age; 5) The Drug Abuse Office and
Treatment Act of 1972 (PL 92-255), as amended, relating to nondiscrimination on the basis of
drug abuse; 6) The Comprehensive Alcohol Abuse and Alcoholism Prevention, Treatment and
Rehabilitation Act of 1970 (PL 91-616), as amended, relating to nondiscrimination on the basis
of alcohol abuse or alcoholism; 7) The Public Health Service Act of 1912, ss. 523 and 527 (42
USC ss. 690dd-3 and 290ee-3), as amended, relating to confidentiality of alcohol and drug
abuse patient records; 8) Title VIII of the Civil Rights Act of 1968 (42 USC s. et seq.), as
amended, relating to nondiscrimination in the sale, rental or financing of housing; 9) The
Americans with Disabilities Act of 1990 (42 USC s. 1201 Note), as maybe amended from time to
time, relating to nondiscrimination on the basis of disability; 10) Any other nondiscrimination
provisions in any Federal or state statutes which may apply to the parties to, or the subject
matter of, this Agreement.
k) Covenant of No Interest. County and Contractor covenant that neither presently has
any interest, and shall not acquire any interest, which would conflict in any manner or degree
with its performance under this Agreement, and that only interest of each is to perform and
receive benefits as recited in this Agreement.
l) Code of Ethics. County agrees that officers and employees of the County recognize
and will be required to comply with the standards of conduct for public officers and employees
as delineated in Section 112.313, Florida Statutes, regarding, but not limited to, solicitation or
public position, conflicting employment or contractual relationship; and disclosure or use of
certain information.
m) No Solicitation/Payment. The County and Contractor warrant that, in respect to
itself, it has neither employed nor retained any company or person, other than a bona fide
employee working solely for it, to solicit or secure this Agreement and that it has not paid or
agreed to pay any person, company, corporation, individual, or firm, other than a bona fide
employee working solely for it, any fee, commission, percentage, gift, or other consideration
contingent upon or resulting from the award or making of this Agreement. For the breach or
violation of the provision, the Contractor agrees that the County shall have the right to terminate
this Agreement without liability and, at its discretion, to offset from monies owed, or otherwise
recover, the full amount of such fee, commission, percentage, gift, or consideration.
n) Public Access. The County and Contractor shall allow and permit reasonable access
to, and inspection of, all documents, papers, letters or other materials in its possession or under
its control subject to the provisions of Chapter 119, Florida Statutes, and made or received by
the County and Contractor in conjunction with this Agreement; and the County shall have the
right to unilaterally cancel this Agreement upon violation of this provision by Contractor.
Contractor is required to:
(1) Keep and maintain public records that ordinarily and necessarily would be required
by the public agency in order to perform the service.
(2) Provide the public with access to public records on the same terms and conditions
that the public agency would provide the records and at a cost that does not exceed the
cost provided in this chapter or as otherwise provided by law.
(3) Ensure that public records that are exempt or confidential and exempt from public
records disclosure requirements are not disclosed except as authorized by law.
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
(4) Meet all requirements for retaining public records and transfer, at no cost, to the
for retaining public records and transfer, at no cost, to the for retaining public records and transfer, at no cost, to the for retaining public records and transfer, at no cost, to
the
public agency all public records in possession of the contractor upon termination of the
public agency all public records in possession of the contractor upon termination of the public agency all public records in possession of the contractor upon termination of the
public agency all public records in possession of the contractor upon termination of the
contract and destroy any duplicate public records that are exempt or confidential and
contract and destroy any duplicate public records that are exempt or confidential and contract and destroy any duplicate public records that are exempt or confidential and contract and
destroy any duplicate public records that are exempt or confidential and
exempt from public records disclosure requirements. All records stored electronically
records disclosure requirements. All records stored electronically records disclosure requirements. All records stored electronically records disclosure requirements. All records stored
electronically
must be provided to the public agency in a format that is compatible with the information
must be provided to the public agency in a format that is compatible with the information must be provided to the public agency in a format that is compatible with the information must
be provided to the public agency in a format that is compatible with the information
technology systems of the public agency.
technology systems of the public agency.technology systems of the public agency.
o) Non-Waiver of Immunity. Notwithstanding the provisions of Sec. 768.28, Florida
Waiver of Immunity. Notwithstanding Waiver of Immunity. Notwithstanding
the provis
Statutes, the participation of the Contractor and the County in this Agreement and the
Statutes, the participation of the Cand the and the County
ontractor
acquisition of any commercial liability insurance coverage, self-insurance coverage, or local
acquisition of any commercial liability insurance coverage, selfacquisition of any commercial liability insurance coverage, selfacquisition of any commercial liability insurance coverage,
self
government liability insurance pool coverage shall not be deemed a waiver of immunity to the
hall not be deemed a waiver of immunity to the
government liability insurance pool coverage sgovernment liability insurance pool coverage s
extent of liability coverage, nor shall any contract entered into by the County be required to
extent of liability coverage, nor shall any contract entered into by the County be required to extent of liability coverage, nor shall any contract entered into by the County be required
to
contain any provision for waiver.
contain any provision for waiver.contain any provision for waiver.
p) Privileges and Immunities. All of the privileges and immunities from liability,
Privileges and Immunities. All of the privileges and immunities from liabPrivileges and Immunities. All of the privileges and immunities from liab
compensation, and other benefits which apply to the activity of officers, agents, or employees of
compensation, and other benefits which apply to the activity of officers, agents, or employees of compensation, and other benefits which apply to the activity of officers, agents, or
employees of
any public agents or employees of the County, when performing their respective functions under
any public agents or employees of the County, when performingany public agents or employees of the County, when performing
this Agreement within the territorial limits of the County shall apply to the same degree and
this Agreement within the territorial limits of the County shall apply to the same degree and this Agreement within the territorial limits of the County shall apply to the same degree
and
extent to the performance of such functions and duties of such officers, agents, volunteers, or
extent to the performance of such functions and duties of such officers, agents, volunteers, or extent to the performance of such functions and duties of such officers, agents, volunteers,
or
employees outside the territorial limits of the County.
employees outside the territoriaemployees outside the territoria
q) Legal Obligations and Responsibilities: Non-Delegation of Constitutional or Statutory
q)
Legal Obligations and Responsibilities: Non
Duties. This Agreement is not intended to, nor shall it be construed as, relieving any
Duties. This Agreement is not intended to, nor shall it be construed as, relieving any
participating entity from any obligation or responsibility imposed upon the entity by law except to
participating entity from any obligation or r
the extent of actual and timely performance thereof by any participating entity, in which case the
performance may be offered in satisfaction of the obligation or responsibility. Further, this
Agreement is not intended to, nor shall it be construed as, authorizing the delegation of the
constitutional or statutory duties of the County, except to the extent permitted by the Florida
constitution, state statute, and case law.
r) Non-Reliance by Non-Parties. No person or entity shall be entitled to rely upon the
terms, or any of them, of this Agreement to enforce or attempt to enforce any third-party claim or
entitlement to or benefit of any service or program contemplated hereunder, and the County and
the Contractor agree that neither the County nor the Contractor or any agent, officer, or
employee of either shall have the authority to inform, counsel, or otherwise indicate that any
particular individual or group of individuals, entity or entities, have entitlements or benefits under
this Agreement separate and apart, inferior to, or superior to the community in general or for the
purposes contemplated in this Agreement.
s) Attestations. Contractor agrees to execute such documents as the County may
reasonably require, to include a Public Entity Crime Statement, an Ethics Statement, and a
Drug-Free Workplace Statement.
t) No Personal Liability. No covenant or agreement contained herein shall be deemed
to be a covenant or agreement of any member, officer, agent or employee of Monroe County in
his or her individual capacity, and no member, officer, agent or employee of Monroe County
shall be liable personally on this Agreement or be subject to any personal liability or
accountability by reason of the execution of this Agreement.
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
u) Execution in Counterparts. This Agreement may be executed in any number of
Execution in Counterparts. This Agreement may be executed in any number of Execution in Counterparts. This Agreement may be executed in any number of Execution in Counterparts. This
Agreement may be executed in any number of
counterparts, each of which shall be regarded as an original, all of which taken together shall
counterparts, each of which shall be regarded as an original, all of which taken together shall counterparts, each of which shall be regarded as an original, all of which taken together
shall
constitute one and the same instrument and any of the parties hereto may execute this
constitute one and the same instrument and any of the parties hereto may execute thiconstitute one and the same instrument and any of the parties hereto may execute thiconstitute one
and the same instrument and any of the parties hereto may execute thi
Agreement by signing any such counterpart.
counterpart.
v) Hold Harmless and Indemnification. Notwithstanding any minimum insurance
and Indemnificationand IndemnificationNotwithstanding any minimum insurance
Hold Harmless
requirements prescribed elsewhere in this agreement, Contractor shall defend, indemnify and
requirements prescribed elsewhere in this agreement, Contractor shall defend, indemnify and requirements prescribed elsewhere in this agreement, Contractor shall defend, indemnify and
and appointed officers and employees harmless
and appointed officers and employees harmless and appointed officers and employees harmless
from and against (i) any claims, actions or causes of action, (ii) any litigation, administrative
from and against (i) any claims, actions or causes of action, (ii) any litigation, administrative from and against (i) any claims, actions or causes of action, (ii) any litigation, administrative
proceedings, appellate proceedings, or other proceedings relating to any type of injury
proceedings, appellate proceedings, or other proceedings relating to any type of injury proceedings, appellate proceedings, or other proceedings relating to any type of injury
proceedings, appellate proceedings, or other proceedings relating to any type of injury
(including death), loss, damage, fine, penalty or business interruption, and (iii) any costs or
(including death), loss,damage, fine, penalty or business interruption, and (iii) any costs or
expenses that may be asserted against, initiated with respect to, or sustained by, any
expenses that may be asserted against, initiated with respect to, or sustained by, any expenses that may be asserted against, initiated with respect to, or sustained by, any
indemnified party by reason of, or in connection with, (A) any activity of Contractor or any of its
indemnified party by reason of, or in connection with, (A) any activity of Contractor or any of iindemnified party by reason of, or in connection with, (A) any activity of Contractor
or any of i
employees, agents, contractors or other invitees during the term of this Agreement, (B) the
employees, agents, contractors or other invitees during the term of this Agreement, (B) the employees, agents, contractors or other invitees during the term of this Agreement, (B)
the
negligence or recklessness, intentional wrongful misconduct, errors or other wrongful act or
negligence or recklessness, intentional wrongful misconduct, errors or other wrongful act or negligence or recklessness, intentional wrongful misconduct, errors or other wrongful act
or negligence or recklessness, intentional wrongful misconduct, errors or other wrongful act or
omission of Contractor or any of its employees, agents, sub-contractors or other invitees, or (C)
omissionof Contractor or any of its employees, agents, subof Contractor or any of its employees, agents, sub
Contractor's default in respect of any of the obligations that it undertakes under the terms of this
Contractor's default in respect of any of the obligations that it undertakes under the terms of this Contractor's default in respect of any of the obligations that it undertakes under
the terms of this
Agreement, except to the extent the claims, actions, causes of action, litigation, proceedings,
Agreement, except to the extent the claims, actions, causes of action, litigation, proceedings,
Agreement, except to the extent the claims, actions, causes of action, litigation, proceedings,
costs or expenses arise from the intentional or sole negligent acts or omissions of the COUNTY
costs or expenses arise fromcosts or expenses arise from
or any of its employees, agents, contractors or invitees (other than Contractor). Insofar as the
or any of its employees, agents, contractors or invitees (other than Contractor). Insofar as the or any of its employees, agents, contractors or invitees (other than Contractor). Insofar
as the
claims, actions, causes of action, litigation, proceedings, costs or expenses relate to events or
claims, actions, causes of action, litigation, proceedings, costs or expenses relate to eveclaims, actions, causes of action, litigation, proceedings, costs or expenses relate to eve
circumstances that occur during the term of this Agreement, this section will survive the
circumstances that occur during the term of this Agreement, this section will survive the circumstances that occur during the term of this Agreement, this section will survive the
expiration of the term of this Agreement or any earlier termination of this Agreement.
expiration of the term of this Agreement or any earlier termination of this Agreement.
In the event that the completion of the project (to include the work of others) is delayed or
In the event that the completion of the project (to include the work of others) is delayed or
suspended as a result of the Contractor s failure to purchase or maintain the required insurance,
the Contractor shall indemnify the County from any and all increased expenses resulting from
such delay. Should any claims be asserted against the County by virtue of any deficiency or
ambiguity in the plans and specifications provided by the Contractor, the Contractor agrees and
warrants that the Contractor shall hold the County harmless and shall indemnify it from all
The first ten dollars ($10.00) of remuneration paid to the Contractor is for the indemnification
provided for the above.
w) Section Headings. Section headings have been inserted in this Agreement as a
matter of convenience of reference only, and it is agreed that such section headings are not a
part of this Agreement and will not be used in the interpretation of any provision of this
Agreement.
x) Disadvantaged Business Enterprise (DBE) Policy and Obligation. It is the policy of
participate in the performance of contracts financed in whole or in part with County funds under
this agreement. The DBE requirements of applicable federal and state laws and regulations
opportunity to participate in the performance of the Agreement. In this regard, all recipients and
contractors shall take all necessary and reasonable steps in accordance with applicable federal
nity to compete and
perform contracts. The County and Contractor and subcontractors shall not discriminate on the
basis of race, color, national origin or sex in award and performance of contracts, entered
pursuant to this Agreement.
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
y) Agreements with Subcontractors. In the event that the Contractor subcontracts any or
Subcontractors. In the event that the Contractor subcontracts any or Subcontractors. In the event that the Contractor subcontracts any or
all of the work in this project to any third party, the Contractor specifically agrees to identify the
all of the work in this project to any third party, the Contractor specifically agrees to identifall of the work in this project to any third party, the Contractor specifically agrees
to identif
all of the work in this project to any third party, the Contractor specifically agrees to identif
COUNTY as an additional insured on all insurance policies required by the County. In addition,
as an additional insured on all insurance policies required by the County. In addition, as an additional insured on all insurance policies required by the County. In addition, as an
additional insured on all insurance policies required by the County. In addition,
the Contractor specifically agrees that all agreements or contracts of any nature with his
the Contractor specifically agrees that all agreements or contracts of any nature with his the Contractor specifically agrees that all agreements or contracts of any nature with his
the Contractor specifically agrees that all agreements or contracts of any nature with his
subcontractors shall include the COUNTY as additional insured.
hall include the COUNTYas additional as additional
insured
z) Florida Green Building Coalition Standards. Monroe County requires its buildings to
Green Building Coalition Standards. Monroe County requires its buildings to Green Building Coalition Standards. Monroe County requires its buildings to
conform to Florida Green Building Coalition standards.
conform to Florida Green Building Coalition standards.conform to Florida Green Building Coalition standards.
Special Conditions, if any are detailed in Section 00990 of the Project Manual for this Project.
Special Conditions, if any are detailed in Section 0Special Conditions, if any are detailed in Section 0
0990
%68-'0)
%68-'0)
8IVQMREXMSRSV7YWTIRWMSR
8IVQMREXMSRSV7YWTIRWMSR
8IVQMREXMSR
8.1 The Contract may be terminated by the Owner as provided in Article 14 of the General
8.1The Contract may be terminated by the Owner as provided in Article 14 of the General
Conditions.
Conditions.
%68-'0)
%68-'0)
)RYQIVEXMSRSJ'SRXVEGX(SGYQIRXW
)RYQIVEXMSRSJ'SRXVEGX(SGYQIRXW)RYQIVEXMSRSJ'SRXVEGX(SGYQIRXW
9.1 The Contract Documents, except for Modifications issued after execution of this
The Contract Documents, except for Modifications issued after execution of this
9.1
Agreement, are enumerated as follows: (Insert information here).
are enumerated as follows:
Agreement,
a) Drawings: Cover, E-0.1, E-1.1, M-0.1, M-1.0
b) Project Manual; Request for Proposals Dated May 2016,
Aprilaire Model 1870 Dehumidifier Sepcification Sheet
DRD1 junction box Spec Sheet
Aprilaire Model 1870 Dehumidifier Installation manual
9.1.1 The Agreement is this executed Standard Form of Agreement Between Owner and
Contractor.
9.1.2 The General Conditions are the General Conditions of the Contract for Construction.
The General Conditions are the General Conditions of the Contract for Construction.
9.1.3 The Supplementary and other Conditions of the Contract are those contained in the
The Supplementary and other Conditions of the Contract are those
contained in the
Project Manual: Request for Proposals Dated May 2016,
9.1.4 The Addenda, if any, are as follows:
Number Date Page
Page
9.1.5 The Alternates, if any, are as follows:
2S%PXIVREXIW
)2(%08)62%8)7
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
This Agreement is entered into as of the day and year first written above and is executed in at
least four original copies of which one is to be delivered to the Contractor.
&%0%2')3*4%+)-28)28-32%00=0)*8&0%2/
7-+2%896)4%+)83*3003;
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Execution by the Contractor must be by a person with authority to bind the entity.
7-+2%896)3*8,)4)6732)<)'98-2+8,)(3'91)281978&)238%6->)(%2(
;-82)77)(&=%238,)63**-')63*8,))28-8=
&3%6(3*'3928='311-77-32)67
(SEAL)
3*13263)'3928=*036-(%
Attest: Amy Heavilin, Clerk
By: By:
Deputy Clerk Mayor/Chairman
Date
'3286%'836
(SEAL)
Attest:
By: By:
Print Name: Print Name:
Title: Title:
Date: Date:
And:
By:
Print Name:
Title:
Dare:
78%8)3**036-(%
'3928=3*
On this day of , 20 , before me ,the undersigned notary public, personally
appeared , known to me to be the person whose name is subscribed
above or who produced as identification, and acknowledged that he/she is the
person who executed the above contract with Monroe County for Stock Island Fire Station HVAC
Repairs for the purposes therein contained.
Notary Public
Print Name
My commission expires: _________________ Seal
End of Section 00500
AGREEMENT 00500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
GENERAL REQUIREMENTS
;LIVI4VSNIGX1EREKIQIRXMW2SXE'SRWXVYGXSV
Section 00750 General Conditions
Section 00970 Project Safety and Health Plan
Section 00980 Contractor Quality Control Plan
Section 00990 Special Conditions
Section 01010 Summary of Work
Section 01015
Section 01027 Application for Payment
Section 01030 Alternates
Section 01040 Project Coordination
Section 01045 Cutting and Patching
Section 01050 Field Engineering
Section 01200 Project Meetings
Section 01301 Submittals
Section 01310 Progress Schedules
Section 01370 Schedule of Values
Section 01385 Daily Construction Reports
Section 01395 Request for Information (RFI)
Section 01400 Quality Control
Section 01410 Testing Laboratory Services
Section 01421 Reference Standards and Definitions
Section 01500 Temporary Facilities
Section 01520 Construction Aids
Section 01550 Access Roads and Parking Areas
Section 01560 Temporary Controls
Section 01590 Field Offices and Sheds
Section 01595 Construction Cleaning
Section 01600 Material and Equipment
Section 01630 Post-Proposal Substitutions
Section 01640 Product Handling
Section 01700 Contract Closeout
Section 01710 Final Cleaning
Section 01720 Project Record Documents
Section 01730 Operation and Maintenance Data
Section 01740 Warranties
GENERAL REQUIREMENTS Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7IGXMSR
General Conditions of the Contract for Construction
;LIVI4VSNIGX1EREKIQIRXMW2SXE'SRWXVYGXSV
8EFPISJ%VXMGPIW
1. General Provisions
2. Owner
3. Contractor
4. Administration of the Contract
5. Subcontractors
6. Construction by Owner or By Other Contractors
7. Changes in the Work
8. Time
9. Payments and Completion
10. Protection of Persons and Property
11. Insurance and Bonds
12. Uncovering and Correction of Work
13. Miscellaneous Provisions
14. Termination or Suspension of the Contract
GENERAL REQUIREMENTS Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
+)2)6%0'32(-8-3273*8,)'3286%'8
+)2)6%0463:-7-327
&EWMG(IJMRMXMSRW
1.1
8LI'SRXVEGX(SGYQIRXW
1.1.1 : The Contract Documents consist of the Agreement
between Owner and Contractor, Conditions of the Contract (General, Supplementary and other
Conditions), Drawings, Specifications, addenda issued prior to execution of the Contract,
Owners proposal documents, other documents listed in the Agreement and Modifications issued
proposal and supporting documentation. A
Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change
Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work
issued by Project Management.
8LI'SRXVEGX
1.1.2 The Contract represents the entire and integrated agreement between
the parties hereto and supersedes prior negotiations, representations or agreements, either
written or oral. The Contract may be amended or modified only by a Modification. The Contract
Documents shall not be construed to create a contractual relationship of any kind (1) between
the Architect and Contractor, (2) between Project Management and Contractor, (3) between the
Architect and Project Management, (4) between the Owner and a Subcontractor or (5) between
any persons or entities other than the Owner and Contractor. The Owner shall, however, be
entitled to enforce the obligations under the Contract intended to facilitate performance of the
duties of Project Management and Architect.
8LI;SVO
1.1.3 required by the
Contract Documents, whether completed or partially completed, and includes all other labor,
materials, equipment and services provided or to be provided by the Contractor to fulfill the
whole or a part of the Project.
8LI4VSNIGX
1.1.4 The Project is the total construction of which the Work performed under
the Contract Documents may be the whole or a part and which may include construction by
es including persons or entities under separate
contracts not administered by Project Management.
8LI(VE[MRKW
1.1.5 The Drawings are the graphic and pictorial portions of the Contract
Documents, wherever located and whenever issued, showing the design, location and
dimensions of the Work, generally including plans, elevations, sections, details, schedules and
diagrams.
8LI7TIGMJMGEXMSRW
1.1.6 The Specifications are that portion of the Contract Documents
consisting of the written requirements for materials, equipment, construction systems, standards
and workmanship for the Work, and performance of related services.
8LI4VSNIGX1ERYEP
1.1.7 The Project Manual is the volume usually assembled for the Work
which may include the proposal requirements, sample forms, Conditions of the Contract and
Specifications.
)\IGYXMSR'SVVIPEXMSRERH-RXIRX
1.2.2 Execution of the Contract by the Contractor is a representation that the Contractor has
visited the site, become familiar with local conditions under which the Work is to be performed
and correlated personal observations with requirements of the Contract Documents.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1.2.3 The intent of the Contract Document is to include all items necessary for the proper
execution and completion of the Work by the contractor. The Contract Documents are
complementary, and what is required by one shall be as binding as if required by all;
performance by the Contractor shall be required only to the extent consistent with the Contract
Documents and reasonably inferable from them as being necessary to produce the intended
results.
1.2.4 Organization of the Specifications into divisions, sections and articles, and arrangement
of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in
establishing the extent of Work to be performed by any trade.
1.2.5 Unless otherwise stated in the Contract Documents, words which have well-known
technical or construction industry meanings are used in the Contract Documents in accordance
with such recognized meanings.
1.2.6 Where on any of the drawings a portion of the Work is drawn out and the remainder is
indicated in outline, the parts drawn out shall also apply to all other like portions of the Work.
XLIV(SGYQIRXW
1.3.1 The Drawing, Specifications and other documents prepared by the Architect are
is described. The Contractor may retain one contract record set. Neither the Contractor nor
any Subcontractor, Sub-subcontractor or material or equipment supplier shall own or claim a
copyright in the Drawings, Specifications and other documents prepared by the Architect. All
s record set, shall be returned or suitably accounted for to
Project Management, on request, upon completion of the Work. The Drawings, Specifications
and other documents prepared by the Architect, and copies thereof furnished to the Contractor,
are for use solely with respect to the Project. They are not to be used by the Contractor or any
Subcontractor, Sub-subcontractor or material or equipment suppliers unless they are granted a
limited license to use and reproduce applicable portions of the Drawings, Specifications and
other documents prepared by the Architect appropriate to and for use in the execution of their
Work under the Contract Documents. All copies made under this license shall bear the
statutory copyright notice, if any, shown on the Drawings, Specifications and other documents
prepared by the Architect. Submittal or distribution to meet official regulatory requirements or
for other purposes in connection with this Project is not to be construed as publication in
derogation of copyright or other reserved rights
1.3.2 Unless otherwise provided in the Contract Documents, the Contractor will be furnished,
two (2) original sealed copies and one (1) electronic copy of Drawings, Specifications and the
Project Manual free of charge for the execution of the Work. Additional copies may be obtained
from Project Management at a fee of $5.00 per page for full size drawings (.25 per page for
'ETMXEPM^EXMSR
1.4.1 Terms capitalized in these General Conditions include those which are (1) specifically
defined, (2) the titles of numbered articles and identified references to Paragraphs,
Subparagraphs and Clauses in the document or (3) the titles of other documents published by
the American Institute of Architects.
-RXIVTVIXEXMSR
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1.5.1 In the interest of brevity the Contract Documents frequently omit modifying words such
absent from one statement and appears in another is not intended to affect the interpretation of
either statement.
3;2)6
(IJMRMXMSR
2.1.1
authorized representative.
-RJSVQEXMSRERH7IVZMGIW6IUYMVIHSJXLI3[RIV
2.2.2 The owner shall furnish initial site surveys describing physical characteristics, legal
limitations and utility locations for the site of the Project, and a legal description of the site.
2.2.3 For existing facilities the Owner shall secure and pay for necessary approvals,
easements, assessments and charges, required for construction, use or occupancy of
permanent structures or for permanent changes in existing facilities except for permits and fees
which are the responsibility of the Contractor under the Contract Documents. It is the
(s) for the project.
2.2.4 by the Owner with
reasonable promptness to avoid delay in orderly progress of the Work.
2.2.5 Unless otherwise provided in the Contract Documents, the Contractor will be furnished
two (2) original sealed copies and one (1) electronic copy of Drawings, Specifications and the
Project Manual free of charge for the execution of the Work as provided in Subparagraph 1.3.2.
2.2.6 The Owner shall forward all communications to the Contractor through Project
Management and may contemporaneously provide the same communications to the Architect.
2.2.7 The foregoing are in addition to other duties and responsibilities of the Owner
enumerated herein and especially those in respect to Article 6 (Construction by Owner or by
Other Contractors), Article 9 (Payments and Completion) and Article 11 (Insurance and Bonds).
2.3.1 If the Contractor fails to correct Work which is not in accordance with the requirements of
the contract Documents as required by Paragraph 12.2 or persistently fails to carry out Work in
accordance with the Contract Documents, the Owner, by written order signed personally or by
an agent specifically so empowered by the Owner, may order the Contractor to stop the Work,
or any portion thereof, until the cause for such order has been eliminated; however, the right of
the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this
right for the benefit of the Contractor or any other person or entity.
2.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the
Contract Documents and fails within a three-day period after receipt of written notice from the
Owner to commence and continue correction of such default or neglect with diligence and
promptness, the Owner may after such three-day period give the Contractor a second written
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
notice to correct such deficiencies within a three-day period. If the Contractor within such
second three-day period after receipt of such second notice fails to commence and continue to
correct any deficiencies, the Owner may, without prejudice to other remedies the Owner may
have, correct such deficiencies. In such case an appropriate Change Order shall be issued
deducting from payments then or thereafter due the Contractor the cost of correcting such
deficiencies, including compensation for another contractor or subcontractor or Project
expenses made necessary by such default, neglect or failure. If payments then, or thereafter,
due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the
difference to the Owner. In the event of clean-up issues, Owner has right to provide a minimum
of 24 hours notice. In the event of safety issues determined to be of a serious nature, as
determined by Project Management, notice will be given, and contractor is required to rectify
deficiency immediately.
'3286%'836
(IJMRMXMSR
3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred
3.1.2
under Conditions of the Contract that are administered by Project Management, and that are
identical or substantially similar to these Conditions.
6IZMI[SJ'SRXVEGX(SGYQIRXWERH*MIPH'SRHMXMSRWF]'SRXVEGXSV
3.2.1 The Contractor shall carefully study and compare the Contract Documents with each
other and with information furnished by the Owner pursuant to Subparagraph 2.2.2 and shall at
once report to Project Management and Architect errors, inconsistencies or omissions
discovered. The Contractor shall not be liable to the Owner, Project Management or Architect
for damage resulting from errors, inconsistencies or omissions in the Contract Documents
unless the Contractor recognized such error, inconsistency or omission and knowingly failed to
report it to Project Management and Architect. If the Contractor performs any construction
activity knowing it involves a recognized error, inconsistency or omission in the Contract
Documents without such notice to Project Management and Architect, the Contractor shall
assume appropriate responsibility for such performance and shall bear an appropriate amount
of the attributable costs for correction.
3.2.2 The Contractor shall take field measurements and verify field conditions and shall
carefully compare such field measurements and conditions and other information known to the
Contractor with the Contract Documents before commencing activities. Errors, inconsistencies
or omissions discovered shall be reported to Project Management and Architect at once.
3.2.3 The Contractor shall perform the Work in accordance with the Contract Documents and
submittals approved pursuant to Paragraph 3.12.
7YTIVZMWMSRERH'SRWXVYGXMSR4VSGIHYVIW
3.3.1 The Contr
attention. The Contractor shall be solely responsible for and have control over construction
means, methods, techniques, sequences and procedures and for coordinating all portions of the
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Work under this Contract, subject to overall coordination of Project Management as provided in
Subparagraphs 4.6.3 and 4.6.5.
3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the
actors and their agents and employees, and other persons
performing portions of the Work under a contract with the Contractor.
3.3.3 The Contractor shall not be relieved of obligations to perform the Work in accordance
with the Contract Documents either by activities or duties of Project Management in its
administration of the Contract, or by test, inspections or approvals required or performed by
persons other than the Contractor.
3.3.4 The Contractor shall inspect portions of the Project related to the C
order to determine that such portions are in proper condition to receive subsequent work.
3.3.5 The Contractor shall verify that the Construction Documents being worked with are the
most recent and updated available, including all Addenda information. Also the Contractor will
perform the work strictly in accordance with this contract.
0EFSVERH1EXIVMEPW
3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and
pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat,
utilities, transportation, and other facilities and services necessary for proper execution and
completion of the Work, whether temporary or permanent and whether or not incorporated or to
be incorporated in the Work.
3.4.2
employees and other persons carrying out the Contract. The Contractor shall not permit
employment of unfit persons or persons not skilled in tasks assigned to them.
3.4.3 The Contractor is responsible for the conduct of his employees at all times. Misconduct,
destruction of property, unsafe practices, or violation of any Federal or State regulations
including abuse of alcohol or drugs, will be cause for permanent dismissal from the project. If
Management, the Contractor will remove and/or replace the employee at the request of Project
Management. Employees dismissed from the project will be transported from the job site at the
3.4.4 The Contractor shall be totally responsible for the security of his work, materials,
equipment, supplies, tools, machinery, and construction equipment.
3.4.5 The Contractor shall be responsible for complete, timely and accurate field
measurements as necessary for proper coordination, fabrication and installation of his materials
and equipment. The Contractor agrees to cooperate with Project Management, if required, to
accommodate any discovered variations or deviations from the Drawings and Specifications so
that the progress of the Work is not adversely affected.
;EVVERX]
3.5.1 The Contractor warrants to the Owner, Project Management and Architect that materials
and equipment furnished under the Contract will be of good quality and new unless otherwise
required or permitted by the Contract Documents, that the Work will be free from defects not
inherent in the quality required or permitted, and that the Work will conform with the
requirements of the Contract Documents. Work not conforming to these requirements, including
substitutions not properly approved and authorized, may be considered defective. The
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
e or defect caused by abuse, modifications
not executed by the Contractor, improper or insufficient maintenance, improper operation, or
normal wear and tear under normal usage. If required by Project Management, the Contractor
shall furnish satisfactory evidence as to the kind and quality of materials and equipment.
8E\IW
3.6.1 The Contractor shall pay sales, consumer, use and similar taxes for the Work or portions
thereof provided by the Contractor which are legally enacted when bids are received or
negotiations concluded, whether or not yet effective or merely scheduled to go into effect.
4IVQMXW*IIWERH2SXMGIW
3.7.1 The Contractor shall secure and pay for all permits, impact fees, governmental fees,
licenses, inspections, testing, surveys and utility fees required by Federal, State, Municipal or
Utility entities having jurisdiction over the project for the proper execution and completion of the
Work which are customarily secured after execution of the Contract and which are legally
required at the time bids are received. The Contractor will be responsible for all building permit
costs or impact fees required for this project. The Contractor shall secure and pay for all
building and specialty permits including plumbing, electrical, HVAC, etc.
3.7.2 The Contractor shall comply with and give notices required by laws, ordinances, rules,
regulations and lawful orders of public authorities bearing on performance of the Work.
3.7.3 It is not the Contractor
accordance with applicable laws, statutes, ordinances, building codes, and rules and
regulations. However, if the Contractor observes that portions of the Contract Documents are at
variance therewith, the Contractor shall promptly notify Project Management, Architect and
Owner in writing, and necessary changes shall be accomplished by appropriate Modification.
3.7.4 If the Contractor performs Work knowing it to be contrary to laws, statutes, ordinances,
building codes, and rules and regulations without such notice to Project Management, Architect
and Owner, the Contractor shall assume full responsibility for such Work and shall bear the
attributable costs.
7YTIVMRXIRHIRX
3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who
shall be in attendance at the Project site during performance of the Work. The superintendent
shall represent the Contractor, and communications given to the superintendent shall be as
binding as if given to the Contractor. Important communications shall be confirmed in writing.
Other communications shall be similarly confirmed on written request in each case. The
superintendent shall be satisfactory to Project Management and shall not be changed except
with the consent of Project Management, unless the superintendent proves to be unsatisfactory
to the Contractor or ceases to be in his employ.
3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for
Construction Schedule for the Work. Such schedule shall not exceed time limits current under
the Contract Documents, shall be revised at appropriate intervals as required by the conditions
of the Work and Project, shall be related to the entire Project construction schedule to the extent
required by the Contract Documents, and shall provide for expeditious and practicable
execution of the Work. This schedule, to be submitted within fourteen (14) days after Contract
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Award, shall indicate the dates for the starting and completion of the various stages of
construction, shall be revised as required by the conditions of the Work, and shall be subject to
3.10.2 The Contractor shall cooperate with Project Management in scheduling and performing
Contractors or the co
3.10.4 The Contractor shall conform to the most recent schedules.
3.10.5 Project Management will schedule and conduct a project meeting at a minimum of one
meeting per month in each month which the Contractor shall attend. At this meeting, the
parties can discuss jointly such matters as progress, scheduling, and problems.
(SGYQIRXWERH7EQTPIWEXXLI7MXI
3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings,
Specifications, addenda, Change Orders and other Modifications, in good order and marked
currently to record changes and selections made during construction, and in addition approved
Shop Drawings, Product Data, Samples and similar required submittals. These shall be
available to Project Management and Architect and shall be delivered to Project Management
for submittal to the Owner upon completion of the Work.
7LST(VE[MRKW4VSHYGX(EXEERH7EQTPIW
3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for
the Work by the Contractor or a Subcontractor, Sub-subcontractor, manufacturer, supplier or
distributor to illustrate some portion of the Work.
3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions,
brochures, diagrams and other information furnished by the Contractor to illustrate materials or
equipment for some portion of the Work.
3.12.3 Samples are physical examples which illustrate materials, equipment or workmanship
and establish standards by which the Work will be judged.
3.12.4 Shop Drawings, Product Data, Samples and similar submittals are not Contract
Documents. The purpose of their submittal is to demonstrate for those portions of the Work for
which submittals are required the way the Contractor proposes to conform to the information
given and the design concept expressed in the Contract Documents. Review by Project
Management is subject to the limitations of Subparagraph 4.6.12.
3.12.5 The Contractor shall review, approve and submit to Project Management, in accordance
with the schedule and sequence approved by Project Management, Shop Drawings, Product
Data, Samples and similar submittals required by the Contract Documents. The Contractor
shall cooperate with Proj
Drawings, Product Data, Samples and similar submittals with related documents submitted by
other Contractors. Submittals made by the Contractor which are not required by the Contract
Documents may be returned without action.
3.12.6 The Contractor shall perform no portion of the Work requiring submittal and review of
Shop Drawings, Product Data, Samples or similar submittals until the respective submittal has
been approved by Project Management. Such Work shall be in accordance with approved
submittals.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
3.12.7 By approving and submitting Shop Drawings, Product Data, Samples and similar
submittals, the Contractor represents that the Contractor has determined and verified materials,
field measurements and field construction criteria related thereto, or will do so, and has checked
and coordinated the information contained within such submittals with the requirements of the
Work and of the Contract Documents.
3.12.8 The Contractor shall not be relieved of responsibility for deviations from requirements of
the Contract Documents by Project Management approval of Shop Drawings, Product Data,
Samples or similar submittals unless the Contractor has specifically informed Project
Management and Architect in writing of such deviation at the time of submittal and Project
Management have given written approval to the specific deviation. The Contractor shall not be
relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples or
simila
3.12.9 The Contractor shall direct specific attention, in writing or on resubmitted Shop
Drawings, Product Data, Samples or similar submittals, to revisions other than those requested
by Project Management and Architect on previous submittals.
3.12.10 Informational submittals upon which Project Management are not expected to take
responsive action may be so identified in the Contract Documents.
3.12.11 When professional certification of performance criteria of materials, systems or
equipment is required by the Contract Documents, Project Management and Architect shall be
entitled to rely upon the accuracy and completeness of such calculations and certifications.
3.12.12 If materials specified in the Contract Documents are not available on the present
market, the Contractor may submit data on substitute materials to Project Management for
approval by the Owner.
9WISJ7MXI
3.13.1 The Contractor shall confine operations at the site to areas permitted by law, ordinances,
permits and the Contract Documents and shall not unreasonably encumber the site with
materials or equipment.
3.13.2
approval of, Project Management before using any portion of the site.
'YXXMRKERH4EXGLMRK
3.14.1 The Contractor shall be responsible for cutting, fitting or patching required to complete
the Work or to make its parts fit together properly; He shall also provide protection of existing
work as required.
3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially
excavating or otherwise altering such construction. The Contractor shall not cut or otherwise
consent of Project Management, Owner and such other contractors: such consent shall not be
unreasonably withheld. The Contractor shall not unreasonably withhold from the other
When structural members are involved, the written consent of Project Management shall also be
required. The Contractor shall not unreasonably withhold from Project Management or any
separate contractor his consent to cutting or otherwise altering the Work.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
3.14.3 The Contractor shall arrange for any blockouts, cutouts, or openings required for the
installation of his materials and equipment and the execution of his work, whether or not shown
or indicated on the Drawings. The Contractor shall be further responsible for sealing and/or
finishing, in an acceptable fashion and meeting any applicable code requirements, and such
block-out, cutout opening, or other hole in any fire-related floor, ceiling, wall, security wall, or
any other finished surface.
'PIERMRK9T
3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of
waste materials or rubbish caused by operations under the Contract. At completion of the Work
the Contractor shall remove from and about the project waste materials rubbish, the
hinery and surplus materials. Clean up shall be
performed to the satisfaction of the Owner or Project Management.
3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, Project
the cost thereof shall be charged to the
Contractor.
%GGIWWXS;SVO
3.16.1 The Contractor shall provide the Owner, Project Management and Architect access to
the Work in preparation and progress wherever located.
6S]EPXMIWERH4EXIRXW
3.17.1 The Contractor shall pay all royalties and license fees. The Contractor shall defend suits
or claims for infringement of patent rights and shall hold the Owner, Project Management and
Architect harmless from loss on account thereof, but shall not be responsible for such defense
or loss when a particular design, process or product of a particular manufacturer or
manufacturers is required by the Contract Documents. However, if the Contractor has reason to
believe that the required design, process or product is an infringement of a patent, the
Contractor shall be responsible for such loss unless such information is promptly furnished to
the Architect and Project Management.
-RHIQRMJMGEXMSRERH,SPH,EVQPIWW
Notwithstanding any minimum insurance requirements prescribed elsewhere in this
elected and appointed officers and employees harmless from and against (i) any claims, actions
or causes of action, (ii) any litigation, administrative proceedings, appellate proceedings, or
other proceedings relating to any type of injury (including death), loss, damage, fine, penalty or
business interruption, and (iii) any costs or expenses that may be asserted against, initiated with
respect to, or sustained by, any indemnified party by reason of, or in connection with, (A) any
activity of Contractor or any of its employees, agents, contractors or other invitees during the
term of this Agreement, (B) the negligence or recklessness, intentional wrongful misconduct,
errors or other wrongful act or omission of Contractor or any of its employees, agents, sub-
contractors or other invitees, or (C) Contractor's default in respect of any of the obligations that it
undertakes under the terms of this Agreement, except to the extent the claims, actions, causes
of action, litigation, proceedings, costs or expenses arise from the intentional or sole negligent
acts or omissions of the COUNTY or any of its employees, agents, contractors or invitees (other
than Contractor). Insofar as the claims, actions, causes of action, litigation, proceedings, costs
or expenses relate to events or circumstances that occur during the term of this Agreement, this
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
section will survive the expiration of the term of this Agreement or any earlier termination of this
Agreement.
In the event that the completion of the project (to include the work of others) is delayed or
suspended as a result of the Contractor
the Consultant shall indemnify the County from any and all increased expenses resulting from
such delay. Should any claims be asserted against the County by virtue of any deficiency or
ambiguity in the plans and specifications provided by the Contractor, the Contractor agrees and
warrants that the Contractor shall hold the County harmless and shall indemnify it from all
The first ten dollars ($10.00) of remuneration paid to the Contractor is for the indemnification
provided for the above.
%(1-2-786%8-323*8,)'328%'8
%VGLMXIGX)RKMRIIV
4.1.1 The Architect and /or Engineer is the person lawfully licensed to practice
architecture/engineering or any entity lawfully practicing architecture/engineering identified as
such in the Agreement and is referred to throughout the Contract Documents as if singular in
4VSNIGX1EREKIQIRX
4.2.1 Project Management is the person or entity identified as such in the Agreement and is
Department or Project
Duties, responsibilities and limitations of authority of Project Management and Architect
as set forth in the Contract Documents shall not be restricted, modified or extended without
written consent of the Owner, Project Management, Architect and Contractor. Consent shall not
be unreasonably withheld.
In case of termination of employment of Architect, the Owner shall appoint an Architect
whose status under the Contract Documents shall be that of the former Architect.
2SX9WIH
%HQMRMWXVEXMSRSJXLI'SRXVEGX
4.6.1 Project Management and Engineer will provide administration of the Contract as
construction,
time during the correction period described in Paragraph 12.2. Project Management and
Engineer will advise and consult with the Owner and will have authority to act on behalf of the
Owner only to the extent provided in the Contract Document, unless otherwise modified by
written instrument in accordance with other provision of the Contract.
4.6.2 Project Management and Engineer will determine in general that the Work is being
performed in accordance with the requirements of the Contract Documents, will keep the Owner
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
informed of the progress of the Work, and will endeavor to guard the Owner against defects and
deficiencies in the Work.
4.6.3 Project Management will provide for coordination of the activities of other Contractors
The Contractor shall participate with other Contractors and Project Management and Owner in
reviewing their construction schedules when directed to do so. The Contractor shall make any
revisions to the Construction schedule deemed necessary after a joint review and mutual
agreement. The construction schedules shall constitute the schedules to be used by the
Contractor, other Contractors, Project Management and the Owner until subsequently revised.
4.6.4 Not used.
4.6.5 Project Management will visit the site at intervals appropriate to the stage of construction
to become generally familiar with the progress and quality of the completed Work and to
determine in general if the Work is being performed in a manner indicating that the Work, when
completed, will be in accordance with the Contract Documents. However, Project Management
will not be required to make exhaustive or continuous onsite inspections to check quality or
quantity of the Work. On the basis of on-site observations as an architect, Project Management
will keep the Owner informed of progress of the Work, and will endeavor to guard the Owner
against defects and deficiencies in the work.
4.6.6 Project Management will not have control over or charge of and will not be responsible
for construction means, method, techniques, sequences or procedures, or for safety precautions
and programs in connection wi
out the Work in accordance with the Contract Documents. Neither Project Management nor the
Architect will have control over, or charge of, or be responsible for acts or omissions of the
Contractor, Subcontractors, or their agents or employees, or of any other persons performing
portions of the Work.
4.6.7 Communications Facilitating Contract Administration. Except as otherwise provided in
the Contract Documents or when direct communications have been specially authorized, the
Owner and Contractor shall communicate through Project Management, and shall
contemporaneously provide the same communications to the Architect. Communications by
Subcontractors and material suppliers shall be through the Contractor. Communications by and
with other Contractors shall be through Project Management and shall be contemporaneously
provided to the Architect.
4.6.8 Project Management will review and certify all Applications for Payment by the
Contractor, including final payment. Project Management will assemble each of the
Project Application for Payment. After reviewing and certifying the amounts due the
Applications for Payment, will be processed by Project Management.
4.6.9 Based on Project s
Applications for Payment, Project Management will certify the amounts due the Contractors and
will issue a Project Approval for Payment.
4.6.10 Project Management will have authority to reject Work which does not conform to the
Contract Documents, and to require additional inspection or testing, in accordance with
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Subparagraphs 13.5.2 and 13.5.3, whether or not such Work is fabricated, installed or
completed, but will take such action only after notifying Project Management. Subject to review,
Project Management will have the authority to reject Work which does not conform to the
Contract Documents. Whenever Project Management considers it necessary or advisable for
implementation of the intent of the Contract Documents, Project Management will have authority
to require additional inspection or testing of the work in accordance with Subparagraphs 13.5.2
and 13.5.3, whether or not such Work is fabricated, installed or completed. The foregoing
authority of Project Management will be subject to the provisions of Subparagraphs 4.6.18
through 4.6.20 inclusive, with respect to interpretations and decisions of the Architect.
Subparagraph 4.6.10 nor a decision made by either of them in good faith either to exercise or
not to exercise such authority shall give rise to a duty or responsibility of the Architect or Project
Management to the Contractor, Subcontractors, material and equipment suppliers, their agents
or employees, or other persons performing any of the Work.
4.6.11 Project Management will receive from the Contractor and review and approve all Shop
Drawings, Product Data and Samples, coordinate them with information received from other
Contractors, and review those recommended for approval. Project Management actions will be
taken with such reasonable promptness as to cause no delay in the Work of the Contractor or in
the activities of other Contractors or the Owner.
4.6.12 Project Management will review and approve or take other appropriate action upon the
limited purpose of checking for conformance with information given and the design concept
expressed in the Contract Documents. Project Management action will be taken with such
promptness consistent with the constraints of the project schedule so as to cause no delay in
the Work of the Contractor or in the activities of the other Contractors, the Owner, or Project
Management, while allowing sufficient time to permit adequate review. Review of such
submittals is not conducted for the purpose of determining the accuracy and completeness of
other details such as dimensions and quantities, or for substantiating instructions for installation
or performance of equipment or systems, all of which remain the responsibility of the Contractor
as Contractor as required by the Contract Documents. Project Management review of the
ittals shall not relieve the Contractor of the obligations under Paragraphs 3.3,
3.5 and 3.12. Project Management review shall not constitute approval of safety precautions
or, unless otherwise specifically stated by Project Management, of any construction means,
methods, techniques, sequences or procedures. approval of a specific
item shall not indicate approval of an assembly of which the item is a component.
4.6.13 Project Management will prepare Change Orders and Construction Change Directives.
4.6.14 Following consultation with the Owner, Project Management will take appropriate action
on Change Orders or Construction Change Directives in accordance with Article 7 and will have
authority to order minor changes in the Work as provided in Paragraph 7.4.
4.6.16 The Contractor will assist Project Management in conducting inspections to determine
the dates of Substantial completion and final completion, and will receive and forward to Project
Management written warranties and related documents required by the Contract and assembled
by the Contractor. Project Management will review and approve a final Project Application for
Payment upon compliance with the requirements of the Contract Documents.
4.6.17 Project Management will provide one or more project representatives to assist in
carrying out his responsibilities at the site. The duties, responsibilities and limitations of
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
authority of such project representatives shall be as set forth in an exhibit to be incorporated in
the Contract Documents.
4.6.18 Project Management will interpret and decide matters concerning performance under
and requirements of the Contract Documents on written request of the Owner or Contractor.
response to such requests will be made with reasonable promptness and
within any time limits agreed upon. If no agreement is made concerning the time within which
interpretations required of Project Management shall be furnished in compliance with this
Paragraph 4.6, then delay shall not be recognized on account of failure by Project Management
to furnish such interpretations until 15 days after written request is made for them.
4.6.19 Interpretations and decisions of Project Management will be consistent with the intent of
and reasonably inferable from the Contract Documents and will be in writing or in the form of
drawings. When making such interpretations and decisions, Project Management will endeavor
to secure faithful performance by both Owner and Contractor, will not show partiality to either
and will not be liable for results of interpretations or decisions so rendered in good faith.
4.6.20 decisions on matters relating to aesthetic effect will be final if
consistent with the intent expressed in the Contract Documents.
'PEMQWERH(MWTYXIW
(IJMRMXMSR
4.7.1 . A Claim is a demand or assertion by one of the parties seeking, as a matter
of right, adjustment or interpretation of Contract terms, payment of money, extension of time or
disputes and matters in question between the Owner and Contractor arising out of or relating to
the Contract. Claims must be made by written notice. The responsibility to substantiate Claims
shall rest with the party making the claim.
1IIXERH'SRJIV
4.7.2 . The Contractor and Project Management shall try to resolve the
claim or dispute with meet and confer sessions to be commenced within 15 days of the dispute
or claim. Any claim or dispute that the parties cannot resolve shall be decided by the Circuit
th
Court, 16 Judicial Circuit, Monroe County, Florida.
8MQI0MQMXWSR'PEMQW
4.7.3 . Claims by either party must be made within 21 days after
occurrence of the event giving rise to such Claim or within 21 days after the claimant first
recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by
written notice submitted to the designated representative. An additional Claim made after the
initial Claim has been implemented by Change Order will not be considered unless submitted in
in a timely manner.
4.7.3.1 Any claim not filed with the Owner within such time and in compliance with the
preceding provisions shall be deemed conclusively to have been waived and shall be dismissed
at the option of the Owner. The claim shall set forth in detail all known facts and circumstances
supporting the claim; final costs associated with any claim upon which notice has been filed
must be submitted in writing to the Owner with thirty (30) calendar days after notice has been
received. In the event the Contractor seeks to make a claim for an increase in the contract
price, as a condition precedent to any liability of the Owner therefore, unless emergency
conditions exist, the Contractor shall strictly comply with the requirements of this Section and
such claim shall be made by the Contractor before proceeding to execute any work for which a
claim is made. Failure to comply with this condition precendent shall constitute a waiver by the
Contractor of any claim for additional compensation.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
'SRXMRYMRK'SRXVEGX4IVJSVQERGI
4.7.4 . Pending final resolution of a Claim unless
otherwise agreed in writing the Contractor shall proceed diligently with performance of the
Contract and the Owner shall continue to make payments in accordance with the Contract
Documents.
;EMZIVSJ'PEMQW*MREP4E]QIRX
4.7.5. The making of final payment shall constitute a
waiver of Claim by the Owner except those arising from:
.1 liens, Claims, security interests or encumbrances arising out of the Contract and
unsettled;
.2 failure of the Work to comply with the requirements of the Contract Documents; or
.3 terms of special warranties required by the Contract Documents.
'PEMQWJSV'SRGIEPIHSV9RORS[R'SRHMXMSRW
4.7.6 If conditions are encountered at the
site which are (1) subsurface or otherwise concealed physical conditions which differ materially
from those indicated in the Contract Documents or (2) unknown physical conditions of an
unusual nature, which differ materially from those ordinarily found to exist and generally
recognized as inherent in construction activities of the character provided for in the Contract
Documents, then notice by the observing party shall be given to the other party promptly before
conditions are disturbed and in no event later than 10 days after first observance of the
conditions. Project Management will promptly investigate such conditions, and the parties will
follow the procedure in paragraph 4.7.2.
4.7.6.1 As a condition precedent to the Owner having any liability to the Contractor due to
concealed and unknown conditions, the Contractor must give the Owner and Owner Engineer
written notice of, and an opportunity to observe, such condition prior to disturbing it. The failure
by the Contractor to give the written notice and make the claim as provided by the provisions
herein shall constitute a waiver by the Contractor of any rights arising out of or relating to such
concealed and unknown condition.
'PEMQWJSV%HHMXMSREP'SWX
4.7.7 . If the Contractor wishes to make Claim for an increase in
the Contract Sum, written notice as provided herein shall be given before proceeding to execute
the Work. Prior notice is not required for Claims relating to an emergency endangering life or
property arising under Paragraph 10.3 If the Contractor believes additional cost is involved for
reasons including but not limited to (1) a written interpretation from Project Management, (2) a
written order for a minor change in the Work issued by Project Management, (3) failure of
(6) other reasonable grounds, Claim shall be filed in accordance with the procedure established
herein. In a claim by the Contractor against the Owner for compensation in excess of the
Contract Sum, any liability of the Owner to the Contractor shall be strictly limited and computed
in accordance with the contract documents and shall in no event include indirect costs or
consequential damages of the Contractor or any estimated costs or damages.
'PEMQWJSV%HHMXMSREP8MQI
4.7.8.1. If the Contractor wishes to make Claim for an increase in the Contract Time, written
notice as provided herein shall be given.
4.7.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim
shall be documented by data substantiating that weather conditions were abnormal for the
period of time and could not have been reasonably anticipated, and that weather conditions had
an adverse effect on the scheduled construction.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
-RNYV]SV(EQEKIXS4IVWSRSV4VSTIVX]
4.7.9 If either party to the Contract suffers injury
or damage to person or property because of an act or omission of the other party, of any of the
yees or agents, or of others for whose acts such party is legally liable, written
notice of such injury or damage, whether or not insured, shall be given to the other party within
a reasonable time not exceeding 21 days after first observance. The notice shall provide
sufficient detail to enable the other party to investigate the matter. If a Claim for additional cost
or time related to this Claim is to be asserted, it shall be filed as provided in Subparagraphs
4.7.7 or 4.7.8.
79&'3286%'8367
(IJMRMXMSRW
5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to
Contract Documents as if singular in number and means a Subcontractor or an authorized
Contractors or subcontractors of other Contractors.
5.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a
-
referred to throughout the Contract Documents as if singular in number and means a Sub-
subcontractor or an authorized representative of the Sub-subcontractor.
%[EVHSJ7YFGSRXVEGXWERH3XLIV'SRXVEGXWJSV4SVXMSRWSJXLI;SVO
5.2.1 Unless otherwise stated in the Contract Documents or the bidding requirements, the
Contractor, as soon as practicable after award of the Contract, shall furnish in writing to Project
Management for review by the Owner and Project Management the names of persons or
entities (including those who are to furnish materials or equipment fabricated to a special
design) proposed for each principal portion of the Work. Project Management will promptly
reply to the Contractor in writing stating whether or not the Owner or Project Management, after
due investigation, has reasonable objection to any such proposed person or entity. Failure of
Project Management to reply promptly shall constitute notice of no reasonable objection.
5.2.2 The Contractor shall not contract with a proposed person or entity to which the Owner or
Project Management has made reasonable and timely objection. The Contractor shall not be
required to contract with anyone to whom the Owner or Project Management has made
reasonable objection.
5.2.3 If the Owner or Project Management refuses to accept any person or entity on a list
submitted by the Contractor in response to the requirements of the Contract Documents, the
Contractor shall submit an acceptable substitute; however, no increase in the Contract Sum
shall be allowed for any such substitution.
5.2.4 The Contractor shall not change a Subcontractor, person or entity previously selected if
the Owner or Project Management makes reasonable objection to such change.
7YFGSRXVEGXYEP6IPEXMSRW
5.3.1 By appropriate written agreement, the Contractor shall require each Subcontractor, to
the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by
terms of the Contract Documents, and to assume toward the Contractor all the obligations and
responsibilities which the Contractor, by these Documents, assumes toward the Owneror
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Project Management. Each subcontract agreement shall preserve and protect the rights of the
Owner or Project Management under the Contract Documents with respect to the Work to be
performed by the Subcontractor so that subcontracting thereof will not prejudice such rights.
When appropriate, the Contractor shall require each Subcontractor to enter into similar
agreements with Sub-subcontractors. The Contractor shall make available to each proposed
Subcontractor, copies of the Contract Documents which the Subcontractor will be bound, and,
upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of
the proposed subcontract agreement which may be at variance with the Contract Documents.
Subcontractors shall similarly make copies of applicable portions of such documents available
to their respective proposed Sub-subcontractors.
'SRXMRKIRX%WWMKRQIRXSJ7YFGSRXVEGXW
5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to
the Owner provided that:
.1 assignment is effective only after termination of the Contract by the Owner for cause
pursuant to Paragraph 14.2 and only for those subcontract agreements which the Owner
accepts by notifying the Subcontractor in writing; and
.2 assignment is subject to the prior rights of the surety, if any, obligated under public
construction bond covering the Contract.
i. If the work has been suspended for more than 30 days, the
'327869'8-32&=3;2)636&=38,)6'3286%'8367
'SRWXVYGXMSR[MXL3[R*SVGIWERHXS%[EVH3XLIV
'SRXVEGXW
6.1.1 The Owner reserves the right to perform construction or operations released to the
not administered by Project Management. The Owner further reserves the right to award other
contracts in connection with other portions of the Project or other construction or operations on
the site under Conditions of the Contract identical or substantially similar to these including
those portions related to insurance and waiver or subrogation.
6.1.2
including persons or entities under separate contracts not administered by Project Management,
the Owner shall provide for coordination of such forces with the Work of the Contractor who
shall cooperate with them.
6.1.3 It shall be the responsibility of the Contractor to coordinate his work with the work of
other contractors on the site. The Owner and Project Management shall be held harmless for
any and all costs associated with improper coordination.
1YXYEP6IWTSRWMFMPMX]
6.2.1 s, Project Management and other
contractors reasonable opportunity for introduction and storage of their materials and equipment
construction and operations with theirs as required by the Contract Documents.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
6.2.2 If part of the Co
prior to proceeding with that portion of the Work, promptly report to Project Management any
apparent discrepancies or defects in such other construction that would render it unsuitable for
such proper execution and results. Failure of the Contractor so to report shall constitute an
leted or partially
not then reasonably discoverable.
6.2.3 Costs caused by delays or by improperly timed activities or defective construction shall
be borne by
caused by delays or improperly timed activities or defective construction shall be an extension
of time.
6.2.4 The Contractor shall promptly remedy damage wrongfully caused by the Contractor to
completed or partially completed construction or to property of the Owner or other contractors
as provided in Subparagraph 10.2.5.
6.2.5 Claims and other disputes and matters in question between the Contractor and other
contractors shall be subject to the provisions of Paragraph 4.7 provided the other contractors
have reciprocal obligations.
6.2.6 The Owner and other contractors shall have the same responsibilities for cutting and
patching as are described for the Contractor in Paragraph 3.14.
6.2.7 Should the Contractor contend that he is entitled to an extension of time for completion
of any portion or portions of the work, he shall, within (72) hours of the occurrence of the cause
of the delay, notify Project Management in writing, of his contention: setting forth (A) the cause
for the delay, (B) a description of the portion or portions of work affected thereby, and (C) all
details pertinent thereto. A subsequent written application for the specific number of days of
extension of time requested shall be made by the Contractor to Project Management within (72)
hours after the delay has ceased to exist.
.1 It is a condition precedent to the consideration or prosecution of any claim for an
extension of time that the foregoing provisions be strictly adhered to in each instance and, if the
Contractor fails to comply, he shall be deemed to have waived the claim.
.2 The Contractor agrees that whether or not any delay, regardless of cause, shall be
the basis for an extension of time he shall have no claim against the Owner or Project
Management for an increase in the Contract price, nor a claim against the Owner or Project
Management for a payment or allowance of any kind for damage, loss or expense resulting from
delays; nor shall the Contractor have any claim for damage, loss or expense resulting from
interruptions to, or suspension of, his work to enable other contractors to perform their work.
The only remedy available to the Contractor shall be an extension of time.
ER9T
6.3.1 If a dispute arises among the Contractor, other contractors and the Owner as to the
responsibility under their respective contracts for maintaining the premises and surrounding
area free from waste materials and rubbish as described in Paragraph 3.15, the Owner may
clean up and allocate the cost among those responsible as Project Management determines to
be just.
',%2+)7-28,);36/
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
'LERKIW
7.1.1 Changes in the Work may be accomplished after execution of the Contract, and without
invalidating the Contract, by Change Order, Construction Change Directive or order for a minor
change in the Work, subject to the limitations stated in this Article 7 and elsewhere in the
Contract Documents.
7.1.2 A Change Order shall be based upon agreement among the Owner, Project
Management and Contractor; a Construction Change Directive require agreement by the
Owner, Project Management and may or may not be agreed to by the Contractor; an order for a
minor change in the Work may be issued by Project Management alone.
7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract
Documents, and the Contractor shall proceed promptly, unless otherwise provided in the
Change Order, Construction Change Directive or order for a minor change in the Work.
7.1.4 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if
quantities originally contemplated are so changed in a proposed Change Order or Construction
Change Directive that application of such unit prices to quantities of Work proposed will cause
substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably
adjusted.
'LERKI3VHIVW
7.2.1 A Change Order is a written instrument prepared by Project Management and signed by
the Owner, Project Management and Contractor stating their agreement upon all of the
following:
.1 a change in the Work;
.2 the amount of the adjustment in the Contract Sum, if any; and
.3 the extent of the adjustment in the Contract Time, if any.
7.2.2 The cost or credit to the Owner resulting from a change in the Work shall be determined
in one or more of the following methods:
.1 mutual acceptance of lump sum properly itemized and supported by sufficient
substantiating data to permit evaluation and payment, and approved by the appropriate
authority in writing;
.2 unit prices stated in the Contract Documents or subsequently agreed upon, and
approved by the appropriate authority in writing;
.3 cost to be determined in a manner agreed upon by the parties and a mutually
acceptable fixed or percentage fee;
.4 or by method provided in subparagraph 7.2.3.
7.2.3 If none of the methods set forth in Clauses 7.2.1 or 7.2.2 is agreed upon, the Contractor,
provided a written order signed by the Owner or Project Management is received, shall promptly
proceed with the Work involved. The cost of such Work shall then be determined by daily force
accounts in a form acceptable to the Owner and Project Management. The daily force account
forms shall identify Contractor and /or Subcontractor personnel by name, total hours for each
man, each piece of equipment and total hours for equipment and all material(s) by type for each
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
extra Work activity claim. Each daily force account form shall be signed by the designated
Project Management representative no later than the close of business on the day the Work is
performed to verify the items and hours listed. Extended pricing of these forms shall be
submitted to Project Management with all supporting documentation required by Project
Management for inclusion into a change order. Unless otherwise provided in the Contract
Documents, cost shall be limited to the following: cost of materials, including sales tax and cost
of delivery; cost of labor, including social security, old age and unemployment insurance, and
and the rental value of equipment and machinery. Markups for overhead and profit will be in
accordance with subparagraph 7.2.4. Pending final determination of cost, payments on account
shall be made as determined by Project Management. The amount of credit to be allowed by
the Contractor for any deletion or change, which results in a net decrease in the Contract Sum,
will be the amount of the actual net cost to the Owner as confirmed by Project Management.
When both additions and credits covering related Work or substitutions are involved in any one
change, the allowance for overhead and profit shall be figured on the basis of the net increase,
if any with respect to that change.
7.2.4 The actual cost of Changes in the Work may include all items of labor or material, power
tools, and equipment actually used, utilities, pro rata charges for foreman, and all payroll
overhead and profit shall be allowed on items of Social Security and Sales Tax. If deductions
are ordered the amount of credit shall be net cost to Owner as defined in section 5.6.1 of the
Contract. Items considered as overhead shall include insurance other than that mentioned
above, bond or bonds, superintendent, timekeeper, clerks, watchmen, use of small tools,
miscellaneous supplies, incidental job costs, warranties, and all general home/field office
expenses. The actual cost of Changes in the Work (other than those covered by unit prices set
forth in the Contract Documents) shall be computed as follows:
.1 if the Contractor performs the actual Work, the maximum percentage mark-up for
overhead shall be five percent (5%) and the maximum percentage for profit shall be five percent
(5%);
tage mark-
up for overhead and profit shall be a maximum addition of ten percent (10%). If the Contractor
does not perform the Work, the maximum mark-up for managing the Work will be five percent
(5%);
3. If the Subcontractor performs part of the actual Work, his percentage mark-up for
overhead and profit shall be a maximum addition of ten percent (10%) on his direct Work only. If
the Contractor performs part of the actual Work, his percentage mark-up for overhead and profit
shall be a maximum addition of ten percent (10%) on his direct Work only.
7.2.5 The Contractor shall furnish to the Owner through Project Management, an itemized
breakdown of the quantities and prices used in computing the value of any change that might be
ordered. Any additional supporting documentation requested by Project Management such as
certified quotations or invoices shall be provided by the Contractor to Project Management at no
additional cost to the Owner.
7.2.6 If the Contractor claims that any instructions given to him by Project Management, by
drawings or otherwise, involve extra Work not covered by the Contract, he shall give Project
Management written notice thereof within five (5) days after the receipt of such instructions and
before proceeding to execute the work, except in emergencies endangering life or property, in
which case the Contractor shall proceed in accordance with Paragraph 10.3.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
.1 The written notice to Project Management for the Extra Work shall include a complete
description of the extra Work, the total cost and a detailed cost breakdown by labor, material
and equipment for each additional activity required to be performed. Mark-ups shall be limited
as specified elsewhere in this Article.
.2 Except as otherwise specifically provided, no claim for additional cost shall be
allowed unless the complete notice specified by this subparagraph is given by the Contractor.
7.2.7 Unless otherwise agreed in writing, the Contractor shall carry on the Work and maintain
its progress during any dispute or claim proceeding, and Owner shall continue to make
payments to the Contractor in accordance with the Contract Documents. Disputes unresolved
shall be settled in accordance with subparagraph 4.7. The Contractor shall maintain completed
daily force account forms in accordance with subparagraph 7.2.3 for any dispute or claim item.
7.2.8 One or more changes to the Work within the general scope of this Contract, may be
ordered by Change Order. The Owner may also issue written directions for changes in the
Work and may issue Construction Change Directives, as set forth below. The Contractor shall
proceed with any such changes or Construction Change Directives without delay and in a
diligent manner, and same shall be accomplished in strict accordance with the terms and
conditions otherwise provided for in the Contract.
7.2.9 The execution of a Change Order by the Contractor shall constitute conclusive evidence
of
amended, the Contract Price and the time for performance by the Contractor. The Contractor,
by executing the Change Order, waives and forever releases any claim against the Owner for
additional time or compensation for matters relating to, arising out of or resulting from the Work
included within or affected by the executed Change Order of which the Contractor knew or
should have known.
%YXLSVMX]
7.3.1 Project Management will have authority to order minor changes in the Work not involving
adjustment in the Contract sum or extension of the Contract Time and not inconsistent with the
intent of the Contract Documents. Such changes shall be effected by written order issued
through Project Management and shall be binding on the Owner and Contractor. The Contractor
shall carry out such written order promptly.
8-1)
(IJMRMXMSRW
8.1.1 Unless otherwise provided, Contract Time is the period of time, including authorized
adjustments, allotted in the Contract Documents for Substantial Completion of the Work.
8.1.2 The date of commencement of the Work is the date established in the Agreement. The
date shall not be postponed by the failure to act of the Contractor or of persons or entities for
which the Contractor is responsible.
8.1.3 The date of Substantial Completion is the date certified by Project Management in
accordance with Paragraph 9.8.
8.1.4 unless
otherwise specifically defined.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
8.1.5 The Owner/Project Management shall be the final judge as to whether Substantial
Completion has been achieved and certifies the date to the Contractor.
4VSKVIWWERH'SQTPIXMSR
8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By
executing the Agreement the Contractor confirms that the Contract Time is a reasonable period
for performing the Work.
8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in
writing, prematurely commence operations on the site or elsewhere prior to the effective date of
insurance required by Article 11 to be furnished by the Contractor. The date of commencement
of the Work shall not be changed by the effective date of such insurance.
8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve
Substantial Completion within the Contract Time.
(IPE]WERH)\XIRWMSRWSJ8MQI
8.3.1 If the Contractor is delayed, at any time, in the progress of the Work by any act or
neglect of the Owner, Project Management, or the Architect/Engineer, or by any employee of
either, or by any separate contractor employed by the Owner, or by changes ordered in the
Work, or by fire, unusual delay in transportation, adverse weather conditions not reasonably
authorized by the Owner, Project Management, or by any other cause which Project
Management determines may justify the delay, then the Contract Time shall be extended by no
cost Change Order for such reasonable time as Project Management may determine, in
accordance with subparagraph 6.2.7.
8.3.2 Any claim for extension of time shall be made in writing to Project Management not more
than Seventy-two (72) hours after the commencement of the delay in accordance with
paragraph 6.2.7; otherwise it shall be waived. Any claim for extension of time shall state the
cause of the delay and the number of days of extension requested. If the cause of the delay is
continuing, only one claim is necessary, but the Contractor shall report the termination of the
cause for the delay within seventy-two (72) hours after such termination in accordance with
paragraph 6.2.7; otherwise, any claim for extension of time based upon that cause shall be
waived.
8.3.3 No claim for an increase in the Contract Sum for either acceleration or delay will be
allowed for extensions of time pursuant to this Paragraph 8.3 or for other changes in the
Construction Schedules.
8.3.4
Work on the date of commencement as defined in Paragraph 8.1.2, or his refusal or failure to
carry the Work forward expeditiously with adequate forces, the Contractor causing the delay
shall be liable for, but not limited to, delay claims from other Contractors which are affected.
4%=1)287%2('3140)8-32
'SRXVEGX7YQ
9.1.1 The Contract Sum is stated in the Agreement and, including authorized adjustments, is
the total amount payable by the Owner to the Contractor for performance of the Work under the
Contract Documents.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7GLIHYPISJ:EPYIW
9.2.1 Before submittal of the first Application for Payment, the Contractor shall submit to
Project Management, a schedule of values allocated to various portions of the Work, prepared
in such form and supported by such data to substantiate its accuracy as Project Management
may require. This schedule, unless objected to by Project Management, shall be used as a
%TTPMGEXMSRWJSV4E]QIRX
9.3.1 At least fifteen days before the date established for each progress payment, the
Contractor shall submit to Project Management an itemized Application for Payment for Work
completed in accordance with the schedule of values. Such application shall be notarized and
s right to payment as the Owner or Project
Management may require, such as copies of requisitions from Subcontractors and material
suppliers, and reflecting retainage if provided for elsewhere in the Contract Documents.
.1 Such applications may include request for payment on account of changes in the
Work which have been properly authorized by Construction Change Directives but not yet
included in Change Orders.
.2 Such applications may not include requests for payment of amounts the Contractor
does not intend to pay to a Subcontractor or material supplier because of a dispute or other
reason.
9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on
account of materials and equipment delivered and suitably stored at the site for subsequent
incorporation in the Work. If approved in advance by the Owner, payment may similarly be
made for materials and equipment suitably stored off the site at a location agreed upon in
writing. Payment for materials and equipment stored on or off the site shall be conditioned upon
compliance by the Contractor with procedures satisfactory to the Owner to establish the
shall include applicable insurance, storage and transportation to the site for such materials and
equipment stored off the site.
9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will
pass to the Owner no later than the time of payment. The Contractor further warrants that upon
submittal of an Application for Payment all Work for which approval for payment have been
knowledge, information and belief, be free and clear of liens, claims security interests or
encumbrances in favor of the Contractor, Subcontractors, material suppliers, or other persons or
entities making a claim by reason of having provided labor, materials and equipment relating to
the Work. All Subcontractors and Sub-subcontractors shall execute an agreement stating that
title will so pass, upon their receipt of payment from the Contractor. The warranties are for the
administrative convenience of the Owner only and do not create an obligation on the part of the
Owner to pay directly any unpaid subcontractor, laborer or materialmen. Such persons must
seek payment from the Contractor or his public construction bond surety only.
%TTVSZEPJSV4E]QIRX
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
9.4.1 Project Management will assemble a Project Application for Payment by combining the
similar applications for progress payments from other Contractors
and certify the amounts due on such applications.
9.4.2 After the receipt of the Project Application for Payment, Project
Management will either approve the Application for Payment, with a copy to the Contractor, for
such amount as Project Management determine is properly due, or notify the Contractor in
in Subparagraph 9.5.1.
9.4.3 The issuance of a separate Approval for Payment will constitute representations made
by Project Management to the Owner, based on their individual observations at the site and the
data comprising the Application for Payment submitted by the Contractor, that the Work has
progressed to the point indicated and that, to the best of Project ,
information and belief, quality of the Work is in accordance with the Contract Documents. The
foregoing representations are subject to an evaluation of the Work for conformance with the
Contract Documents upon Substantial Completion, to results of subsequent tests and
inspections, to minor deviations from the Contract Documents correctable prior to completion
and to specific qualifications expressed by Project Management. The issuance of a separate
Approval for Payment will further constitute a representation that the Contractor is entitled to
payment in the amount approved. However, the issuance of a separate Approval for Payment
will not be a representation that Project Management has (1) made exhaustive or continuous
on-
construction means, methods, techniques, sequences or procedures, (3) reviewed copies of
requisitions received from Subcontractors and material suppliers and other data requested by
ascertain how or for what purpose the Contractor has used money previously paid on account of
the Contract Sum.
(IGMWMSRWXS;MXLLSPH%TTVSZEP
9.5.1 Project Management may decline to approve an Application for Payment if, in his
opinion, the application is not adequately supported. If the Contractor and Project Management
cannot agree on a revised amount, Project Management shall process the Application for the
amount it deems appropriate. Project Management may also decline to approve any
Application for Payment because of subsequently discovered evidence or subsequent
inspections. It may nullify, in whole or part, any approval previously made to such extent as may
be necessary in its opinion because of: (1) defective Work not remedied; (2) third party claims
filed or reasonable evidence indicating probable filing of such claims; (3) failure of the
Contractor to make payments properly to Subcontractors or for labor, materials, or equipment;
(4) reasonable evidence that the Work cannot be completed for the unpaid balance of the
Contract Sum; (5) damage to Project Management, the Owner, or another contractor working at
the project; (6) reasonable evidence that the Work will not be completed within the contract
time; (7) persistent failure to carry out the Work in accordance with the Contract Documents.
No payment shall be made to the Contractor until certificates of insurance or other evidence of
compliance by the Contractor, with all the requirements of Article 11, have been filed with the
Owner and Project Management.
9.5.2 When the above reasons for withholding approval are removed, approval will be made
for amounts previously withheld.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
4VSKVIWW4E]QIRXW
9.6.1 After Project Management has issued an Approval for Payment, the Owner shall make
payment in the manner and within the time provided in the Contract Documents, and shall so
notify Project Management. From the total of the amount determined to be payable on a
progress payment, a retainage in accordance with the Florida Local Government Prompt
Payment Act, Chapter 218, Florida Statutes will be deducted and retained by the Owner until
the final payment is made. The balance of the amount payable, less all previous payments, shall
be approved for payment.
.1 It is understood and agreed that the Contractor shall not be entitled to demand or
receive progress payment based on quantities of Work in excess of those provided in the
proposal or covered by approved change orders, except when such excess quantities have
been determined by Project Management to be a part of the final quantity for the item of Work in
question.
.2 No progress payment shall bind the Owner to the acceptance of any materials or
Work in place, as to quality or quantity. All progress payments are subject to correction at the
time of final payments.
9.6.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the
s portion of
the Work, the amount to which said Subcontractor is entitled, reflecting percentages actually
Work. The Contractor shall, by appropriate agreement with each Subcontractor, require each
Subcontractor to make payments to Sub-subcontractors in similar manner.
9.6.3 Project Management will, on request, furnish to a Subcontractor, if practicable,
information regarding percentages of completion or amounts applied for by the Contractor and
action taken thereon by the Owner and Project Management on account of portions of the Work
done by such Subcontractor.
9.6.4 Neither the Owner nor Project Management shall have an obligation to pay, or to see to,
the payment of money to a Subcontractor except as may otherwise be required by law.
9.6.5 Payment to material suppliers shall be treated in a manner similar to that provided in
Subparagraphs 9.6.2, 9.6.3 and 9.6.4.
9.6.6 A progress payment, or partial or entire use or occupancy of the Project by the Owner
shall not constitute acceptance of Work not in accordance with the Contract Documents.
9.6.7 All material and work covered by partial payments made shall thereupon become the
sole property of the Owner, and by this provision shall not be construed as relieving the
Contractor from the sole responsibility for the materials and Work upon which payments have
been made or the restoration for any damaged material, or as a waiver of the right of the Owner
or Project Management to require the fulfillment of all the terms of the Contract.
9.6.8 Except in case of bona fide disputes, or where the Contractor has some other justifiable
reason for delay, the Contractor shall pay for all transportation and utility services not later than
the end of the calendar month following that in which services are rendered and for all materials,
tools, and other expendable equipment which are delivered at the site of the Project. The
Contractor shall pay to each of his Subcontractors, not later than the end of the calendar month
in which each payment is made to the Contractor, the representative amount allowed the
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Contractor on account of the Work performed by the Subcontractor. The Contractor shall, by an
appropriate agreement with each Subcontractor, also require each Subcontractor to make
payments to his suppliers and Sub-subcontractors in a similar manner.
7YFWXERXMEP'SQTPIXMSR
9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or
designated portion thereof is sufficiently complete in accordance with the Contract Documents
so the Owner can occupy or utilize the Work for its intended use.
9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner
agrees to accept separately, is substantially complete, the Contractor and Project Management
shall jointly prepare a comprehensive list of items to be completed or corrected. The Contractor
shall proceed promptly to complete and correct items on the list. Failure to include an item on
such list does not alter the responsibility of the Contractor to complete all Work in accordance
with the Contract Documents. Upon receipt of the list, Project Management will make an
inspection to determine whether the Work or designated portion thereof is substantially
complete. If the inspection discloses any item, whether or not included on the list, which is not
in accordance with the requirements of the Contract Documents, the Contractor shall, before
issuance of the Certificate of Substantial Completion, complete or correct such item upon
notification by Project Management. The Contractor shall then submit a request for another
inspection by Project Management, to determine Substantial Completion. When the Work or
designated portion thereof is substantially complete, Project Management will prepare a
Certificate of Substantial Completion, shall establish responsibilities of the Owner and
Contractor for security, maintenance, heat, utilities, damage to the Work and insurance, and
shall fix the time within which the Contractor shall finish all items on the list accompanying the
Certificate. Warranties required by the Contract Documents shall commence on the date of
Substantial Completion of the Work or designated portion thereof unless otherwise provided in
the Certificate of Substantial Completion. The Certificate of Substantial Completion shall be
submitted to the Owner and Contractor for their written acceptance of responsibilities assigned
to them in such Certificate.
9.8.3 Upon Substantial Completion of the Work or designated portion thereof and upon
application by the Contractor and certification by Project Management, the Owner shall make
payment, reflecting adjustment in retainage, if any, for such Work or portion thereof as provided
in the Contract Documents.
4EVXMEP3GGYTERG]SV9WI
9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work
at any stage when such portion is designated by separate agreement with the Contractor,
provided such occupancy or use is consented to by the insurer as required under Subparagraph
11.3.1 and authorized by public authorities having jurisdiction over the Work. Such partial
occupancy or use may commence whether or not the portion is substantially complete, provided
the Owner and Contractor have accepted in writing the responsibilities assigned to each of them
for payments, retainage if any, security, maintenance, heat, utilities, damage to the Work and
insurance, and have agreed in writing concerning the period for correction of the Work and
commencement of warranties required by the Contract Documents. When the Contractor
considers a portion substantially complete, the Contractor and Project Management shall jointly
prepare a list as provided under Subparagraph 9.8.2. Consent of the Contractor to partial
occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
shall be determined by written agreement between the Owner and Contractor or, if no
agreement is reached, by decision of Project Management.
9.9.2 Immediately prior to such partial occupancy or use, the Owner, Project Management and
Contractor shall jointly inspect the area to be occupied or portion of the Work to be used in order
to determine and record the condition of the Work.
9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the
Work shall not constitute acceptance of Work not complying with the requirements of the
Contract Documents.
*MREP'SQTPIXMSRERH*MREP4E]QIRX
9.10.1 Upon completion of the Work, the Contractor shall forward to Project Management a
written Notice that the Work is ready for final inspection and acceptance and shall also forward
t, Project
Management will promptly make such inspection. When Project Management, finds the Work
acceptable under the Contract Documents and the Contract fully performed, Project
Management will promptly issue a final Approval for Payment stating that to the best of their
knowledge, information and belief, and on the basis of their observations and inspections, the
Work has been completed in accordance with terms and conditions of the Contract Documents
and that the entire balance found to be due the Contractor and noted in said final Approval is
being entitled to final payment have been fulfilled.
9.10.2 Neither final payment nor any remaining retained percentage shall become due until the
Contractor submits to Project Management (1) an affidavit that payrolls, bills for materials and
equipment, and other indebtedness connected with the Work for which the Owner or the
been paid or otherwise satisfied, (2) a certificate evidencing that insurance required by the
Contract Documents to remain in force after final payment is made, is currently in effect and will
the Owner, (3) a written statement that the Contractor knows of no substantial reason that the
insurance will not be renewable to cover the period required by the Contract Documents, (4)
consent of surety, if any, to final payment and (5), if required by the Owner, other data
establishing payment or satisfaction of obligations, such as receipts, releases and waivers of
liens, claims, security interests or encumbrances arising out of the Contract. The following
documents (samples included in section 1027) are required for Final Payment:
(1) Application and Certificate for Payment
(2) Continuation Sheet
(3) Certificate of Substantial Completion
(4)
(5)
(6) Final Release of Lien
(7) Contractor shall provide two (2) hard copies in tabulated divided binders and
one (1) saved electronically tabbed and indexed in Adobe Acrobat file (.PDF)
format delivered on a downloadable CD/DVD of all the following but not limited
to:
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A .Project Record Documents (As Built Documents).
B. Operating and maintenance data, instructions to the Owner's personnel.
C. Warranties, bond and guarantees.
D. Keys and keying schedule.
E. Spare parts and maintenance materials.
F.Electronic copies of approved submittals
G. Evidence of payment and final release of liens and consent of surety to final release
(includes final release from all utilities and utility companies).
9.10.3 Acceptance of final payment by the Contractor, a Subcontractor or material supplier shall
constitute a waiver of claims by that payee except those previously made in writing and
identified by that payee as unsettled at the time of final Application for Payment. Such waivers
shall be in addition to the waiver described Subparagraph 4.7.5.
4E]QIRXSJ7YFGSRXVEGXSVW
9.11.1 Any requirement of this Article 9 that the Contractor furnish proof to the Owner or Project
Management that the subcontractors and materialmen have been paid is for the protection and
convenience of the Owner only. Unpaid subcontractors and materialmen may only seek
8LI'SRXVEGXSVQYWXMRWIVXXLMWTEVEKVETLMREPPMXWGSRXVEGXW[MXL
Bond.
WYFGSRXVEGXSVWERHQEXIVMEPQIR
4638)'8-323*4)67327%2(4634)68=
7EJIX]4VIGEYXMSRWERH4VSKVEQW
10.1.1 The Contractor shall be responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the performance of the Contract. The Contractor
afety program to Project Management for review, approvaland
coordination with the safety programs of other Contractors.
10.1.2 In the event the Contractor encounters on the site material reasonably believed to be
asbestos or polychlorinated biphenyl (PCB) which has not been rendered harmless, the
Contractor shall immediately stop Work in the area affected and report the condition to the
Owner and Project Management in writing. The Work in the affected area shall not thereafter
be resumed except by written agreement of the Owner and Contractor if in fact the material is
asbestos or polychlorinated biphenyl (PCB) and has not been rendered harmless. The Work in
the affected area shall be resumed in the absence of asbestos or polychlorinated biphenyl
(PCB), or when it has been rendered harmless, by written agreement of the Owner and
Contractor.
10.1.3 The Contractor shall not be required pursuant to Article 7 to perform without consent any
Work relating to asbestos or polychlorinated biphenyl (PCB).
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
10.1.5 If reasonable precautions will be inadequate to prevent foreseeable bodily injury or death
to persons resulting from a material or substance encountered on the site by the Contractor, the
Contractor shall, upon recognizing the condition, immediately stop Work in the affected area
and report the condition to Project Management in writing. The Owner, Contractor and Project
Management shall then proceed in the same manner described in Subparagraph 10.1.2.
10.1.6 The Owner shall be responsible for obtaining the services of a licensed laboratory to
verify a presence or absence of the material or substance reported by the Contractor and, in the
event such material or substance is found to be present, to verify that it has been rendered
harmless. Unless otherwise required by the Contract Documents, the Owner shall furnish in
writing to the Contractor and Project Management the names and qualifications of persons or
entities who are to perform tests verifying the presence or absence of such material or
substance or who are to perform the task of removal or safe containment of such material or
substance. The Contractor and Project Management will promptly reply to the Owner in writing
stating whether or not any of them has reasonable objection to the persons or entities proposed
by the Owner. If the Contractor or Project Management has an objection to a person or entity
proposed by the Owner, the Owner shall propose another to whom the Contractor and Project
Management have no reasonable objection.
7EJIX]SJ4IVWSRWERH4VSTIVX]
10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide
reasonable protection to prevent damage, injury or loss to:
.1 employees on the Work and other persons who may be affected thereby;
.2 the Work and materials and equipment to be incorporated therein, whether in storage
Subcontractors or Sub-subcontractors;
.3 other property at the site or adjacent thereto, such as trees, shrubs, lawns, walks,
pavements, roadways, structures and utilities not designated for removal, relocation or
replacement in the course of construction; and
.4 construction or operations by the Owner or other Contractors.
10.2.2 The Contractor shall give notices and comply with applicable laws, ordinances, rules,
regulations and lawful orders of public authorities bearing on safety of persons or property or
their protection from damage, injury or loss.
10.2.3 The Contractor shall erect and maintain, as required by existing conditions and
performance of the Contract, reasonable safeguards for safety and protection, including posting
danger signs and other warnings against hazards, promulgating safety regulations and notifying
owners and users of adjacent sites and utilities.
10.2.4 When use or storage of explosives or other hazardous materials or equipment or
unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost
care and carry on such activities under supervision of properly qualified personnel.
10.2.5 The Contractor shall promptly remedy damage and loss to property referred to in
Clauses 10.2.1.2, 10.2.1.3, 10.2.1.4 caused in whole or in part by the Contractor, a
Subcontractor, a Sub-subcontractor, or anyone directly or indirectly employed by any of them, or
by anyone for whose acts they may be liable and for which the Contractor is responsible under
Clauses 10.2.1.2, 10.2.1.3 and 10.2.1.4, except damage or loss attributable to acts or omissions
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
of the Owner, Project Management or Architect or anyone directly or indirectly employed by any
of them, or by anyone for whose acts any of them may be liable, and not attributable to the fault
or negligence of the Contractor. The foregoing obligations of the Contractor are in addition to
10.2.6
the site whose duty shall be the prevention of accidents. This person shall be
superintendent unless otherwise designated by the Contractor in writing to the Owner orProject
Management.
10.2.7 The Contractor shall not load or permit any part of the construction or site to be loaded
so as to endanger its safety.
)QIVKIRGMIW
10.3.1 In an emergency affecting safety of persons or property, the Contractor shall act, at the
or extension of time claimed by the Contractor on account of an emergency shall be determined
as provided in Paragraph 4.7 and Article 7.
7MXI7TIGMJMG7EJIX]4PER
See Section 00970 for minimum requirements of job site safety plan.
-2796%2')%2(&32(7
11.1.1 Prior to commencement of Work governed by this contract (including the pre-staging of
personnel and material), the Contractor shall obtain, at its own expense, insurance as specified
in the schedule set forth in Section 00110 Bid Form which are made part of this Agreement.
The Contractor will ensure that the insurance obtained will extend protection to all
subcontractors engaged by the Contractor. As an alternative the Contractor may require all
subcontractors to obtain insurance consistent with the attached schedules.
11.1.2 The Contractor will not be permitted to commence Work governed by the Agreement
(including pre-staging of personnel and material) until satisfactory evidence of the required
insurance has been furnished to the County as specified below. Delays in the commencement
of Work resulting from the failure of the Contractor to provide satisfactory evidence of the
required insurance shall not extend deadlines specified in this Agreement and any penalties and
failure to perform assessments shall be imposed as if the Work commenced on the specified
11.1.3 The Contractor shall maintain the required insurance throughout the entire term of this
contract and any extensions specified in any attached schedules. Failure to comply with this
provision may result in the immediate suspension of all Work until the required insurance has
been reinstated or replaced. Delays in the completion of Work resulting from the failure of the
Contractor to maintain the required insurance shall not extend deadlines specified in this
Agreement and any penalties and failure to perform assessments shall be imposed as if the
provide
satisfactory evidence of insurance.
11.1.4 The Contractor shall provide, to the County in care of Project Management as
satisfactory evidence of the required insurance, either:
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Certificate of Insurance
Or
A certified copy of the actual insurance policy
11.1.5 The County, at its sole option, has the right to request a certified copy of any or all
insurance policies required by this Contract.
11.1.6 All insurance policies must specify that they are not subject to cancellation, nonrenewal,
material change, or reduction in coverage unless a minimum of thirty (30) days prior notification
is given to the County by the insurer.
11.1.7
relieving the Contractor from any liability or obligation assumed under this contract or imposed
by law.
11.1.8 The Monroe County Board of County Commissioners, its employees and officials will be
11.1.9 In addition, the County will be named as an additional insured and loss payee on all
policies covering County-owned property.
11.1.10 Any deviations from these General Insurance Requirements must be requested in
writing on the County prepared form
11.2 Not Required
11.3 Public Construction Bond
11.3.1 A Public Construction Bond in the amount of the cost of construction may be a
requirement of this Contract as determined by the Director of Project Management. Bond must
be issued by an A rated surety company doing business in the State of Florida.
92'3:)6-2+%2('366)'8-323*;36/
9RGSZIVMRKSJ;SVO
12.1.1
requirements specifically expressed in the Contract Documents, it must, if required in writing by
Project Management, be uncovered for their observation and be repla
expense without change in the Contract Time.
12.1.2 If a portion of the Work has been covered which Project Management has not
specifically requested to observe prior to its being covered, Project Management may request to
see such Work and it shall be uncovered by the Contractor, if such Work is in accordance with
the Contract Documents, costs of uncovering and replacement shall, by appropriate Change
Order, be charged to the Owner, if such Work is not in accordance with the Contract
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Documents, the Contractor shall pay such costs unless the condition was caused by the Owner
or one of the other Contractors in which event the Owner shall be responsible for payment of
such costs.
'SVVIGXMSRSJ;SVO
12.2.1 The Contractor shall promptly correct Work rejected by Project Management or failing to
conform to the requirements of the Contract Documents, whether observed before or after
Substantial Completion and whether or not fabricated, installed or completed. The Contractor
shall bear costs of correcting such rejected Work, including additional testing and inspections
12.2.2 If, within one year after the date of Substantial Completion of the Work or designated
portion thereof, or after the date for commencement of warranties established under
Subparagraph 9.9, or by terms of an applicable special warranty required by the Contract
Documents, any of the Work is found to be not in accordance with the requirements of the
Contract Documents, the Contractor shall correct it promptly after receipt of written notice from
the Owner to do so unless the Owner has previously given the Contractor a written acceptance
of such condition. This period of one year shall be extended with respect to portions of Work
first performed after Substantial Completion by the period of time between Substantial
Completion and the actual performance of the Work. This obligation under this Subparagraph
12.2.2 shall survive acceptance of the Work under the Contract and termination of the Contract.
The Owner shall give such notice promptly after discovery of the condition.
12.2.3 The Contractor shall remove from the site portions of the Work which are not in
accordance with the requirements of the Contract Documents and are neither corrected by the
Contractor nor accepted by the Owner.
12.2.4 If the Contractor fails to correct nonconforming Work within a reasonable time, the
Owner may correct it in accordance with Paragraph 2.4. If the Contractor does not proceed with
correction of such nonconforming Work within a reasonable time fixed by written notice from
Project Management, the Owner may remove it and store the salvageable materials or
Contractor does not pay costs of such removal
notice sell such materials and equipment at auction or at private sale and shall account for the
proceeds thereof, after deducting costs and damages that should have been borne by the
necessary thereby. If such proceeds of sale do not cover costs which the Contractor should
have borne, the Contract Sum shall be reduced by the deficiency. If payments then or
thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay
the difference to the Owner.
12.2.5 The Contractor shall bear the cost of correcting destroyed or damaged construction,
whether completed or partially completed, of the Owner or other Contractors caused by the
the Contract Documents.
12.2.6 Nothing contained in this Paragraph 12.2 shall be construed to establish a period of
limitation with respect to other obligations which the Contractor might have under the Contract
Documents. Establishment of the time period of one year as described in Subparagraph 12.2.2,
relates only to the specific obligation of the Contractor to correct the Work, and has no
relationship to the time within which the obligation to comply with the Contract Documents may
be sought to be enforced, nor to the time within which proceedings may be commenced to
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
specifically to correct the Work.
%GGITXERGISJ2SRGSRJSVQMRK;SVO
12.3.1 If the Owner prefers to accept Work which is not in accordance with the requirements of
the Contract Documents, the Owner may do so instead of requiring its removal and correction,
in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment
shall be effected whether or not final payment has been made.
1-7')00%2)397463:-7-327
13.0
+SZIVRMRK0E[
13.1.1 The contract shall be governed by the laws of the State of Florida. Venue for any claims
or disputes arising under this contract shall be in the Circuit Court of the 16th Judicial Circuit of
the State of Florida.
7YGGIWWSVWERH%WWMKRW
13.2.1 The Owner or Project Management (as the case may be) and the Contractor each binds
himself, his partners, successors, assigns, and legal representatives of such other party in
respect to all covenants, agreements, and obligations contained in the Contract Documents.
Neither party to the Contract shall assign the Contract or sublet it as a whole without the written
consent of the other.
13.2.2 The Contractor shall not assign any monies due or to become due under this Contract
without prior written consent of the Owner or Project Management.
;VMXXIR2SXMGI
13.3.1 Any written notices or correspondence given pursuant to this contract shall be sent by
United States Mail, certified, return receipt requested, or by courier with proof of delivery.Notice
shall be sent to the following persons:
For Contractor: ________________________________
________________________________
________________________________
________________________________
For Owner: Director of Project Management Assistant County Administrator, PW & E
1100 Simonton St., Room 2-216 1100 Simonton St.
Key West, Florida 33040 Key West, Florida 33040
6MKLXWERH6IQIHMIW
13.4.1 Duties and obligations imposed by the Contract Documents and rights and remedies
available thereunder shall be in addition to and not a limitation of duties, obligations, rights and
remedies otherwise imposed or available by law.
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
13.4.2 No action or failure to act by the Owner, Project Management, Architect or Contractor
shall constitute a waiver of a right or duty afforded them under the contract, nor shall such
action or failure to act constitute approval of or acquiescence in a breach thereunder, except as
may be specifically agreed in writing.
8IWXWERH-RWTIGXMSRW
13.5.1 Tests, inspections and approvals of portions of the Work required by the Contract
Documents or by laws, ordinances, rules, regulations or orders of public authorities having
jurisdiction shall be made at an appropriate time. Unless otherwise provided, the Contractor
shall make arrangements for such tests, inspections and approvals with an independent testing
laboratory or entity acceptable to the Owner, or with the appropriate public authority, and shall
bear all related costs of tests, inspections and approvals. The Contractor shall give Project
Management timely notice of when and where tests and inspections are to be made so Project
Management may observe such procedures. The Owner shall bear costs of test, inspections or
approvals which do not become requirements until after bids are received or negotiations
concluded.
13.5.2 If Project Management, Owner or public authorities having jurisdiction determine that
portions of the Work require additional testing, inspection or approval not included under
Subparagraph 13.5.1, Project Management will, upon written authorization from the Owner,
instruct the Contractor to make arrangements for such additional testing, inspection or approval
by an entity acceptable to the Owner, and the Contractor shall give timely notice to Project
Management of when and where tests and inspections are to be made so Project Management
may observe such procedures. The Owner shall bear such costs except as provided in
Subparagraph 13.5.3.
13.5.3 If such procedures for testing, inspection or approval under Subparagraphs 13.5.1 and
13.5.2 reveal failure of the portions of the Work to comply with requirements established by the
Contract Documents, the Contractor shall bear all costs made necessary by such failure
including those of repeated procedures and compensation
and expenses.
13.5.4 Required certificates of testing, inspection or approval shall, unless otherwise required
by the Contract Documents, be secured by the Contractor and promptly delivered to Project
Management.
13.5.5 If Project Management is to observe tests, inspections or approvals required by the
Contract Documents, Project Management will do so promptly and, where practicable, at the
normal place of testing.
13.5.6 Test or inspections conducted pursuant to the Contract Documents shall be made
promptly to avoid unreasonable delay in the Work.
'SQQIRGIQIRXSJ7XEXYXSV]0MQMXEXMSR4IVMSH
13.7.1 The statute of limitations applicable to this contact are as provided in Section 95.11 (3)
(C), Florida Statutes.
8)61-2%8-32367974)27-323*8,)'3286%'8
8IVQMREXMSRF]XLI3[RIVJSV'EYWI
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
14.1.1 The Owner may terminate the Contract if the Contractor:
.1 persistently or repeatedly refuses or fails to supply enough properly skilled workers or
proper materials;
.2 fails to make payment to Subcontractors for materials or labor in accordance with the
respective agreements between the Contractor and the Subcontractors;
.3 persistently disregards laws, ordinances, or rules, regulations or orders of a public
authority having jurisdiction;
.or
.4 Otherwise is guilty of substantial breach of a provision of the Contract Documents.
14.1.2 When any of the above reasons exist, the Owner, after consultation with Project
Management, and upon certification by Project Management that sufficient cause exists to
justify such action, may without prejudice to any other rights or remedies of the Owner and after
employment of the Contractor and may, subject to any prior rights of the surety:
.1 take possession of the site and of all materials, equipment, tools, and construction
equipment and machinery thereon owned by the Contractor;
.2 accept assignment of subcontracts pursuant to Paragraph 5.4; and
.3 finish the Work by whatever reasonable method the Owner may deem expedient.
14.1.3 When the Owner terminates the Contract for one of the reasons stated in Subparagraph
14.1.1, the Contractor shall not be entitled to receive further payment until the Work is finished.
7YWTIRWMSRSV8IVQMREXMSRF]XLI3[RIVJSV'SRZIRMIRGI
14.2.1 The Owner may, without cause, order the Contractor in writing to terminate, suspend,
delay or interrupt the Work in whole or in part for such period of time as the Owner may
determine.
14.2.2 In the event of Termination the Owner shall pay for work completed to date of
Termination.
End of Section 00750
GENERAL CONDITIONS 00750-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463.)'87%*)8=%2(,)%08,40%2
REGULATIONS AND POLICIES
A. Every Contractor and Subcontractor employed on the Project shall comply with all
applicable local, State, and Federal safety and health regulations and with Monroe County
safety and health policies as described herein.
The Contractor shall comply with OSHA (Occupational Safety and Health Administration) Parts
1910 and 1926, Construction Industry Standards and Interpretations, and with this supplement.
Requests for variances or waiver from this supplement are to be made to the Contracting Officer
in writing supported by evidence that every reasonable effort has been made to comply with the
contractual requirements. A written request for a waiver or a variance shall include--
(1) Specific reference to the provision or standard in question;
(2) An explanation as to why the waiver is considered justified; and
(3) The Contractor's proposed alternative, including technical drawings, materials, or equipment
specifications needed to enable the Contracting Officer to render a decision.
No waiver or variance will be approved if it endangers any person. The Contractor shall not
proceed under any requested revision of provision until the Contracting Officer has given written
approval. The Contractor is to hold and save harmless Monroe county Florida free from any
claims or causes of action whatsoever resulting from the Contractor or subcontractors
proceeding under a waiver or approved variance.
Copies of OSHA Parts 1910 and 1926, Construction Industry Standards and Interpretations,
may be obtained from:
U.S. Government Printing Office Bookstore
710 North Capitol Street N.W.
Washington, DC
http://www.gpo.gov/about/bookstore.htm
GENERAL CONTRACTOR REQUIREMENTS
7%*)8=463+6%1
Each Contractor and sub-contractor is to demonstrate that he or she has facilities for conducting
a safety program commensurate with the work under contract. The Contractor is to submit in
writing a proposed comprehensive site specific safety program for approval to the Contracting
Officer for Monroe County before the start of construction operations.
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The program is to specifically state what provisions the Contractor proposes to take for the
health and safety of all employees, including subcontractors and rental equipment operators.
The program shall be site specific and provide details relevant to the work to be done, the
hazards associated with the work, and the actions that will be necessary to minimize the
identified hazards.
The Safety Program will also be required to provide emergency contact person, emergency
planning and a personnel evacuation plan for any hurricane evacuation event.
1.2 PRECONSTRUCTION SAFETY MEETING
Representatives for the Contractor are to meet with the Contracting Officer (CO) or the CO's
representative before the start of construction to discuss the safety program and the
implementation of all health and safety standards pertinent to the work under this contract.
1.3 JOINT SAFETY POLICY COMMITTEE
The Contractor or designated on-site representative is to participate in monthly meetings of a
joint Safety Policy Committee with Monroe County Project Management and Contractor
supervisory personnel. At these meetings the Contractor's project manager and the Contracting
Officer will review the effectiveness of the Contractor's safety effort, resolve current health and
safety problems, and coordinate safety activities for upcoming work.
1.4 SAFETY PERSONNEL
Each Contractor is to designate a competent supervisory employee satisfactoryto the
Contracting Officer to administer the safety program.
The Mandatory Safety and Health Rules shall be posted in a conspicuous location along with
the OSHA and Emergency Phone Number posters.
1.5 SAFETY MEETINGS
A minimum of one "on-the-job" or "toolbox" safety meeting is to be conducted each week by all
field supervisors or foremen and attended by mechanics and all construction personnel at the
jobsite.
The Contractor is to also conduct regularly scheduled supervisory safety meetings at least
monthly for all levels of job supervision.
Each Contractor and Subcontractor shall be expected to indoctrinate his employees as to the
safety and health requirements of this project and to enforce adherence to safe work
procedures.
Each Contractor and Subcontractor shall cooperate fully with all other contractors in their
respective safety and health programs.
1.6 SAFETY INSPECTION
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The Contractor shall perform frequent and regular safety inspections of the jobsite, materials,
and equipment, and shall correct deficiencies.
Good housekeeping shall be observed at all times. Waste, debris, and garbage shall be
removed daily or placed in appropriate waste containers. All materials, tools, and equipment
shall be stored in a safe and orderly fashion. Each contractor shall donate 10% of their staff to
a crew that will convene every Friday at 1:00 pm for a joint site clean-up effort not to exceed
duration of three hours.
In summary, there will be a three-part clean-up plan.
1. The first part consists of the contractor cleaning up on a daily basis, his workstations, and
his trade work.
2. The second part consists of the general clean-up, the concerted effort by all trade
contractors working on the project. A minimum of one (1) crew is to be utilized by each
contractor, or 10%, whichever is more.
3. The third part consists of the Owner cleaning up for a particular trade contractor should
adequate notice not compel him to clean up his work. In this case, the appropriate
contractors will be back charged.
Shortly after the award of the contract and prior to the beginning of work, an Activity Hazard
Analysis (phase plan) shall be prepared by the contractor and submitted to Monroe County for
approval. The analysis will address the hazards for each activity to be performed in that phase
and will present the procedures and safeguards necessary to eliminate the hazards or reduce
the risk to an acceptable level. A phase is defined as an operation involving a type of work
presenting hazards not experienced in previous operations or where a new subcontractor or
work crew is to perform work. The analysis will be discussed by the contractor and Monroe
County on-site representatives at the Preparatory Inspection Meeting. Work will not proceed on
that phase until the Activity Hazard Analysis (phase plan) has been accepted by Monroe
County.
If Monroe County notifies any Contractor of any noncompliance with the provisions of this
program, the Contractor shall make all reasonable efforts to immediately correct the unsafe
conditions or acts. Satisfactory corrective action shall be taken within the specified time. If the
Contractor or Subcontractor refuses to correct unsafe or unhealthy conditions or acts, Monroe
County shall take one or more of the following steps:
a. Cease the operation or a portion thereof.
b. Stop payment for the work being performed.
c. Correct the situation using other forces and back charge the Contractor expenses
incurred.
d. Increase withholding in proportional increments for that given pay period.
1.7 FIRST AID TRAINING
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Every Contractor foreman's work crew must include an employee who has a current first aid
certificate from the, American Red Cross, or other Monroe County-approved organization.
1.8 REPORTS
Each Contractor is to maintain an accurate record of all job-related deaths, diseases, or
disabling injuries. The records shall be maintained in a manner approved by the Contracting
Officer. A copy of all reports is to be provided to the Contracting Officer.
All fatal or serious injuries are to be reported immediately to the Contracting Officer, and every
assistance is to be given in the investigation of the incident, including submission of a
comprehensive narrative report to the Contracting Officer. Other occurrences with serious
accident potential, such as equipment failures, slides, and cave-ins, must also be reported
immediately.
The Contractor is to assist and cooperate fully with the Contracting Officer in conducting
accident investigations. The Contracting Officer is to be furnished all information and data
pertinent to investigation of an accident.
1.9 CERTIFICATION OF INSURANCE
Contractors are to provide the Contracting Officer or his or her authorized representative with
certificates of insurance before the start of operations indicating full compliance with State
Worker's Compensation statutes, as well as other certificates of insurance required under the
contract.
*-678%-(%2(1)(-'%0*%'-0-8-)7
2.1 FIRST AID KITS
A 16-unit first aid kit approved by the American Red Cross is to be provided at accessible, well-
identified, locations at the ratio of at least 1 kit for each 25 employees. The first aid kits are to be
moisture proof and dust tight, and the contents of the kits are to be replenished as used or as
they become ineffective or outdated.
2.2 EMERGENCY FIRST AID
At least one employee certified to administer emergency first aid must be available on each shift
and duly designated by the Contractor to care for injured employees. The names of the certified
employees shall be posted at the jobsite.
2.4 COMMUNICATION AND TRANSPORTATION
Prior to the start of work, the Contractor is to make necessary arrangements for prompt and
dependable communications, transportation, and medical care for injured employees.
2.5 FIRST AID AND MEDICAL REPORTS
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The Contractor is to maintain a record system for first aid and medical treatment on the jobsite.
Such records are to be readily available to the Contracting Officer and are to include--
(a) A daily treatment log listing chronologically all persons treated for occupational injuries and
illnesses;
(b) Cumulative record of injury for each individual;
(c) Monthly statistical records of occupational injuries, classified by type and nature of injury;
and
(d) Required records for worker's compensation.
2.5 SIGNS AND DIRECTIONAL MARKINGS
Adequate identification and directional markers are to be provided to readily denote the location
of all first aid stations.
2.6 EMERGENCY LISTING
A listing of telephone numbers and addresses of doctor, rescue squad, hospital, police, and fire
departments is to be provided at all first aid locations.
4,=7-'%059%0-*-'%8-3273*)1403=))7
3.1 GENERAL REQUIREMENTS
Persons employed throughout the contract are to be physically qualified to perform their
assigned duties. Employees must not knowingly be permitted or required to work while their
ability or alertness is impaired by fatigue, illness, or any other reason that may jeopardize
themselves or others.
2STIVWSREPVEHMSWSVWXIVISW
will be allowed on the job-site.
3.2 HOIST OPERATORS
Operators of cranes, cableways, and other hoisting equipment shall be examined annually by a
physician and provided with a certification stating that they are physically qualified to safely
operate hoisting equipment. The Contractor is to submit a copy of each certification to the
Contracting Officer.
3.3 HEAVY EQUIPMENT OPERATORS
It is recommended that operators of trucks and heavy construction equipment be given physical
examinations to determine if they are physically qualified to perform their assigned work without
endangering themselves or others.
3.4 MOTOR VEHICLE OPERATORS
Operators of motor vehicles engaged primarily in the transportation of personnel are to be 18
years of age or older and have a valid state operator's permit or license for the equipment being
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
operated. The operators must have passed a physical examination administered by a licensed
physician within the past year showing that they are physically qualified to operate vehicles
safely.
4)6732%04638)'8-:))59-41)28
4.1 HARDHAT AREAS
The entire jobsite, with the exception of offices, shall be considered a hardhat area. All persons
entering the area are, without exception, required to wear hardhats. The Contractor shall
provide hardhats for visitors entering hardhat areas.
4.1.1 LABELS
Hardhats shall bear a manufacturer's label indicating design compliance with the appropriate
ANSI (American National Standards Institute) standard.
4.2 POSTING
Signs at least 3 by 4 feet worded as follows with red letters (minimum 6 inches high) and white
background shall be erected at access points to designated hardhat areas:
'327869'8-32%6)%,%6(,%876)59-6)(&)=32(8,-743-28
These signs are to be furnished and installed by the Contractor at entries to shops, construction
yards, and job access points.
4.3 SAFETY GOGGLES (DRILLERS)
4.3.1 DRILLERS AND HELPERS.
Drillers and helpers operating pneumatic rock drills/concrete saws must wear protective safety
goggles.
1%',-2)6=%2(1)',%2->)()59-41)28
5.1 SAFE CONDITION
Before any machinery or mechanized equipment is initially used on the job, it must be inspected
and tested by qualified personnel and determined to be in safe operating condition and
appropriate for the intended use. Operators shall inspect their equipment prior to the beginning
of each shift. Any deficiencies or defects shall be corrected prior to using the equipment. Safety
equipment, such as seatbelts, installed on machinery is to be used by equipment operators.
5.2 TAGGING AND LOCKING
The controls of power-driven equipment under repair are to be locked. An effective lockout and
tagging procedure is to be established, prescribing specific responsibilities and safety
procedures to be followed by the person or persons performing repair work. Mixer barrels are to
be securely locked out before permitting employees to enter them for cleaning or repair.
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
5.3 HAUL ROADS FOR EQUIPMENT
5.3.1 ROAD MAINTENANCE
The Contractor shall maintain all roadways, including haul roads and access roads, in a safe
condition so as to eliminate or control dust and ice hazards. Wherever dust is a hazard,
adequate dust-laying equipment shall be available at the jobsite and utilized to control the dust.
5.3.2 SINGLE-LANE HAUL ROADS
Single-lane haul roads with two-way traffic shall have adequate turnouts. Where turnouts are
not practical, a traffic control system shall be provided to prevent accidents.
5.3.3 TWO-WAY HAUL ROADS
On two-way haul roads, arrangements are to be such that vehicles travel on the right side
wherever possible. Signs and traffic control devices are to be employed to indicate clearly any
variations from a right-hand traffic pattern. The road shall be wide enough to permit safe
passage of opposing traffic, considering the type of hauling equipment used.
5.3.4 DESIGN AND CONSTRUCTION OF HAUL ROADS
Haul road design criteria and drawings, if requested by the Contracting Officer, are to be
submitted for approval prior to road construction. Sustained grades shall not exceed 12 percent
and all curves shall have open-sight line with as great a radius as practical. All roads shall be
posted with curve signs and maximum speed limits that will permit the equipment to be stopped
within one-half the minimum sight distance.
5.3.5 OPERATORS.
Machinery and mechanized equipment shall be operated only by authorized qualified persons.
5.3.6 RIDING ON EQUIPMENT
Riding on equipment by unauthorized personnel is prohibited. Seating and safety belts shall be
provided for the operator and all passengers.
5.3.7 GETTING ON OR OFF EQUIPMENT
Getting on or off equipment while the equipment is in motion is prohibited.
5.3.8 HOURS OF OPERATION.
Except in emergencies, an equipment operator shall not operate any mobile or hoisting
equipment for more than 12 hours without an 8-hour rest interval away from the job.
5.4 POWER CRANES AND HOISTS (TRUCK CRANES, CRAWLER CRANES, TOWER
CRANES, GANTRY CRANES, HAMMERHEAD CRANES, DERRICKS, CABLEWAYS, AND
HOISTS)
5.4.1 PERFORMANCE TEST
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Before initial onsite operation, at 12-month intervals, and after major repairs or modification,
power cranes, derricks, cableways, and hoists must satisfactorily complete a performance test
shall be conducted in the presence of a representative of the Contracting Officer. Test data shall
be recorded and a copy furnished the Contracting Officer.
5.4.2 PERFORMANCE TESTPOWER CRANES (Crawler mounted, truck mounted and
wheel mounted)
The performance test is to be carried out as per ANSI requirements. The test is to consist of
raising, lowering, and braking the load and rotating the test load through 360° degrees at the
specified boom angle or radius. Cranes equipped with jibs or boom-tip extensions are to be
tested using both the main boom and the jib, with an appropriate test load in each case.
5.4.3 PERFORMANCE TESTDERRICKS, GANTRY CRANES, TOWER CRANES,
CABLEWAYS, AND HOISTS, INCLUDING OVERHEAD CRANES
This equipment is to be performance tested as per ANSI requirements.
5.4.4 BOOM ANGLE INDICATOR
Power cranes (includes draglines) with booms capable of moving in the vertical plane shall be
provided with a boom angle indicator in good working order.
5.4.5 CRANE TEST CERTIFICATION.
The performance test required by 5.4.2 and 5.4.3 is fulfilled if the Contractor provides the
Contracting Officer a copy of a certificate of inspection made within the past 12 months by a
qualified person or by a government or private agency satisfactory to the Contracting Officer.
5.4.6 POSTING FOR HIGH VOLTAGE LINES
A notice of the 10-foot (or greater) clearance required by OSHA 1926.550, Subpart N, shall be
-type concrete pumps, backhoes, and
related equipment.
5.4.7 BOOM STOPS
Cranes or derricks with cable-supported booms, except draglines, shall have a device attached
between the gantry of the A-frame and the boom chords to limit the elevation of the boom. The
device shall control the vertical motions of the boom with increasing resistance from 83° or less,
until completely stopping the boom at not over 87° above horizontal.
5.4.8 SAFETY HOOKS
Hooks used in hoisting personnel or hoisting loads over construction personnel or in the
immediate vicinity of construction personnel shall be forged steel equipped with safety keepers.
When shackles are used under these conditions, they shall be of the locking type or have the
pin secured to prohibit turning.
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
5.5.1 ROLLOVER PROTECTIVE STRUCTURES
OSHA 1926, Subpart W, Overhead Protection, Sections 1001 and 1002 are applicable
regardless of the year in which the equipment was manufactured and regardless of the struck
capacity of the equipment.
5.5.2 EQUIPMENT REQUIRING ROPS
The requirement for ROPS meeting 5.5.1 above applies to crawler and rubber-tired tractors
such as dozers, push-and-pull tractors, winch tractors, tractors with backhoes, and mowers; off-
highway, self-propelled, pneumatic-tired earthmovers, including scrapers, motor graders and
loaders; and rollers, compactors, water tankers (excluding trucks with cabs). These
requirements shall also apply to agricultural and industrial tractors and similar equipment.
5.5.3 EQUIPMENT REQUIRING SEATBELTS
The requirements for seatbelts as specified in OSHA Subpart 0, Motor Vehicles, Mechanized
Equipment, and Marine Operations, Section 1926.602 shall also apply to self-propelled
compactors and rollers, and rubber-tired skid-steer equipment.
5.6 LIFT PLAN
A Crane Lift or concrete boom truck Plan is required for any crane lift on a Monroe County
project.
Lifts exceeding 75% of the cranes stability / structural capacity chart, requiring movement of a
crane carriage with the load, personnel platforms, sensitive loads (long lead time, cost), loads
requiring two (or more) hooks, work over occupied facilities or work involving encroachment on
public rights of way are considered critical. These lifts must be authorized in advance.
Critical crane lift plans, if authorized, may have to be reviewed by a professional
engineer (the contractor shall budget the PE review within project budget). Additionally,
a critical lift JHA shall be submitted with the crane lift plan.
Crane Lift Plans must be submitted at least 48 hours (2 business days) prior to mobilization 5
days for critical and helicopter lifts.
deductions and lift radius for a specific crane configuration in a specific location.
The Crane Lift Plan may be valid for more than one day, as long as the configuration, location,
maximum expected load, and maximum expected radius does change. Use multiple lift
RSX
plans for multiple locations.
The Crane Lift Plan must be along with attachments see Section 5 for the
'3140)8)
required Attachments.
All rigging devices bear the name of the manufacturer and be certified as to their
1978
capacity. Custom-fabricated devices (lifting beams, spreader bars, etc) may be acceptable with
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
proper PE stamp or proof testing as required by applicable standards. Capacities shall be
marked and legible on all such devices.
Work that is not anticipated in the Crane Lift Plan, but may arise due to site conditions (moving
equipment, loading materials onto floors, etc) must be reviewed with Monroe County prior to
hoisting. Changes affecting crane configuration and / or location may require the Crane Lift Plan
to be amended.
The contractor is responsible to visit the site prior to the lift date to review documentary
information pertaining to the site, which is maintained by Monroe County.
The contractor is responsible (determining adequacy, supplying and installing) for all supporting
material (as defined within 29 CFR 1926.1402) necessary for the crane lift.
The contractor is responsible to obtain all information that is necessary to develop a power line
safety plan.
The contractor is responsible to train all personnel involved in the Assembly / Disassembly and
or Crane Lift.
The contractor must provide the following information along with the Crane Lift Plan:
Competent / Qualified Person Designation Forms for A/D Director, Operator, Rigger,
Signal Person
Load Chart (complete with notes)
Range Chart
Dimension Illustration and Specifications for Crane
Lightning and Wind Restrictions (from operators manual)
Area (Quadrant) of Operation Diagram
Operators License, Operators Training Information, USDOT Medical Certification, OSHA
10/30 Hour Course Completion Cards, as may be required by the project.
Jurisdictional Registration, if required
JHA for Assembly / Disassembly of Crane, Severe Weather, Truck Load / Unload, Etc.
JHA for Power Line Encroachment
3rd Party Inspection Certification and Report see Crane Lift Plan for requirements
(Note: The inspector shall be certified with the CCAA).
Weights of Materials
Rigging Plan
Logistics Plan
The contractor shall comply with the Site Specific Safety Plan.
The contractor / Crane Company / Rigging Company is responsible for the accuracy of plan and
inspections. This planning process has been established to help ensure proper coordination
between Contractor, subcontractors and Monroe County.
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
No warranty or certification of the suitability of this plan is accepted by Monroe County. It is the
responsibility of the Contractor/Subcontractor and the Crane Operator to ensure that they and
their employees are qualified, competent, properly equipped and properly trained to perform the
activities outlined in this plan.
0%(()67%2(7'%**30(-2+
6.1 LADDERS.
OSHA 1926, Subpart L - Section 450. Ladders shall be used as work platforms only when use
of small hand tools or handling of light material is involved. No work requiring lifting of heavy
materials or substantial exertion shall be done from ladders.
6.2 SCAFFOLDING. OSHA 1926, Subpart L - Section 451
Scaffolds, platforms or temporary floors shall be provided for all work except that which can be
done safely from the ground or similar footing.
6.3 SAFETY BELTS, LIFELINE, AND LANYARDS. OSHA 1926, Subpart E, Section 104
Lifelines, safety belts and lanyards independently attached or attended, shall be used when
performing such work as the following when the requirements of 6.1 or 6.2 above cannot be
met.
(a) Work on stored material in hoppers, bins, silos, tanks, or other confined spaces.
(b) Work on hazardous slopes, structural steel, or poles; erection or dismantling of safety nets,
tying reinforcing bars; and work from Boatswain's chairs, swinging scaffolds, or other unguarded
locations at elevations greater than 6 feet.
(c) Work on skips and platforms used in shafts by crews when the skip or cage does not block
the opening to within 1 foot of the sides of the shaft, unless cages are provided.
*-6)4638)'8-32
A. Every Contractor and Subcontractor employed on the Project shall exercise good
construction practices to prevent fire. It shall be the responsibility of the Contractor to insure
that general fire protection facilities are adequate for his work and to provide additional fire
protection facilities and devices, including fire extinguishers as required by their scope of work.
;36/2)%6)2)6+->)()0)'86-'%00-2)73638,)698-0-8-)7
A. It shall be the Contractor's sole and exclusive responsibility:
(a) To provide personnel capable of working adjacent to energized electrical lines or other
utilities
(b) To provide adequate, safe and properly maintained equipment
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
(c) To conduct all of his work in accordance with the safety rules and regulations prescribed by
the National Electric Code, National Electric Safety Code, H30, and Safety Rules for Installation
and Maintenance of Electrical Supply and Communication Lines Hand Book 81, Occupational
Safety and Health Act of 1970, as well as other safety codes in effect at the site of construction
and as specified elsewhere herein, or as are generally applicable to the type of work being
performed
(d) To continuously supervise and inspect the work being performed to assure that the
requirements of (a), (b), and (c) above are complied with, and nothing in these Contract
Documents shall be held to mean that any such responsibility is the obligation of the Owner or
the Architect or Project Management.
&%66-'%()7;%62-2+():-')7%2(0-+,8-2+
A. The Contractor shall be solely responsible for providing temporary ladders, guard rails,
warning signs, barricades, night guard lights, and deck or floor closures required in connection
with his work to comply with Federal, State and local safety requirements. The Contractor shall
be solely and exclusively responsible for the design, construction, inspection and maintenance
of such facilities at all times.
B. It shall be the responsibility of the Contractor to provide additional temporary lighting, if
needed to maintain safe conditions.
C. It shall be the sole and exclusive responsibility of the Contractor to provide a safe place
to work for all laborers and mechanics and other persons employed on or in connection with the
project, and nothing in these Contract Documents shall be construed to give any of such
responsibility to the Owner, the Architect, or Project Management.
D. The Contractor shall provide a security fence around the area of the Work so as to
prevent entry into the Work area by unauthorized personnel and the general public. The fence
shall have fence post bases that eliminate the need to penetrate the ground for support.
,%>%6(3971%8)6-%07
10.1 In the event the Contractor encounters on the site material reasonably believed to be
asbestos or polychlorinated biphenyl (PCB) which has not been rendered harmless, the
Contractor shall immediately stop Work in the area affected and report the condition to the
Owner and Project Management in writing. The Work in the affected area shall not thereafter
be resumed except by written agreement of the Owner and Contractor if in fact the material is
asbestos or polychlorinated biphenyl (PCB) and has not been rendered harmless. The Work in
the affected area shall be resumed in the absence of asbestos or polychlorinated biphenyl
(PCB), or when it has been rendered harmless, by written agreement of the Owner and
Contractor.
10.1.1 The Contractor shall not be required pursuant to Article 7 to perform without
consent any Work relating to asbestos or polychlorinated biphenyl (PCB).
10.1.2 If reasonable precautions will be inadequate to prevent foreseeable bodily injury
or death to persons resulting from a material or substance encountered on the site by the
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Contractor, the Contractor shall, upon recognizing the condition, immediately stop Work in the
affected area and report the condition to Project Management in writing. The Owner, Contractor
and Project Management shall then proceed in the same manner described in Subparagraph
10.1
10.1.3 The Owner shall be responsible for obtaining the services of a licensed
laboratory to verify a presence or absence of the material or substance reported by the
Contractor and, in the event such material or substance is found to be present, to verify that it
has been rendered harmless. Unless otherwise required by the Contract Documents, the
Owner shall furnish in writing to the Contractor and Project Management the names and
qualifications of persons or entities who are to perform tests verifying the presence or absence
of such material or substance or who are to perform the task of removal or safe containment of
such material or substance. The Contractor and Project Management will promptly reply to the
Owner in writing stating whether or not any of them has reasonable objection to the persons or
entities proposed by the Owner. If the Contractor or Project Management has an objection to a
person or entity proposed by the Owner, the Owner shall propose another to whom the
Contractor and Project Management have no reasonable objection.
7EJIX]SJ4IVWSRWERH4VSTIVX]
10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide
reasonable protection to prevent damage, injury or loss to:
.1 employees on the Work and other persons who may be affected thereby;
.2 The Work and materials and equipment to be incorporated therein, whether in storage
on or off
Subcontractors or Sub-subcontractors;
.3 other property at the site or adjacent thereto, such as trees, shrubs, lawns, walks,
pavements, roadways, structures and utilities not designated for removal, relocation or
replacement in the course of construction; and
.4 construction or operations by the Owner or other Contractors
10.2.2 The Contractor shall give notices and comply with applicable laws, ordinances, rules,
regulations and lawful orders of public authorities bearing on safety of persons or property or
their protection from damage, injury or loss.
10.2.3 The Contractor shall erect and maintain, as required by existing conditions and
performance of the Contract, reasonable safeguards for safety and protection, including posting
danger signs and other warnings against hazards, promulgating safety regulations and notifying
owners and users of adjacent sites and utilities.
10.2.4 When use or storage of explosives or other hazardous materials or equipment or
unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost
care and carry on such activities under supervision of properly qualified personnel.
10.2.5 The Contractor shall promptly remedy damage and loss to property referred to in
Clauses 10.2.1.2, 10.2.1.3, 10.2.1.4 caused in whole or in part by the Contractor, a
Subcontractor, a Sub-subcontractor, or anyone directly or indirectly employed by any of them, or
by anyone for whose acts they may be liable and for which the Contractor is responsible under
Clauses 10.2.1.2, 10.2.1.3 and 10.2.1.4, except damage or loss attributable to acts or omissions
of the Owner, Project Management or Architect or anyone directly or indirectly employed by any
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
of them, or by anyone for whose acts any of them may be liable, and not attributable to the fault
or negligence of the Contractor. The foregoing obligations of the Contractor are in addition to
ons under Paragraph 3.18.
10.2.6
superintendent unless otherwise designated by the Contractor in writing to the Owner or Project
Management.
10.2.7 The Contractor shall not load or permit any part of the construction or site to be loaded
so as to endanger its safety.
)1)6+)2'-)7
11.1 In an emergency affecting safety of persons or property, the Contractor shall act, at the
or extension of time claimed by the Contractor on account of an emergency shall be determined
as provided in Paragraph 4.7 and Article 7
End of Section 00970
PROJECT SAFETY AND HEALTH PLAN 00970-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
'3286%'83659%0-8='32863040%2
463.)'8
A. The Project Management Representative will monitor all work performed by the
Contractor and assist the Contractor with his conformance of the work to the
Contract Drawings and Specifications.
'3286%'8367(98-)7%2(6)74327-&-0-8-)7
A. The Contractor is responsible for the quality of the work performed by his work
force on this project as well as the quality of the material, equipment and supplies
furnished by him to be incorporated into the work.
B. The Contractor will provide a Quality Control Plan for approval and designate a
Quality Control Representative who will be on site at all times while the
respective Contractor's work is in progress and will have the authority and
responsibility to accept or reject items of work. The Contractor's Quality Control
Representative may delegate his duties but the primary responsibility and
authority will rest on him.
C. The Contractor's Quality Control Representative will coordinate the submittal of
all shop drawings, product data and samples to Project Management. Any
submittal that is at variance to the contract requirements must be identified as
such and transmitted to Project Management for submittal and approval by the
Owner. No work requiring submittal of a shop drawing, product data or sample
shall commence until the submittal has been reviewed and approved by Project
Management.
D. The Contractor will bear the responsibility of scheduling all required testing and
inspections by the designated material-testing laboratory, in a timely fashion, to
prevent needless cancellations and delays of work activities. Any costs caused
by untimely notification shall be borne by the Contractor.
E. The Contractor's Quality Control Representative will review his drawings,
procurement documents and contracts to insure that the technical information
provided and all work performed is in accordance with the latest revisions of the
Contract Drawings and Specifications.
F. The Contractor's Quality Control Representative will perform an inspection upon
receipt at the site of the work of all materials, equipment and supplies including
those furnished to him by the Owner. Notes from this inspection will be filled out
on the appropriate form and included with the Contractor Daily Quality Control
Report. Items which are damaged or not in conformance with the respective
submittals, quality standards, contract drawings and specifications shall be
brought to the attention of Monroe County representative on site and then will be
identified and segregated from accepted items. Items thus identified will not be
incorporated into the work until corrective action acceptable to Project
Management is completed. Items determined unsalvageable will be removed
CONTRACTOR QUALITY CONTROL PLAN 00980-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
from the job site. These items shall be noted as deficient in the applicable
section of the Contractor Daily Quality Control Report.
-274)'8-32%2(8)78-2+
A. INSPECTION PLAN
Project Management utilizes a multi-point inspection plan for each separate
feature of work to be performed under this Contract, i.e., work described by each
division of the technical provision section of the contract specifications. This plan
consists of the following:
1. Preparatory InspectionPrior to commencing the work, the Contractor's
Quality Control Representative will meet with Project Management
representative and check the following items at a minimum for
conformance:
(a) Approval of shop drawings and submittals.
(b) Approval of inspection and test reports of materials and equipment
to be utilized.
(c) Completion of previous operations of preliminary work.
(d) Availability of materials and equipment required.
(e) Potential utility outages.
(f) Any other preparatory steps dependent upon the particular
operation.
(g) Quality standards.
(h) Safety or environmental precautions to be observed. (Phase
Hazard)
Note: Project Management will record the minutes to this inspection meeting
and distribute accordingly.
2. Initial InspectionUpon completion of a representative sample of a given
feature of the work, the Contractor's Quality Control Representative will
meet with Project Management representative and check the following
items at a minimum for conformance:
(a) Workmanship to established quality standards.
(b) Conformance to contract drawings and specifications.
(c) Construction methods, equipment and tools utilized.
(d) Materials and articles utilized.
(e) Adequacy of testing methods.
(f) Adequacy of shop drawings.
(g) Adequacy of safety or environmental precautions.
Note: Project Management will record the minutes to this inspection meeting
and distribute accordingly.
3. Follow-up InspectionsThe Contractor's Quality Control Representative
will inspect the work daily to assure the continuing conformance of the
CONTRACTOR QUALITY CONTROL PLAN 00980-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
work to the workmanship standards established during the preparatory
and initial inspections.
Additionally, as a part of the follow-up inspection, sign-off sheets will be
utilized as often as possible. The intent of these sheets is to achieve
concurrence from other trade contractors and responsible parties that
ensuing work can indeed commence over underlying work. This will
prevent oversights and omissions which could elevate costs. Sign-off
sheets shall be used for, but not be limited to, concrete, drywall, ceilings,
painting, roofing substrates and flooring. These reports are to be
generated by the Contractor and submitted to Project Management
Superintendent for approval prior to the start-up of work.
Failure to generate a sign-off sheet or to attain proper signatures prior to
covering up underlying work may affect payment for that piece of work if
ensuing problems are detected or not. This disciplinary action shall be
carried out via the Nonconformance Report. (See Section 1.4.B of this
plan.)
Note: The Contractor shall be responsible to record these inspections and all
other project related activities encountered throughout the day on the
Contractor Daily Quality Control Report.
4. Completion InspectionsUpon completion of a given feature of the work,
the Contractor's Quality Control Representative will meet with the Project
Management Superintendent, if he so desires to attend, to perform an
inspection of the completed work. Nonconforming items will be identified
and corrected prior to commencement of the next operation.
Note: The Contractor shall conduct and report corrections of this inspection
which shall be a required submittal.
5. Follow-On InspectionsUpon execution of the contractor's completion
inspection in elements of the work which result in concealment; such as,
ceiling and drywall installations, the Contractor shall schedule and
conduct multi-trade or singular inspections prior to covering installation.
Note: Project Management will record the minutes to this inspection meeting.
6. Pre-Final InspectionUpon substantial completion of the project work
Project Management shall coordinate and conduct a universal inspection
of all areas and elements of the work. The Architect/Engineer may be
represented if he so desires. This inspection shall be completed at least
(15) days prior to the final substantial completion inspection which shall
be conducted by Project Management. All deficiencies and incomplete
work should be completed prior to the final substantial completion
inspection.
B. OPERATION AND CHECK OUT TESTING
CONTRACTOR QUALITY CONTROL PLAN 00980-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The Contractor will provide personnel and equipment to perform the operational
tests and check-out of the equipment, facilities or equipment constructed,
fabricated or installed under this Contract. The Project Management
Superintendent will coordinate and witness all such tests. Notification should be
given at least ten (10) days in advance of the scheduled tests.
C. FINAL INSPECTION
Project Management will coordinate and attend all final inspections of the work.
Prior to requesting a final inspection, all tests for the equipment and systems
must be completed.
See Section 01700 for contract closeout.
6)4368-2+
Maintaining accurate and retrievable records is extremely important in the Quality
Assurance Program. These records will act as a main source of information in the
present and in the future for the entire project management team. The main report that
will be utilized to provide this information is the Daily Quality Control Report.
Nonconformance Reports may also be issued.
A. DAILY QUALITY CONTROL REPORT
The Daily Quality Control Report shall be used to document the summary of daily
inspection activities performed by the Contractor's designated Quality Control
Representative. It shall include any of the steps of inspection that are performed
that day, all test monitoring and any rework of nonconforming items. The daily
Quality Control Report section of the Daily Superintendent's Report will be
routinely used for daily reporting requirements. When the magnitude or
complexity necessitates such, a more separate and comprehensive form will be
used. Reference Contractor's Daily Report, and as needed Contractor Daily
Quality Control Report, Section 01385.
B. NONCONFORMANCE REPORT
Nonconformance Reports will be issued for work that is found to be in
nonconformance with the contract documents or the referenced quality
standards. The report will be issued by Project Management.
It is not the intent to routinely and repeatedly issue nonconformance reports, but
to issue them only after normal enforcement standards have been exhausted, or
if the work performed is a detriment to the project.
A copy of the Nonconformance Report will be forwarded to the Site Project
Manager for his information and/or action. It should also be included in the
Contractor's Daily Quality Report package for general review.
Nonconformance Reports will be signed off once the deficient item or items have
adequately been corrected. This will be done by the issuing Superintendent and
Project Manager. These sign-offs will be included with a corresponding
CONTRACTOR QUALITY CONTROL PLAN 00980-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
corrective action taken. Significant nonconformance needs to be addressed to
prevent recurrence. The signed-off report will also be submitted for review.
Work activities affected by a Nonconformance Report will proportionally counter-
affect payments. Whether that be partial or full retainage will be left up to the
discretion of Project Management.
%9(-87
A. Project Management may choose at its option to perform Contractor audits of
their Contractor Quality Control Plan at any time. Reports of these audit results
will be forwarded to the Project Manager for his action. Any action items noted
during an audit for the Contractor will be followed up and documented to insure
compliance and avoid recurrence.
7911%6=
The intention of this plan is to create a system of checks and balances that will minimize
delays caused by rework and a lack of planning and maximize production and insure
that the finished product is one that the entire construction team can pride themselves in.
These goals can be achieved by giving the Owner exactly what he has bought. The
Owner will expect no more and through Quality Assurance, the construction team will
provide no less.
End of Section 00980
CONTRACTOR QUALITY CONTROL PLAN 00980-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
74)'-%0'32(-8-327
1. Construction shall be conducted in such a manner as to cause the least possible
interruption to normal County business. Necessary access to and from adjacent
buildings and the parking area shall be provided at all times.
2. Contractor shall take all means necessary to contain dust and debris as an
integral part of the work.
3. Weather intrusion and unauthorized access to the Project Site due to
construction activities
of work, or other means satisfactory to the Owner.
4. Contractor shall coordinate construction activities as necessary to avoid security
or safety concerns at the Project Site.
5. Information shown on the Drawings is assembled from numerous record
information sources and may be inaccurate or incomplete. Contractor shall make
such field visits or investigations as are necessary to prepare an accurate and
complete bid. Claims for extra work or expense after bid closing which are due to
reasonably foreseeable circumstances shall be denied and shall remain the sole
risk and expense of the Contractor. Field measured dimensions shall be
obtained by the Contractor prior to placing orders for fabrications or prefabricated
materials. Adjustments, delays, re-fabrications, or replacement materials due to
inaccurate information are the sole responsibility of the Contractor.
6. SITE SURVEY
A. The Plat of Survey and other survey data, are available in the Office of
Project Management for review, and are for the general information of the
contractor. The data contained was prepared by the Owner for the Architect's
use for the design of the project, and neither the Owner nor the Architect, nor
Project Management make any representation, guarantee of warranty as to the
accuracy or completeness of data indicated, expressed or implied.
B. Proposers shall visit the site; make their own investigations, assumptions
and conclusions as to the nature and extent of existing surface and overhead
conditions affecting the work. Neither the Owner nor the Architect, nor Project
Management will be responsible for additional type or extent of work required to
be performed under the Contract due to any assumptions or conclusions by the
successful proposer based upon the survey information provided.
End of Section 00990
SPECIAL CONDITIONS 00990-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
7911%6=3*8,);36/
4VSNIGX3ZIVZMI[
Contractor is to:
1. Provide and install complete 2 space dehumidifiers as indicated on these plans
including all supports, electric power, and condensate drain system.
2. Provide and install electrical control and power for the dehumidifiers, service
recepticles, lighting in attic for service, and new circuit breakers, conduit and
conductors as detailed on the electrical plans.
3. Provide and make accessible attic access and maintenance space in the existing
attic.
4. Pickup County Permit Submitted by owner #16102478
5. Clean up space during and after installation
6. Coordinate access installation with fire chief and Monroe County Project Manager.
7. Re-insulate existing supply duct work on fisrt floor as shown.
8. Install new return air duct on first floor as shown
9. Provide and install new door sweeps, thresholds and seals.
The Contractor shall be responsible for complying with regulations, approvals, and
1SRVSI'SYRX]&YMPHMRK(ITX*MVI1EVWLEPPER]SXLIV
permitting by the:
TIVQMXXMRKSVVIKYPEXSV]EKIRGMIWEWETTPMGEFPI
+IRIVEP4VSNIGX-RXIRXERH7GSTI
2.
Provide all labor, supervision, engineering, materials, supplies, equipment, tools,
transportation, surveying, layout, and protection for the proper execution and completion of all
the work in accordance with the Contract Documents. The Work shall include but not be limited
to that shown on the Drawings and detailed in the Technical Specifications if any included in this
Contract.
+IRIVEP6IUYMVIQIRXW
3.
F. Construction work times shall be limited to: 8:00 am to 5:00 pm Mon-Fri
G. Contractor needs to be aware of weather and location and plan accordingly.
H. Contractor needs to be aware of the facility, its vendors and staff with unusual schedules
and plan accordingly. Coordination of each days works shall be done in advance with
approval from County. All spaces interior and exterior shall be cleaned and returned to
normal work period/ day.
I. The Scope of Work shall include, but not be limited to, all work shown and listed in the
Project Drawings. The Contractor is required to provide a complete job as contemplated
by the drawings and specifications, which are a part of this bid package. The Contractor
shall furnish all labor, supervision, materials, power, tools, equipment, supplies and any
other means of construction necessary or proper for performing and completing the
Scope of Work, unless otherwise specifically stated.
J. SPECIAL PROVISIONS
SUMMARY OF THE WORK 01010-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
The following Special Provisions are intended to clarify the scope of work, or highlight
features of the work, or modify, change, add to, or delete from the General Scope of this
Proposal Package.
1. All licenses required in order to perform the scope of work in the specified
location, shall be procured and maintained by the contractor and his
subcontractors. Contractor shall submit copies to Project Management prior to
notice to pro
2. Provide, replace, and maintain any safety rails and barricades as necessary
during the process of work, or during deliveries of materials or equipment.
3. Contractor is to review Division 1 General Requirements for additional
responsibilities required in order to perform this Work.
4. If in the event of conflicting, or overlapping requirements in any area of the
proposal documents, technical specifications, or drawings, the most stringent
condition shall be proposed and constructed. Notify Project Management in any
event, in order to not compromise the Owner's right to make appropriate
decisions.
5. Contractor shall maintain As-Built Drawings, (Record Drawings per Section
01720), of his work progression.
6. The Contractor shall not store materials, tools or debris inside the building with
out written permission. Contractor shall provide suitable storage container, and
be responsible for disposal off-site of all debris and trash.
7. Th
for Job Site access. Job site will have limited 8:00 AM -5:00PM work hours.
Contractor will need to schedule work shifts typically from 8:00 AM- 5:00PM
weekly. Any change to agreed upon schedule must be obtained in writing with a
minimum of 72 hrs advanced notice.
8. Coordination of each days works shall be done in advance with approval from
County. All spaces interior and exterior shall be cleaned and returned to normal
each work period.
4638)'8-32
A. The Contractor shall use every available precaution to provide for the safety of property
owner, visitors to the site, and all connected with the work under the Contract.
B. All existing facilities both above and below ground shall be protected and maintained
free of damage. Existing facilities shall remain operating during the period of construction
unless otherwise permitted. All access roadways must remain open to traffic unless otherwise
permitted.
C. Barricades shall be erected to fence off all construction areas from operations personnel
and the general public. Fence posts shall have bases that eliminate the need to penetrate the
ground for support.
SUMMARY OF THE WORK 01010-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
D. Safety Requirements
1. All application, material handling, and associated equipment shall conform to and be
operated in conformance with OSHA safety requirements.
2. Comply with federal, state and local and owner fire and safety requirements.
3. Advise owner whenever work is expected to be hazardous to owner employeesand/or
operations.
4. Maintain a crewman as a floor area guard whenever roof and or decking is being
repaired or replaced.
5. Maintain proper fire extinguisher within easy access whenever power tools, roofing
kettles, and torches are being used.
,397)/))4-2+
1. Keep materials neat and orderly.
2. Remove scrap, waste and debris from project area daily.
3. Maintenance of clean conditions while work is in progress and cleanup when work is
completed shall be in strict accordance with the "General Conditions" of this contract.
4. Maintain Fire protection during construction
5.
Housekeeping required on a daily basis
End of Section 01010
SUMMARY OF THE WORK 01010-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
4%68+)2)6%0
()7'6-48-32
A. Work included:
This Section applies to situations in which the Contractor or his representatives including, but
not necessarily limited to, suppliers, subcontractors, employees, and field engineers, enter upon
Owner's property.
Related work:
Documents affecting work of this Section include, but are not limited to, General Conditions,
Supplementary Conditions, and Sections in Division 1 of these Specifications.
59%0-8=%7796%2')
A. Promptly upon award of the Contract, notify all pertinent personnel regarding
requirements of this Section.
Require all personnel who will enter upon the Owner's property certify their awareness of and
familiarity with requirements of this Section.
79&1-88%07
Maintain an accurate record of names and identification of all persons entering upon Owner's
property in connection with Work of this Contract, including times of entering and times of
leaving, and submit a copy of the record to Owner daily.
86%274368%8-32*%'-0-8-)7
A. Provide adequate protection for curbs and sidewalks over which trucks and equipment
pass to reach job site.
Contractor's vehicles:
1. Require Contractor's vehicles, vehicles belonging to employees of Contractor, and all
other vehicles entering upon Owner's property in performance of Work of Contract, to use only
the Access Route approved in advance by Owner.
Do not permit such vehicles to park on any street or other area of Owner's property except in
the area approved by Owner as "Contractor's Parking Area."
7)'96-8=
A. Restrict access of all persons entering upon the Owner's property in connection
with work to the Access Route and to actual site of the work.
End of Section 01015
01015-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
%440-'%8-32*364%=1)28
7911%6=
This section provides procedures for preparation and submittal of Applications for
Payment.
*361%8
The Application for Payment including the Continuation Sheet is the required format for
submitting invoices. A copy of these forms is included in this section. The Owner reserves the
right to modify the format to better suit his internal accounting system.
79&1-88%0463')(96)7
A. The initial Application for Payment will not be processed until the Contractor's
'SRWXVYGXMSR7GLIHYPI7GLIHYPISJ:EPYIWERHXLIMRMXMEP7YFQMXXEP7GLIHYPI
ETTVSZIH
have been received, reviewed and by Project Management.
B. Submit an updated Construction Schedule and Submittal Schedule and a Partial
Release of Lien with each Application for Payment.
C. Payment shall be made according to the Local Government Prompt Payment
Act, Sec. 218.70 et seq. Florida Statutes.
D. Monroe County makes every effort to meet the payment schedule. It is
requested that the contractor not make any calls to any County office inquiring about
th
payment until the twentieth (20) day after submission of the pay request.
1328,0=4%=6)59)78463')(96)
A. Project Management to review as-builts as to current additions, corrections, etc.,
prior to monthly approval to ensure as-builts are current.
*-2%04%=463')(96)
A. To help expedite the final payment, it is necessary for Project
Management to have a correct and complete package of documents 20 days in advance
of requested pay date.
B. A minimum of ten (10) working days is required from receipt of correct
documents for Project Management to obtain necessary signatures and submit project
for Final Payment. Contractor shall submit all required forms and releases to Project
Management. The following documents (samples attached) are required for Final
Payment:
APPLICATION FOR PAYMENT 01027-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
(1) Application and Certificate for Payment
(2) Continuation Sheet
(3) Certificate of Substantial Completion
(4) bts and Claims
(5)
(6) Final Release of Lien
-
drawings, including red-lined site plan, submittal documents, certification that all utility
bills (i.e., electric, local water) have been paid, and a complete list of subcontractors with
addresses and phone numbers must be submitted prior to final payment in both bound
paper and electronic PDF form on CD/DVD.
'-XMWVIWTSRWMFMPMX]XSIRWYVIXLIGSQTPIXIRIWWSJ
XLI*MREP4E]4EGOEKI-RGSQTPIXIRIWW[MPPVIWYPXMRHIPE]SJ*MREP4E]*MREP4E]
6IUYIWXW[MPPRSXFITVSGIWWIHYRXMPEPPXLIVIUYMVIHHSGYQIRXWEVIVIGIMZIHF]
1SRVSI'SYRX]4VSNIGX1EREKIQIRX*MREP4E]6IUYIWXQYWXFIWYFQMXXIHRS
PEXIVXLERHE]WEJXIVJMREPTVSNIGXGSQTPIXMSRERHEGGITXERGI
79&78%28-%8-2+(%8%
A. When the Owner's Representative requires substantiating information, submit
data justifying dollar amounts in question.
B. Provide one copy of data with cover letter for each copy of submittal. Indicate
Application number, date, line item by number and description.
APPLICATION FOR PAYMENT 01027-Page of
4EGOIX4K
%XXEGLQIRX6*4JSV,:%'6ITEMVW7-*7?6IZMWMSRA
%TTVSZEPXS%HZIVXMWI6*4JSV7XSGO-WPERH
%XXEGLQIRX6*4JSV,:%'6ITEMVW7-*7?6IZMWMSRA
%TTVSZEPXS%HZIVXMWI6*4JSV7XSGO-WPERH
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1')41
3263)3928=2+-2))6-2+63.)'8%2%+)1)28
CCO
ONTRACT HANGE RDER
463.)'88-80)',%2+)36()623
-2-8-%8-32(%8)
83'3286%'836'3286%'8(%8)
The Contract is changed as follows:
The original (Contract Sum)
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
The date of Substantial Completion a
Detailed description of change order and justification:
This change Order is % of the original contract price.
2SXZEPMHYRXMPWMKRIHF]3[RIV%VGLMXIGX
MJETTPMGEFPI
ERH'SRXVEGXSV
ARCHITECT:
Date
CONTRACTOR:
Date
DIRECTOR PROJECT MANAGEMENT:
Date
SR. DIRECTOR ENG/PW: _______
Date
COUNTY/DEPUTY ADMINISTRATOR
Date
4EGOIX4K
APPLICATION FOR PAYMENT 01027-Page of
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
'LERKI3VHIV%XXEGLQIRXTIV3VHMRERGI2S
Change Order was not included in the original contract specifications. Yes No
If Yes, explanation:
Change Order was included in the original specifications. Yes No
If Yes, explanation of increase in price:
Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes No
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes No
If no, explanation of why:
Change Order is correcting an error or omission in design document. Yes No
Should a claim under the applicable professional liability policy be made? Yes No
Explain:
CERTIFICATE OF SUBSTANTIAL COMPLETION
4EGOIX4K
APPLICATION FOR PAYMENT 01027-Page of
PROJECT: CONTRACT FOR:
CONTRACT DATE:
(Name and address)
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
TO OWNER: CONTRACT FOR:
CONTRACT DATE:
(Name and address)
PROJECT:
(Name and address)
State of:
County of:
The undersigned, pursuant to Article 9 of the General Conditions of the Contract for Construction, hereby certifies that, except as listed
below, he has paid in full or has otherwise satisfied all obligations for all materials and equipment furnished, for all work, labor, and
services performed, and for all known indebtedness and claims against the Contractor for damages arising in any manner in connection
with the performance of the Contract referenced above for which the Owner or his property might in any way be held responsible.
d by the Owner, the Contractor shall furnish bond satisfactory to the Owner for each
exception).
SUPPORTING DOCUMENTS ATTACHED HERETO:
CONTRACTOR:
1. Consent of Surety to Final Payment. Whenever
Surety is involved, Consent of Surety is required.
AIA DOCUMENT G707, CONSENT OF
SURETY, may be used for this purpose. Indicate
attachment: yes ( ) no ( ) Address:
The following supporting documents should be attached
hereto:
By:
1.
conditional upon receipt of final payment.
Subscribed and sworn to before me this
2. Separate Releases or Waivers of Liens from day of ,20 .
Subcontractors and material and equipment
suppliers, to the extent required by the Owner,
accompanied by a list thereof. Notary Public:
3. ase of Liens.
My Commission Expires:
4EGOIX4K
APPLICATION FOR PAYMENT 01027-Page of
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
RELEASE OF LIENS
833;2)6'3286%'8*36
2EQIERHEHHVIWW
'3286%'8(%8)(
463.)'8
2EQIERHEHHVIWW
State of ___________________:
County of _________________:
tion and belief,
except as listed below, the Releases or Waivers of Lien attached hereto include the Contractor, all
Subcontractors, all suppliers of materials and equipment, and all performers of Work, labor or services
who have or may have liens or encumbrances or the right to assert liens or encumbrances against any
property of the Owner arising in any manner out of the performance of the Contract referenced above.
EXCEPTIONS:
CONTRACTOR:
SUPPORTING DOCUMENTS ATTACHED
2EQIERHEHHVIWW
HERETO:
1.
conditional upon receipt of final payment.
By:
_____________________________________
2. Separate Releases or Waivers of Liens from
7MKREXYVISJEYXLSVM^IHVITVIWIRXEXMZI
Subcontractors and material and equipment
suppliers, to the extent required by the Owner,
accompanied by a list thereof. _____________________________________
4VMRXIH2EQIERH8MXPI
Subscribed and sworn to before me this date:
_____________________________
Notary Public:
_____________________________
(SEAL)
My Commission Expires:
____________________
4EGOIX4K
APPLICATION FOR PAYMENT 01027-Page of
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
13263)'3928=
FINAL RELEASE OF LIEN
KNOW ALL MEN BY THESE PRESENTS, that
for and consideration of the sum of
Dollars ($ )
paid to
by Monroe County, Florida receipt of which is hereby acknowledged, do(es) hereby release
and quit claim to Monroe County, Florida, the Owner, its successors or assigns, all liens, lien
rights, claims or demands of any kind whatsoever which
has (have) or might have against the property, building, and/or improvements, on account of
labor performed, material furnished, and/or for any incidental expense for the construction of:
thereon or in otherwise improving said property situated as above described.
IN WITNESS WHEREOF THIS day of , 20
Witness Name of Company
Witness Signature, Title
Notary Public
My commission expires:
APPLICATION FOR PAYMENT 01027-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
13263)'3928=
AFFIDAVIT AND PARTIAL RELEASE OF LIEN
APPLICATION NO.: PERIOD ENDING DATE: APPLICATION DATE:
/23;%001)2&=8,)7)46)7)287
, that the undersigned, for and in consideration of the
payment of the sum $ , to be paid to the undersigned, hereby releases,
13263)'3928=3;2)6
acquits, satisfies and forever discharges, , their successors and
assigns from all suits, causes of action, liens, lien rights, claims or demands of any kind
whatsoever, to the extent of the payment to date on account of the furnishing of labor, material
or services for the improvement of the following described property:
As part of this PARTIAL RELEASE, THAT UNDERSIGNED HEREBY CERTIFIES the following:
THAT the contract of the undersigned, as adjusted by all increases and decreases, is in the
amount of $ , as of the date of the Partial Release and the undersigned has
received
$ as payment on the adjusted contract amount as of the date of this Partial
Release.
THAT all supplies of labor, material or services furnished to, or for the benefit of the
undersigned for improvement to the subject property have been paid in full. Any and all
suppliers of labor, material or services for improvement to the subject property, who have not
been paid in full are listed below with the amount owing each, claimed by each and the reason
for non-payment: (If none, write "NONE")
'0%-1%28%13928(9)%13928'0%-1)(6)%732*362324%=1)28
__________
THAT all taxes imposed by all government agencies have been paid and discharged.
THAT all funds have been collected for FICA and withholding taxes have been properly
deposited with appropriate agencies or paid to the government as required by law.
THAT the undersigned has no other claims for money against the OWNER other than those
Subcontractors'/Suppliers' amounts remaining due and owing on the adjusted contract balance
as reflected above.
THAT the undersigned further certifies that if there is a Guarantee, Warranty or Maintenance
Agreement in connection with the labor and material furnished by it, that this payment and
PARTIAL RELEASE shall not release the undersigned from any obligations under such
Guarantee, Warranty, or Maintenance Agreement.
WITNESS MY HAND THIS day of , 20
Witness Name of Company
Witness Signature, Title
APPLICATION FOR PAYMENT 01027-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
%08)62%8)7
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division-1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for Alternates.
B. Definition: An alternate is an amount proposed by Proposer and stated on the Proposal
Form for certain construction activities defined in the Proposal Requirements that may
be added to or deducted from Base Proposal amount if the Owner decides to accept a
corresponding change in either the installation or methods described in Contract
Documents.
C. Coordination: Coordinate related Work and modify or adjust adjacent Work as necessary
to ensure that Work affected by each accepted Alternate is complete and fully integrated
into the project.
D. Notification: Immediately following the award of the Contract, prepare and distribute to
each party involved, notification of the status of each Alternate. Indicate whether
Alternates have been accepted, rejected or deferred for consideration at a later date.
Include a complete description of negotiated modifications to Alternates.
1. Include as part of each Alternate, miscellaneous devices, accessory objects and
similar items incidental to or required for a complete installation whether or not
mentioned as part of the Alternate.
End of Section 01030
ALTERNATES 01030-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463.)'8'336(-2%8-32
PART I GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and
Supplementary Conditions and other Division 1 Specification Sections, apply to
this Section.
1.2 SUMMARY
A. This Section specifies administrative and supervisory requirements of the
Contractor necessary for Project coordination including, but not necessarily
limited to:
1. Coordination
2. Administrative and supervisory personnel
3. General installation provisions
4. Cleaning and protection
B.
C. Progress meetings, coordination meetings and pre-installation conferences are
D.
1.3 COORDINATION
A. Coordination: Coordinate construction activities included under various Sections
of these Specifications to assure efficient and orderly installation of each part of
the Work. Coordinate construction operations included under different Sections
of the Specifications that are dependent upon each other for proper installation,
connection, and operation.
1. Where installation of one part of the Work is dependent on installation of
other components, either before or after its own installation, schedule
construction activities in the sequence required to obtain the best results.
2. Where availability of space is limited, coordinate installation of different
components to assure maximum accessibility for required maintenance,
service and repair.
3. Make adequate provisions to accommodate items scheduled for later
installation.
B. Where necessary, prepare memoranda for distribution to each party involved
outlining special procedures required for coordination. Include items as required
notices, reports, and attendance at meetings.
PROJECT COORDINATION 01040-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1. Prepare similar memoranda for the Owner and separate Contractors
where coordination of their work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required
administrative procedures with other construction activities to avoid conflicts and
ensure orderly progress of the Work. Such administrative activities include, but
are not limited to, the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project Close-out activities.
D. Conservation: Coordinate construction activities to ensure that operations are
carried out with consideration given to conservation of energy, water, and
materials.
1. Salvage materials and equipment involved in performance of, but not
actually incorporated in, the Work. Refer to other sections for disposition
of salvaged materials that
1.4 SUBMITTALS
A. Coordination Drawings: Prepare and submit coordination Drawings where close
and careful coordination is required for installation of products and materials
fabricated off-site by separate entities, and where limited space availability
necessitates maximum utilization of space for efficient installation of different
components.
1. Show the interrelationship of components shown on separate Shop
Drawings.
2. Indicate required installation sequences.
3. Comply with r
B. Staff Names: Within 15 days of Notice to Proceed, submit a list of the
personnel in attendance at the site; identify individuals, their duties and
responsibilities; list their addresses and telephone numbers.
1. Post copies of the list in the Project meeting room, the temporary field
office, and at each temporary telephone.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL INSTALLATION PROVISIONS
PROJECT COORDINATION 01040-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Inspection of Conditions: Require the Installer of each major component to inspect
both the substrate and conditions under which Work is to be performed. Do not
proceed until unsatisfactory conditions have been corrected in an acceptable
manner.
recommendations, to the extent that those instructions and recommendations
are more explicit or stringent than requirements contained in Contract
Documents.
Inspect materials or equipment immediately upon delivery and again prior to
installation. Reject damaged and defective items.
Provide attachment and connection devices and methods necessary for security Work.
Secure Work true to line and level. Allow for expansion and building
movement.
Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in
exposed Work to obtain the best visual effect. Refer questionable choices to
Project Management for final decision.
Recheck measurements and dimensions, before starting each installation.
Install each component during weather conditions and Project status that will ensure
the best possible results. Isolate each part of the completed construction from
incompatible material as necessary to prevent deterioration.
Coordinate temporary enclosures with required inspections and tests, to minimize the
necessity of uncovering completed construction for that purpose.
Mounting Heights: Where mounting heights are not indicated, install individual
components at standard mounting heights recognized within the industry for
the particular application indicated. Refer questionable mounting height
decisions to Project Management for final decision.
3.1 CLEANING AND PROTECTIONS
A. During handling and installation, clean and protect construction in progress and
adjoining materials in place. Apply protective covering where required to ensure
protection from damage or deterioration at Substantial Completion.
B. Clean and maintain completed construction as frequently as necessary through
the remainder of the construction period. Adjust and lubricate operable
components to ensure operability without damaging effects.
C. Limiting Exposures: Supervise construction activities to ensure that no part of
the construction completed or in progress, is subject to harmful, dangerous,
damaging, or otherwise deleterious exposure during the construction period.
Where applicable, such exposures include, but are not limited to, the following:
PROJECT COORDINATION 01040-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
LIMITING EXPOSURES
1. Excessive static or dynamic loading
2. Excessive internal or external pressures
3. Excessively high or low temperatures
4. Thermal shock
5. Excessively high or low humidity
6. Air contamination or pollution
7. Water
8. Solvents
9. Chemicals
10. Light
11. Radiation
12. Puncture
13. Abrasion
14. Heavy traffic
15. Soiling, staining and corrosion
16. Bacteria
17. Rodent and insect infestation
18. Combustion
19. Electrical current
20. High speed operation
21. Improper lubrication
22. Unusual wear or other misuse
23. Contract between incompatible materials
24. Destructive testing
25. Misalignment
26. Excessive weathering
27. Unprotected storage
28. Improper shipping or handling
29. Theft
30. Vandalism
End of Section 01040
PROJECT COORDINATION 01040-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
'988-2+%2(4%8',-2+
PART 1 - GENERAL
1.1. RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 1 Specification Sections, apply to
this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements of the
Contractor for cutting and patching.
B. Related Sections: The following Sections contain requirements that relate to this
Section:
1. Division 1 Section: "Coordination" for procedures for coordination cutting
and patching with other construction activities.
2. Division 2 Section: "Selective Demolition" for demolition of selected
portions of the building for alterations.
3. Refer to other Sections for specific requirements and limitations
applicable to cutting and patching individual parts of the Work.
a. Requirements of this Section apply to mechanical and electrical
installations.
4. Describe anticipated results in terms of changes to existing construction.
Include changes to structural elements and operating components as well
as changes in the building's appearance and other significant visual
elements.
5. List products to be used and firms or entities that will perform Work.
6. Indicate dates when cutting and patching will be performed.
7. Utilities: List utilities that cutting and patching procedures will disturb or
affect. List utilities that will be relocated and those that will be temporarily
out-of-service. Indicate how long service will be disrupted.
8. Where cutting and patching involves adding reinforcement to structural
elements, submit details and engineering calculations showing integration
of reinforcement with the original structure.
9. Approval by Project Management to proceed with cutting and patching
does not waive right to later require complete
removal and replacement of unsatisfactory work.
1.3 NOT USED
1.4 QUALITY ASSURANCE
CUTTING AND PATCHING 01045-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A. Requirements for Structural Work: Do not cut and patch structural elements in a
manner that would change their load-carrying capacity or load-deflection ratio.
1. Obtain approval of the cutting and patching bid before cutting and
patching the following structural elements:
a. Foundation construction.
b. Bearing and retaining walls.
c. Structural concrete.
d. Structural steel.
e. Lintels
f. Timber and primary wood framing.
g. Structural decking.
h. Stair systems
i. Miscellaneous structural metals.
B. Operational Limitations: Do not cut and patch operating elements or related
components in a manner that would result in reducing their capacity to perform
as intended. Do not cut and patch operating elements or related components in
a manner that would result in increased maintenance or decreased operational
life or safety.
1. Obtain approval of the cutting and patching bid before cutting and
patching the following operating elements or safety related systems.
a. Fire protection systems.
b. Control systems.
c. Communication systems.
d. Electrical wiring systems.
C. Visual Requirements: Do not cut and patch construction exposed on the exterior
or in occupied spaces in a manner that would, in Project Management's opinion,
reduce the building's aesthetic qualities. Do not cut and patch construction in a
manner that would result in visual evidence of cutting and patching. Remove and
replace construction cut and patched in a visually unsatisfactory manner.
1. If possible retain the original Installer or fabricator to cut and patch the
exposed Work listed below. If it is impossible to engage the original
Installer or fabricator, engage another recognized experienced and
specialized firm.
a. Stonework and stone masonry.
b. Ornamental metal.
1.5 WARRANTY
A. Existing Warranties: Replace, patch, and repair material and surfaces cut or
damaged by methods and with materials in such a manner as not to void any
warranties required or existing.
PART 2 - PRODUCTS
CUTTING AND PATCHING 01045-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
2.1 MATERIALS, GENERAL
PART 3 - EXECUTION
3.1 INSPECTION
A. Examine surfaces to be cut and patched and conditions under which cutting and
patching is to be performed before cutting. If unsafe or unsatisfactory conditions
are encountered, take corrective action before proceeding.
1. Before proceeding, meet at the Project Site with parties involved in cutting
and patching, including mechanical and electrical trades. Review areas
of potential interference and conflict. Coordinate procedures and resolve
potential conflicts before proceeding.
3.2 PREPARATION
A. Temporary Support: Provide temporary support of work to be cut.
B. Protection: Protect existing construction during cutting and patching to prevent
damage. Provide protection from adverse weather conditions for portions of the
Project that might be exposed during cutting and patching operations.
C. Avoid interference with use of adjoining areas or interruption of free passage to
adjoining areas.
D. Avoid cutting existing pipe, conduit, or ductwork serving the building but
scheduled to be removed or relocated until provisions have been made to bypass
them.
3.3 PERFORMANCE
A. General: Employ skilled workmen to perform cutting and patching. Proceed with
cutting and patching at the earliest feasible time and complete without delay.
1. Cut existing construction to provide for installation of other components or
performance of other construction activities and the subsequent fitting
and patching required to restore surfaces to their original condition.
B. Cutting: Cut existing construction methods least likely to damage elements
retained or adjoining construction. Where possible, review proposed procedures
with the original Installer; comply with the original Installer's recommendations.
1. In general, where cutting, use hand or small power tools designed for
sawing or grinding, not hammering and chopping. Cut holes and slots as
small as possible, neatly to size required, and with minimum disturbance
of adjacent surfaces. Temporarily cover openings when not in use.
2. To avoid marring existing finished surfaces, cut or drill from the exposed
or finished side into concealed surfaces.
CUTTING AND PATCHING 01045-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
3. Cut through concrete and masonry using a cutting machine, such as a
Carborundum saw or a diamond-core drill.
4. Comply with requirements of applicable Division 2 Sections where cutting
and patching requires excavating and backfilling.
5. Where services are required to be removed, relocated, or abandoned, by-
pass utility services, such as pipe or conduit, before cutting. Cut-off pipe
or conduit in walls or partitions to be removed. Cap, valve, or plug and
seal the remaining portion of pipe or conduit to prevent entrance of
moisture or other foreign matter after by-passing and cutting.
C. Patching: Patch with durable seams that are as invisible as possible. Comply
with specified tolerances.
1. Where feasible, inspect and test patched areas to demonstrate integrity of
the installation.
2. Restore exposed finishes of patched areas and extend finish restoration
into retained adjoining construction in a manner that will eliminate
evidence of patching and refinishing.
3. Where removing walls or partitions extends one finished area into another
area, patch and repair floor.
3.4 CLEANING
A. Clean areas and spaces where cutting and patching are performed. Completely
remove paint, mortar, oils, putty, and similar items. Thoroughly clean piping,
conduit, and similar features before applying paint or other finishing materials.
Restore damaged piping covering to its original condition.
End of Section 01045
CUTTING AND PATCHING 01045-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
*-)0()2+-2))6-2+
PART 1- GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Divisions 1 Specification Sections, apply to
this Section.
1.2 SUMMARY
A. General: This Section specifies administrative and procedural requirements of
the Contractor for field-engineering services including, but not limited to, the
following:
1. Land survey work.
2. Civil-engineering services.
3. Damage surveys.
4. Geotechnical monitoring.
B. Related Sections: The following Sections contain requirements that are related
to this Section:
1. Division 1 Section "Coordination" for procedures for coordinating field
engineering with other construction activities.
2. Division 1 Section "Submittals" for submitting Project record surveys.
3. Division 1 Section "Project Closeout" for submitting final property survey
with Project Record Documents and recording of Owner-accepted
deviations from indicated lines and levels.
1.3 SUBMITTALS
A. Certificates: Submit a certificate signed by the land surveyor or professional
engineer certifying the location and elevation of improvements.
B. Project Record Documents: Submit a record of Work performed and record
survey data as required under provisions of "Submittals" and "Project Closeout"
Sections.
1.4 QUALITY ASSURANCE
A. Surveyor Qualifications: Engage a land surveyor registered in the state where
the Project is located, to perform required land-surveying services.
B. Engineer Qualifications: Engage an engineer of the discipline required, licensed
in the state where the Project is located, to perform required engineering
services.
FIELD ENGINEERING 01050-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Identification: The Owner will identify existing control points and property
line corner stakes.
B. Verify layout information shown on the Drawings, in relation to the property
survey and existing benchmarks, before proceeding to lay out the Work. Locate
and protect existing benchmarks and control points. Preserve permanent
reference points during construction.
1. Do not change or relocate benchmarks or control points without prior
written approval. Promptly report lost or destroyed reference points or
requirements to relocate reference points because of necessary changes
in grades or locations.
2. Promptly replace lost or destroyed Project control points. Base
replacements on the original survey control points.
C. Establish and maintain a minimum of 2 permanent benchmarks on the site,
referenced to data established by survey control points.
1. Record benchmark locations, with horizontal and vertical data, on Project
Record Documents.
D. Existing Utilities and Equipment: The existence and location of underground and
other utilities and construction indicated as existing are not guaranteed. Before
beginning site work, investigate and verify the existence and location of
underground utilities and other construction.
1. Prior to construction, verify the location and invert elevation at points of
connection of sanitary, sewer, storm sewer, and water-service piping.
3.2 PERFORMANCE
A. Work from lines and levels established by the property survey. Establish
benchmarks and markers to set lines and levels at each story of construction and
elsewhere as needed to locate each element of the Project. Calculate and
measure required dimensions within indicated or recognized tolerances. Do not
scale Drawings to determine dimensions.
1. Advise entities engaged in construction activities of marked lines and
levels provided for their use.
2. As construction proceeds, check every major element for line, level, and
plumb.
FIELD ENGINEERING 01050-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. Surveyor's Log: Maintain a surveyor's log of control and other survey work.
Make this log available for reference.
1. Record deviations from required lines and levels, and advise Project
Management when deviations that exceed indicated or recognized
tolerances are detected. On Project Record Drawings, record deviations
that are accepted and not corrected.
2. On completion of foundation walls, major site improvements, and other
work requiring field-engineering services, prepare a certified survey
showing dimensions, locations, angles, and elevations of construction
and site work.
C. Site Improvements: Locate and lay out site improvements, including pavements,
stakes for grading, fill and topsoil placement, utility slopes, and invert elevations.
D. Building Lines and Levels: Locate and lay out batter boards for structures,
building foundations, column grids and locations, floor levels, and control lines
and levels required for mechanical electrical work.
E. Existing Utilities: Furnish information necessary to adjust, move, or relocate
existing structures, utility poles, lines, services, or other appurtenances located in
or affected by construction. Coordinate with local authorities having jurisdiction.
End of Section 01050
FIELD ENGINEERING 01050-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463.)'81))8-2+7
PART 1 - GENERAL
1. SUMMARY
A. Section includes:
1. Project meetings
2. PROJECT MANAGEMENT
A. Project Management shall schedule and administer pre-construction meeting,
periodic progress meetings, and specially called meetings throughout progress of
the Work.
1. Prepare agenda for meetings.
2. Provide notice of each meeting 24 hours in advance of meeting date, or
provide as much advance notice as possible.
3. Make physical arrangements for meetings.
4. Preside at meetings.
5. Record the minutes; include significant proceedings and decisions.
6. Reproduce and distribute copies of minutes.
a. To participants in the meeting.
b. To parties affected by decisions made at the meeting.
c. To Project Management staff as needed.
B. Representatives of the Contractors, subcontractors and suppliers attending
meetings shall be qualified and authorized to act on behalf of the entity each
represents.
C. The Architect and the Owner's Representative may attend meetings to ascertain
that the Work is expedited consistent with the Contract Documents and
construction schedules.
3. PRE-CONSTRUCTION MEETING
A. Location: A central site designated by Project Management.
B. Attendance:
1. Monroe County Project Management designee.
2. The Architect and his professional consultants (as required).
3. The Contractor's Superintendent.
4. Major subcontractors.
5. Major suppliers.
6. Others as appropriate.
C. Suggested Agenda:
1. Distribution and discussion of:
a. List of major subcontractors and suppliers.
b. Projected Construction Schedules.
PROJECT MEETINGS 01200-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
2. Critical Work sequencing.
3. Major equipment deliveries and priorities.
4. Project Coordination.
a. Designation of responsible personnel.
5. Procedures and processing of:
a. Field decisions.
b. Bid requests.
c. Submittals.
d. Change Orders.
e. Applications for Payment.
6. Adequacy of distribution of the Contract Documents.
7. Procedures for maintaining Record Documents.
8. Use of premises:
a. Office, work and storage areas.
b. The Owner's requirements.
9. Construction facilities, controls and construction aids.
10. Temporary utilities.
11. Safety and first-aid procedures.
12. Security procedures.
13. Housekeeping procedures.
14. Distribute meeting minutes within (3) days.
4. PERIODIC PROGRESS MEETINGS
A. The Contractor's Project Manager and/or Superintendent shall be required to
attend a periodic scheduled meeting at the discretion of Monroe County Project
Management.
B. Location of the meetings: A central site designated by Project Management,
typically it will be at the project site.
C. Attendance:
1. Monroe County Project Management designee.
2. The Architect and his professional consultants as needed.
3. Contractors as appropriate to the agenda.
4. Suppliers as appropriate to the agenda.
5. Others.
D. Suggested Agenda:
1. Distribute meeting minutes.
2. Approval of the minutes.
3. Review of Work progress since previous meeting.
4. Field observations, problems, conflicts, Requests for Information (RFI).
5. Problems which impede Construction Schedule.
6. Review of off-site fabrication, delivery schedules.
7. Corrective measures and procedures to regain projected schedule.
8. Revisions to Construction Schedule.
9. Progress, schedule, during succeeding Work period.
10. Coordination of schedules.
11. Review submittal schedules.
12. Maintenance of quality standards.
13. Pending changes, substitutions and Change Order Requests (COR).
PROJECT MEETINGS 01200-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
14. Review proposed changes for:
a. Effect on Construction Schedule and on completion date.
b. Effect on other contracts of the Project.
15. Other business.
E. Revisions to minutes:
1. Unless published minutes are challenged in writing prior to the next
regularly scheduled progress meeting, they will be accepted as properly
stating the activities and decisions of the meeting.
2. Persons challenging published minutes shall reproduce and distribute
copies of the challenge to all indicated recipients of the particular set of
minutes.
3.
at the next regularly scheduled meeting.
End of Section 01200
PROJECT MEETINGS 01200-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
79&1-88%07
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. The Contractor shall submit to Project Management, shop drawings,
product data, certifications and samples required by the technical
sections.
2. The Contractor shall prepare and submit a separate schedule listing
dates for submission and dates for review.
B. Related Sections:
1. Section 00750 - GENERAL CONDITIONS
2. Individual submittals required: refer to each specific section, for
certifications, shop drawings, product data and sample requirements.
1.2 SUBMITTAL SCHEDULE
A. The Contractor shall submit within ten (10) days of award of the Contract, and
prior to proceeding with the site work, a preliminary "Submittal Schedule" to
Project Management for review, modification and response. No payment
applications will be processed prior to finalizing the submittal schedule. The
"Submittal Schedule" shall contain the following information for all required
submittals on both paper and electronic PDF.
1. Specification Section number and name.
2. Specification Section paragraph identification which describes submittal
requirement.
3. Submittal information required, (i.e., sample, test data, shop drawing,
etc.).
B. The Contractor shall also supply the following dates in order to meet the project
schedule.
1. Date submittal is scheduled to be submitted.
2. Date contractor has scheduled to order material or equipment or the
submittal item.
3. Date contractor has scheduled delivery to job-site of material or
equipment or the submittal item.
4. Add any remarks or unique items that Project Management should be
aware of.
C. The Contractor shall allow a minimum of two (2) weeks for review of submittal by
Project Management (in calendar days).
D. The submittal master record will then be used to track submittals within the
process.
SUBMITTALS 01301-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1.3 SHOP DRAWINGS
A. Provide shop drawings as complete legible submittals (no partial sets) on original
drawings or information prepared solely by the fabricator or supplier. Deviation
from complete submittals will only be allowed by pre-arranged method.
B. Do not reproduce the Contract Drawings for shop drawing submittals.
C. Sheet sizes shall be the same for all sheets and shall not exceed the size of the
Contract Drawings.
D. Each print shall have blank spaces large enough to accept 4" x 4" review stamps
of Project Management and the Contractor.
E. Each print shall carry the following information:
1. Project name and contract number.
2. Date.
3. Names of:
a. The Architect
b. Project Management
c. The Contractor
d. Supplier
e. Manufacturer
4. Identification of product or material.
5. Relation to adjacent structure or materials.
6. Field dimensions, clearly stated as such.
7. Specification Section number.
8. Contractor to verify that product meets or exceeds applicable standards
listed in document.
9. Identification of deviations from Contract Documents.
10. Reference to construction drawings by drawing number and/or detain
number.
F. The contractor shall submit seven (7) sets to Project Management. Project
Management will check the submission and forward five (5) sets to the
Contractor. After corrections are made, the requested number of sets of shop
drawings issued "For Construction Use" will be distributed to Project
Management and other trade contractors by the Contractor prior to the start of
the Work.
1.4 PRODUCT DATA
A. Product data such as catalog cuts, brochures or manufacturer's sheets will be
submitted and adequately identified to Project Management. Submit seven (7)
copies of product data to Project Management.
B. Modify product data sheets to delete information which is not applicable to the
Project. Provide additional information if necessary to supplement standard
information.
SUBMITTALS 01301-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
C. The contractor shall submit seven (7) sets to Project Management. Project
Management will check and return five (5) copies to the Contractor after review.
1.5 SAMPLES
A. Provide samples to illustrate materials, equipment or workmanship, and to
establish standards by which completed work may be judged.
B. Construct mock-ups as required by the technical sections, at the Project Site in a
location designated by Project Management. Construct mock-ups, including
adjacent work required, to demonstrate the final appearance of the Work.
C. The contractor shall submit (3) samples to Project Management and (1) will be
returned to the contractor after review/return from Project Management.
1.6 CERTIFICATIONS
A. Provide certifications as required by various technical sections on the
Contractor's letterhead stationery. Certifications shall be identified to this Project,
dated and bear Contractor's signature in the same format used for the
Owner/Contractor agreement.
B. Clearly identify the materials referenced and state that the material and the
intended installation methods, where applicable, are in compliance with the
Contract Documents. Attach manufacturer's affidavits where applicable.
C. The Contractor shall submit one (1) original and six (6) copies to Project
Management. Project Management will retain two (2) sets and the balance
returned to the Contractor after review.
1.7 THE CONTRACTOR'S RESPONSIBILITIES
A. Before making submittals to Project Management, review each submittal, make
changes or notations as necessary to conform to the Contract Documents,
identify such review with review stamp and forward reviewed submittal with
comments to Project Management for review. Return submittals not meeting
Contract requirements to subcontractors and do not forward such submittals to
Project Management.
B. Submit catalog sheets, product data, shop drawings and where specified, submit
calculations, material samples, color chips or charts, test data, warranties and
guarantees all at the same time for each submittal item.
C. Verify field measurements and product catalog numbers or similar data.
D. Clearly identify on the submittal and transmittal to Project Management in writing
of deviations in submittals from the requirements of the Contract Documents.
E. After Project Management's review, distribute copies with one copy to be
maintained at the Project Site for reference use and other copies distributed to
suppliers and fabricators.
SUBMITTALS 01301-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
F. Do not begin the Work which requires submittals until return of submittals with
Project Management's stamp and initials indicating review.
G. The Contractor's responsibility for errors and omissions in submittals is not
relieved by Project Management's review of submittals.
H. The Contractor's responsibility for deviations in submittals from requirements of
the Contract Documents is not relieved by Project Management review of
submittals unless Project Management gives written acceptance of specific
deviations.
I. All submittles shall be submitted to Monroe County Project Management and
Consultents in Adobe PDF format.
1.8 PROJECT MANAGEMENT
A. Project Management will review submittals with reasonable promptness,
checking only for conformance with the design compliance of the Project and
compliance with information given in the Contract Documents.
B. Project Management will make changes or notations directly on the submittal,
identify such review with his review stamp, obtain and record the Record File
copy and return the submittal to the Contractor, with copies to Project
Management.
C. Project Management will return to the Contractor, without review, all submittals
not bearing the Contractor's review stamp or not showing it has been reviewed
by the Contractor.
End of Section 01301
SUBMITTALS 01301-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463+6)777',)(90)7
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Contractor submission of Progress schedules.
2. Contractor submission of Revisions to schedules.
B. Related sections:
1. Scope of work.
C. Description:
1. Progress Schedules: promptly after award of the Contract and prior to
proceeding with the site work, prepare and submit to Project Management
for approval, construction progress schedules for the work, with sub-
schedules of related activities which are essential to its progress. Also
incorporate manpower loading related to each activity on the construction
schedule.
2. Revisions to Schedule: submit revised/updated progress schedules with
each payment application.
1.2 FORMAT
A. Prepare Progress Schedules, Contractor to submit format of schedule for
approval by Project Management.
1.3 CONTENT
A. Indicate complete sequence of construction by activity, with dates for beginning
and completion of each element of construction.
B. Identify work of separate stages and other logically grouped activities.
C. Provide sub-schedules to define critical portions of the entire schedule.
D. Submit separate schedule of submittal dates for shop drawings, product data,
and samples, including the Owner furnished products and products identified
under allowances and dates reviewed submittals will be required from the
Architect. Reference Section 01301 - Submittals.
1.4 REVISIONS TO SCHEDULES
A. Indicate progress of each activity to date of submittal, and projected completion
date of each activity.
PROGRESS SCHEDULES 01310-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. Identify activities modified since previous submittal, major changes in scope, and
other identifiable changes.
1. Major changes in scope.
2. Activities modified since previous submission.
3. Revised projections of progress and completion.
4. Other identifiable changes.
C. Provide a narrative report as needed to define:
1. Problem areas, anticipated delays and the impact on the schedule.
2. Corrective action recommended and its effect.
3. The effect of changes on schedules of other prime contractors.
1.5 SUBMITTALS
A. Submit initial schedules within seven (7) days after receipt of the Contract Notice
to Proceed.
1. Project Management will review schedules and return approved copy.
2. Submit revised Progress Schedules with each Application for Payment.
1.6 DISTRIBUTION
A. Distribute copies of the reviewed schedules to:
1. Job site file.
2. Subcontractors.
3. Other concerned parties.
B. Instruct recipients to report promptly to the Contractor, in writing, any problems
anticipated by the projections shown in the schedules.
Note: It is not incumbent upon Project Management to notify the Contractor when to
begin, to cease, or to resume work nor to give early notice of faulty or defective
work, or in any way to superintend so as to relieve the Contractor of responsibility
or of any consequence of neglect or carelessness.
End of Section 01310
PROGRESS SCHEDULES 01310-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
7',)(90)3*:%09)7
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes: Contractor submission of a Schedule of Values.
1. The Schedule of Values allocated to the various portions of the Workby
Divisions shall be submitted to Project Management within three (3) days
after Notice to Proceed.
2. No item in the Schedule of Values shall exceed $25,000.00 without prior
approval from Monroe County Project Management.
3. Upon request of Project Management, revise and/or support the values
with data which will substantiate their correctness.
4. The Schedule of Values forms the basis for the Contractor's Applications
for Payment.
5. The Schedule of Values shall be the basis for the amount of credit to be
allowed by the Contractor to the Owner as per 5.6.1 of the Contract.
1.2 FORM AND CONTENT OF SCHEDULE OF VALUES
A. Type schedule on AIA G703 Form; the Contractor's standard forms and
automated printout will be considered by Project Management upon the
Contractor's request. Identify schedule with:
1. Title of Project and location
2. Architect/Engineer
3. Name and Address of the Contractor
4. Contract designation
5. Date of submission
B. List the installed value of the component parts of the Work in sufficient detail to
serve as a basis for computing values for progress payments during construction.
C. Follow the Specifications as the format for listing component items.
1. Identify each line item with the number and title of the respective major
section of the Specifications.
D. Itemize separate line item cost for each of the following general cost items:
1. Mobilization.
2. Bonds, Insurance and Permits.
3. Clean-up.
4. Submittals.
5. Safety.
E. For each major line item list sub-values of major products or operations under the
item.
F. For the various portions of the Work:
1. Include a directly proportional amount of the Contractor's overhead and
profit for each item.
SCHEDULE OF VALUES 01370-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
2. for items on which progress payments will be requested for stored
materials, break down the value into:
a. The cost of the materials, delivered and unloaded, with taxes paid.
b. The total installed value.
c. Attach vendor invoices.
d. No progress payments will be made for any materials stored off
site.
3. Submit a sub-schedule for each separate stage of work specified
G. The sum of values listed in the schedule shall equal the total Contract Sum.
1.3 REVIEW AND SUBMITTAL
A. After review by Project Management, revise and resubmit schedule (and
Schedule of Material Values) as required.
B. Resubmit revised schedule in same manner.
End of Section 01370
SCHEDULE OF VALUES 01370-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
(%-0='327869'8-326)43687
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Requirement for Daily Construction Reports by the General Contractor.
2. Scheduled submission times for Daily Construction Reports.
1.2 FORM AND CONTENT OF DAILY CONSTRUCTION REPORTS
A. Daily Construction Reports shall be submitted by the General Contractor
performing work on the project. We have provided a form for your use at the end
of this section. If you chose to use your own form, all the information asked for on
the Daily Construction Report form included in this section, must be included on
your form. Items to be addressed on the Report are:
1. Title of Project
2. Name of Contractor
3. Date and day of Report information. For example, you performed work
on Thursday, February 14, 2008, so you would therefore use "Thursday,
2/14/08." This holds true even if you did not complete filling out the
Report until Friday, 2/15/08.
4. Contract designation.
5. Note any major Shipments received on that particular day.
6. Note major equipment used that day.
7. Note manpower used, and designate what trades. For example, if you
were the mechanical contractor, you would also list how many insulators,
pipe fitters, etc., that you were also managing, even if they were
subcontractors. In addition, list the names of the subcontractors that
were on-site that day.
8. Note any deficiencies in your work, and corrective actions taken to
resolve the deficiencies.
9. Note any safety violations discovered, whether or not caused by your
forces.
10. Provide a full description of work performed that day, by all
subcontractors, and or employees, currently working on the project.
Furthermore, be sure to include any problems or unusual conditions
discovered.
11. Report is to be signed by the authorized representative of the contractor,
and should the signature not be legible, print the name of the signer next
to the signature.
1.3 SCHEDULE OF SUBMITTING DAILY REPORTS
A. Daily Reports are to be submitted to Project Management at the regularly
scheduled Project Meetings. Contractors are to submit the original of their
report, and should keep a copy for their records. Project Management
DAILY CONSTRUCTION REPORTS 01385-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
photocopying facilities are not to be used in the reproduction for submission of
the reports.
B. Should contractor fail to comply with these instructions, the contractor's payment
application for the following month will be held in abeyance until such time the
contractor properly submits the delinquent reports.
DAILY CONSTRUCTION REPORT
PROJECT: REPORT NO:
CONTRACTOR:
DATE TIME WEATHER TEMP.RANGE
EST. % OF COMPLETION CONFORMANCE WITH SCHEDULE (+,-)
WORK IN PROGRESS PRESENT AT SITE
OBSERVATIONS
ITEMS TO SATISFY
INFORMATION OR ACTION REQUIRED
ATTACHMENTS
REPORT BY:
DAILY CONSTRUCTION REPORTS 01385-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
6)59)78*36-2*361%8-32
6*-
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Notification to Architect and Project Management in the event errors, field
conflicts, and omissions are found in the Contract Documentsor
clarifications are necessary.
2. Utilization of (RFI) form.
B. Related Sections:
1. General Conditions Article 2.3
2. General Conditions Article 8.3.2
3. General Conditions Article 12.3
1.2 FORM AND CONTENT OF REQUEST FOR INFORMATION
A. All errors, field conflicts, and omissions in the Contract Documents shall be
brought to the attention of Architect/Engineer and Project Management
immediately. If clarifications are necessary, the request is to be conveyed to
Architect/Engineer and Project Management. Architect/Engineer and Project
Management will respond to the Contractor. The RFI is a tool established to
provide expedient clarifications of contract drawings, specifications or field
conflicts. It is not meant to be a substitute for good communication.
B. The RFI is not meant for formal notification of extra work. Reference General
Conditions paragraph 8.3.2 and 12.3 (see Supplementary General Conditions),
when formal correspondence is required for formal notification of time
extensions, and for cost change notifications.
C. The responses provided on the RFI form to the Contractor are considered by the
Owner to be clarifications and/or minor changes in the Work not involving an
adjustment in the Contract Sum or an extension of the Contract time per
Paragraph 12.4 of the Contract General Conditions. Should the Contractor
consider the RFI response requires extra work, notification in accordance with
Paragraph 12.3.1 of the Supplementary General Conditions is required.
1.3 UTILIZATION OF RFI FORM
A. The RFI form to be utilized is included at the end of this section, if you wish to use a
form of your own; it must contain the same information requested on our formand
sumitted in PDF format.
REQUEST FOR INFORMATION (RFI) 01395-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
REQUEST FOR INFORMATION (RFI) 01395-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
59%0-8='328630
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions, and other Division 1 Specification Sections, apply to
this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for quality
control services.
B. Quality control services include inspections, tests, and related actions, including
reports performed by Contractor, by independent agencies, and by governing
authorities. They do not include contract enforcement activities performed by
Architect.
C. Inspection and testing services are required to verify compliance with
requirements specified or indicated. These services do not relieve Contractor of
responsibility for compliance with Contract Document requirements.
D. Requirements of this Section relate to customized fabrication and installation
procedures, not production of standard products.
1. Specific quality control requirements for individual construction activities
are specified in the Sections that specify those activities. Requirements
in those Sections may also cover production of standard products.
2. Specified inspections, tests, and related actions do not limit Contractor's
quality control procedures that facilitate compliance with Contract
Document requirements.
3. Requirements for Contractor to provide quality control services required
by Owner, or authorities having jurisdiction are not limited by provisions of
this Section.
E. Related Sections: The following Sections contain requirements that are related
to this Section:
1. Division 1 Cutting and patching" specifies requirements for repair
and restoration of construction disturbed by inspection and testing
activities.
2. Division 1 Section "Submittals: specifies requirements for development of
a schedule of required tests and inspections.
1.3 RESPONSIBILITIES
QUALITY CONTROL 01400-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A. The contractor shall be responsible to secure, provide, and pay for all
inspections, test, and other quality-control services specified and required by the
contract or governing authorities. Costs for these services are included in the
Contract Sum. Any reference in the Contract Documents, Drawings, Front End
Documents or Technical Specifications indicating the Owner is responsible to
secure and pay for testing shall be disregarded and rendered null and void.
1. Where individual Sections specifically indicate that certain inspections,
tests, and other quality-control services are the Contractor's responsibility,
the Contractor shall employ and pay a qualified independent testing
agency to perform quality-control services. Costs for these services are
included in the Contract Sum.
a. Where the Owner has engaged a testing agency for testing and
inspecting part of the Work, and the Contractor is also required to
engage an entity for the same or related element, the Contractor
shall not employ the entity engaged by the Owner, unless agreed
to in writing by the Owner.
B. Re-testing: The Contractor is responsible for re-testing where results of
inspections, tests, or other quality-control services prove unsatisfactory and
indicate noncompliance with Contract Document requirements, regardless of
whether the original test was Contractor's responsibility.
1. The cost of re-testing construction, revised or replaced by the Contractor,
is the Contractor's responsibility where required tests performed on
original construction indicated noncompliance with Contract Document
requirements.
C. Associated Services: Cooperate with agencies performing required inspections,
tests, and similar services, and provide reasonable auxiliary services as
requested. Notify the agency sufficiently in advance of operations to permit
assignment of personnel. Auxiliary services required include, but are not limited
to, the following:
1. Provide access to the Work.
2. Furnish incidental labor and facilities necessary to facilitate inspections
and tests.
3. Take adequate quantities of representative samples of materials that
require testing or assist the agency in taking samples.
4. Provide facilities for storage and curing of test samples.
5. Deliver samples to testing laboratories.
6. Provide the agency with a preliminary design mix proposed for use for
materials mixes that require control by the testing agency.
7. Provide security and protection of samples and test equipment at the
Project Site.
D. Duties of the Testing Agency: The independent agency engaged to perform
inspections, sampling, and testing of materials and construction specified in
individual Sections shall cooperate with the Architect and the Contractor in
performance of the agency's duties. The testing agency shall provide qualified
personnel to perform required inspections and tests.
QUALITY CONTROL 01400-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1. The agency shall notify the Project Management and the Contractor
promptly of irregularities or deficiencies observed in the Work during
performance of its services.
2. The agency is not authorized to release, revoke, alter, or enlarge
requirements of the Contract Documents or approve or accept any portion
of the Work.
3. The agency shall not perform any duties of the Contractor.
1.4 SUBMITTALS
A. Unless the Contractor is responsible for this service, the independent testing
agency shall submit a certified written report, in duplicate, of each inspection,
test, or similar service to Project Management. If the Contractor is responsible
for the service, submit a certified written report, in duplicate, of each inspection,
test, or similar service through the Contractor.
1. Submit additional copies of each written report directly to the governing
authority, when the authority so directs.
2. Report Data: Written reports of each inspection, test, or similar service
include, but are not limited to, the following:
a. Date of issue.
b. Project title and number.
c. Name, address, and telephone number of testing agency.
d. Dates and locations of samples and tests or inspections.
e. Names of individuals making the inspection or test.
f. Designation of the Work and test method.
g. Identification of product and Specification Section.
h. Complete inspection or test data.
I. Test results and an interpretation of test results.
j. Ambient conditions at the time of sample taking and testing.
k. Comments or professional opinion on whether inspected or tested
Work complies with Contract Document requirements.
l. Name and signature of laboratory inspector.
m. Recommendation on re-testing.
1.5 QUALITY ASSURANCE
A. Qualifications for Service Agencies: Engage inspection and testing service
agencies, including independent testing laboratories, that are pre-qualified as
complying with the American Council of Independent Laboratories"
Recommended Requirements for Independent Laboratory Qualification" and that
specialize in the types of inspections and tests to be performed.
1. Each independent inspection and testing agency engaged on the Project
shall be authorized by authorities having jurisdiction to operate in the
state where the Project is located.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 01400-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
PART 3 - EXECUTION
3.1 REPAIR AND PROTECTION
A. General: Upon completion of inspection, testing, sample taking and similar
services, repair damaged construction and restore substrates and finishes.
Comply with Contract Document requirements for Division 1 Section "Cutting and
Patching".
B. Protect construction exposed by or for quality-control service activities, and
protect repaired construction.
B. Repair and protection is Contractor's responsibility, regardless of the assignment of
responsibility for inspection, testing, or similar services.
End of Section 01400
QUALITY CONTROL 01400-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
8)78-2+0%&36%836=7)6:-')7
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Selection and payment
2. The Contractor submittals
3. Testing laboratory responsibilities
4. Testing laboratory reports
5. Limits on testing laboratory authority
6. The Contractor responsibilities
7. Schedule of inspections and tests
B. Section Includes:
1. Section 00750 - GENERAL CONDITIONS
2. Section 01700 - CONTRACT CLOSEOUT
3. Individual Specification Sections: inspections and tests required, and
standards for testing.
1.2 SELECTION AND PAYMENT
A. The Contractor shall be responsible to secure and pay for all testing services of a
qualified independent testing laboratory to perform specified inspections and
testing as indicated in Technical Specification Sections and as required by the
contract or any governing authorities. Any reference in the Contract Documents,
Drawings, Front End Documents or Technical Specification indicating the Owner
is responsible to secure and pay for testing shall be disregarded and rendered
null and void.
B. Employment of testing laboratory shall in no way relieve the Contractor of
obligation to perform the Work in accordance with requirements of the Contract
Documents.
1.3 QUALITY ASSURANCE
A. Testing laboratory: authorized to operate in the State of Florida.
B. Testing laboratory staff: maintain a full time registered Engineer on staff to
review services.
C. Testing Equipment: calibrated at reasonable intervals with devices of accuracy
traceable to either National Bureau of Standards (NBS) standards or accepted
values of natural physical constants.
D. Meet "Recommended Requirements for Independent Laboratory Qualification,"
published by American Council of Independent Laboratories.
TESTING LABORATORY SERVICES 01410-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1.4 TESTING LABORATORY RESPONSIBILITIES
A. Test samples of mixes.
B. Provide qualified personnel at the Site. Cooperate with the Project Management
and the Contractor in performance of services.
C. Perform specified inspection, sampling, and testing of products in accordance
with specified standards.
D. Ascertain compliance of materials and mixes with requirements of the Contract
Documents.
E. Promptly notify Project Management and the Contractor of observed irregularities
or non-conformance of the Work or products.
F. Perform additional inspections and tests required by the Project Management.
1.5 TESTING LABORATORY REPORTS
A. After each inspection and test, promptly submit copies of testing laboratory report
to Project Management and Contractor.
B. Include:
1. Date issued
2. Project title and number
3. Name of inspector
4. Date and time of sampling or inspection
5. Identification of product and Specifications Section
6. Location in the Project
7. Type of inspection or test
8. Date of test
9. Results of test
10. Conformance with the Contract Documents
C. When requested by Project Management, provide interpretation of test results.
1.6 LIMITS ON TESTING LABORATORY AUTHORITY
A. The testing laboratory may not release, revoke, alter, or enlarge on requirements
of the Contract Documents.
B. The testing laboratory may not approve or accept any portion of the Work.
C. The testing laboratory may not assume any duties of the Contractor.
D. The testing laboratory has no authority to stop the Work.
1.7 THE CONTRACTOR RESPONSIBILITIES
TESTING LABORATORY SERVICES 01410-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A. Deliver to the testing laboratory at designated location, adequate samples of
materials proposed to be used which require testing, along with proposed mix
designs.
B. Cooperate with testing laboratory personnel, and provide access to the Work and
to the manufacturer's facilities.
C. Provide incidental labor and facilities to provide access to the Work to be tested,
to obtain and handle samples at the Site or at source of products to be tested, to
facilitate tests and inspections, storage and curing of test samples.
D. Notify Project Management and the testing laboratory 24 hours prior to expected
time for operations requiring inspection and testing services.
E. Employ services of a separate qualified testing laboratory and pay for additional
samples and tests which are beyond the specified requirements.
1.8 RETEST RESPONSIBILITY
A. Where the results of required inspections, tests, or similar services prove
unsatisfactory and do not indicate compliance with the requirements of the Contract
Documents, the cost for any re-tests shall be the responsibility of the Contractor.
End of Section 01410
TESTING LABORATORY SERVICES 01410-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
6)*)6)2')78%2(%6(7%2(()*-2-8-327
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and
Supplementary Conditions and other Division 1 Specifications Sections, apply to
this Section.
1.2 DEFINITIONS
A. General: Basic Contract definitions are included in the conditions of this
Contract.
B.
schedules on the Drawings, or other Paragraphs or Schedules in the
Specifications, and similar requirements in the Contract Documents. Where
re used, it is to
help the reader locate the reference; no limitation on location is intended.
C.
Project Management
requested by Project Management
D. Project
Management
is limited to Project Managementnsibilities as stated in the
Conditions of the Contract.
E.
lawful orders issued by authorities having jurisdiction, as well as rules,
conventions, and agreements within the construction industry that control
performance of the Work.
F.
site, ready for unloading, unpacking, assembly, installation, and similar
G. to describe operations at project site including
applying, working to dimension, finishing, curing, protecting, cleaning, and similar
H.
I.
either as an employee, subcontractor, or contractor of lower tier for performance
of a particular construction activity, including installation, erection, application,
and similar operations. Installers are required to be experienced in the
operations they are engaged to perform.
1.
having a minimum of five previous projects similar in size and scope to
REFERENCE STANDARDS AND DEFINITIONS 01421-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
this Project, being familiar with the special requirements indicated, and
having complied with requirements of the authority having jurisdiction.
2. intended to imply that
certain construction activities must be performed by accredited or
unionized individuals of a corresponding generic name, such as
exclusively to tradespersons of the corresponding general name.
3. Assignment of Specialists: Certain Sections of the Specifications require
that specific construction activities shall be performed by specialists who
are recognized experts in the operations to be performed. The specialists
must be engaged for those activities, and assignments are requirements
over which the Contractor has no choice or option. Nevertheless, the
ultimate responsibility for fulfilling Contract requirements remains with the
Contractor.
a. This requirement shall not be interpreted to conflict with
enforcement of building codes and similar regulations governing
the Work. It is also not intended to interfere with local trade union
jurisdictional settlements and similar conventions.
J. Project Site is the space available to the contractor for performance of
construction activities, either exclusively or in conjunction with others performing
other work as part of the Project. The extent of the Project site is shown on the
Drawings and may or may not be identical with the description of the land on
which the Project is to be built.
K.
perform specific inspections or tests, either at the Project Site or elsewhere, and
to report on and, if required, to interpret results of those inspection or tests.
1.3 SPECIFICATION FORMAT AND CONTENT EXPLANATION
A. Specification Format: These Specifications are organized into Divisions and
-Divisionformat
and MASTER FORMAT numbering system.
B. Specification Content: This specification uses certain conventions in the use of
language and the intended meaning of certain terms, words, and phrases when
used in particular situations or circumstances. These conventions are explained
as follows:
1. Abbreviated Language: Language used in Specifications and other
Contract Documents is the abbreviated type. Words and meanings shall
be interpreted as appropriate. Words that are implied, but not stated shall
be interpolated as the sense required. Singular words will be interpreted
as plural and plural words interpreted as singular where applicable and
the context of the Contract Documents so indicates.
2. Imperative and streamlined language is used generally in the
Specifications. Requirements expressed in the imperative mood are to
be performed by the Contractor. At certain locations in the text, for clarity,
subjective language is used to describe responsibilities that must be
fulfilled indirectly by the Contractor, or by others when so noted.
a.
colon (:) is used within a sentence or phrase.
REFERENCE STANDARDS AND DEFINITIONS 01421-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1.4 INDUSTRY STANDARDS
A. Applicability of Standards: Except where the Contract Documents include more
stringent requirements, applicable construction industry standards have the same
force and effect as if bound or copied directly into the Contract Documents to the
extent referenced. Such standards are made a part of the Contract Documents
by reference.
B. Publication Dates: Comply with the standard in effect as of the date of the
Contract Documents.
C. Conflicting Requirements: Where compliance with two or more standards is
specified, and the standards may establish different or conflicting requirements
for minimum quantities or quality levels. Refer requirements that are different,
but apparently equal, and uncertainties to Project Management for a decision
before proceeding.
1. Minimum Quantity or Quality Levels: The quantity or quality level shown
or specified shall be the minimum provided or performed. The actual
installation may comply exactly with the minimum quantity or quality
specified, or it may exceed the minimum within reasonable limits. In
complying with these requirements, indicated numeric values are
minimum or maximum, as appropriate for the context of the requirements.
Refer uncertainties to Project Management for a decision before
proceeding.
D. Copies of Standards: Each entity engaged in construction on the Project is
construction activity. Copies of applicable standards are not bound with the
Contract Documents.
1. Where copies of standards are needed for performance of a required
construction activity, the Contractor shall obtain copies directly from the
publications source.
E. Abbreviations and Names: Trade association names and titles of general
standards are frequently abbreviated. Where such acronyms or abbreviations
are used in the Specifications or other Contract Documents, they mean the
recognized name of the trade association, standards generating organization,
authority having jurisdiction, or other entity applicable to the context of the text
Research Co., available in most libraries.
F. Abbreviations and Names:
Trade association names and titles of general standards are frequently
abbreviated. The following abbreviations and acronyms, as referenced in the
Contract Documents, mean the associated names. Names and addresses are
subject to change and are believed, but are not assured, to be accurate and up-
to-date as of the date of the Contract Documents.
AA Aluminum Association
AABC Associated Air Balance Council
REFERENCE STANDARDS AND DEFINITIONS 01421-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
AAMA American Architectural Manufacturers
AAN American Association of Nurserymen
(See ANLA)
AASHTO American Association of State Highway and Transportation Officials
ACI American Concrete Institute
ACPA America Concrete Pipe Association
AHA American Hardboard Association
AI Asphalt Institute
AIA the American Institute of Architects
AISC American Institute of Steel Construction
AITC American Institute of Timber Construction
ALA American Laminators Association
ALSC American Lumber Standards Committee
AMCA Air Movement and Control Association International, Inc.
ANLA American Nursery and Landscape Association
ANSI American National Standards Institute
APA APA-The Engineering Wood Association
(Formerly: American Plywood Association)
APA Architectural Precast Association
ARMA Asphalt Roofing Manufacturers Association
ASA Acoustical Society of America
ASC Adhesive and Sealant Council
ASHRAE American Society of Heating, Refrigerating and Air
Conditioning Engineers
ASME American Society of Mechanical Engineers
ASPA American Sod Producers Association
(See TPI)
ASTM American Society for Testing and Materials
REFERENCE STANDARDS AND DEFINITIONS 01421-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
AWI Architectural Woodwork Institute
AWPA American Wood Preservers' Association
AWS American Welding Society
BHMA Builders Hardware Manufacturers Association
BIA Brick Institute of America
EIMA EIFS Industry Members Association
EJMA Expansion Joint Manufacturers Association
FM Factory Mutual System
GA Gypsum Association
GANA Glass Association of North America
(Formerly: Flat Glass Marketing Association)
HMA Hardwood Manufacturers Association
(Formerly: Southern Hardwood Lumber Manufacturers Association)
HPVA Hardwood Plywood and Veneer Association
MFMA Maple Flooring Manufacturers Association
NAAMM National Association of Architectural Metal Manufacturers
NECA National Electrical Contractors Associations
NEI National Elevator Industry
NELMA Northeastern Lumber Manufacturers Association
NEMA National Electrical Manufacturers Association
NFPA National Fire Protection Association
NHLA National Hardwood Lumber Association
NLGA National Lumber Grades Authority
NOFMA National Oak Flooring Manufacturers Association
NWWDA National Wood Window and Door Association
(Formerly: National Woodwork Manufacturers Association)
PCA Portland Cement Association
PCI Precast/Prestressed Concrete Institute
REFERENCE STANDARDS AND DEFINITIONS 01421-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
RFCI Resilient Floor Covering Institute
SDI Steel Door Institute
SGCC Safety Glazing Certification Council
SIGMA Sealed Insulating Glass Manufacturing Association
SMACNA Sheet Metal and Air Conditioning Contractor's National
Association, Inc.
SPIB Southern Pine Inspection Bureau
SPRI SPRI (Formerly: Single Ply Roofing Institute)
SWRI Sealant, Waterproofing and Restoration Institute
TCA Tile Council of America
UL Underwriters Laboratories, Inc.
WCLIB West Coast Lumber Inspection
WIC Woodwork Institute of California
WWPA Western Wood Products Association
G. Federal Government Agencies: Names and titles of Federal Government standards-or
specification-producing agencies are often abbreviated. The following abbreviations and
acronyms referenced in the Contract Documents indicate names of standards-or
specification-producing agencies of the Federal Government. Names and addresses
are subject to change and are believed, but are not assured, to be accurate and up-to-
date as of the date of the Contract Documents.
OSHA Occupational Safety and Health Administration
(U.S. Department of Labor)
200 Constitution Ave., NW
Washington, DC 20210
End of Section 01421
REFERENCE STANDARDS AND DEFINITIONS 01421-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
8)1436%6=*%'-0-8-)7
PART 1 GENERAL
1.1 DESCRIPTION
A. Work included: Provide temporary facilities needed for the Work including, but
not necessarily limited to:
1. Temporary utilities such as water, electricity, and telephone.
2. Field office for
3. Sanitary facilities.
4. Enclosures such as tarpaulins, barricades, and canopies.
5. Temporary fencing of the construction site as required for public and
employee safety.
6. Project sign.
B. Related Work:
1. Documents affecting work of this Section include, but are not necessarily
limited to Supplementary Conditions, and Sections in Division 1 of these
Specifications.
1.2 PRODUCT HANDLING
A. Maintain temporary facilities and controls in proper and safe condition throughout
progress of the Work.
PART 2 - PRODUCTS
2.1 FIELD OFFICES AND SHEDS
A.
1. Provide a field office adequate in size and accommodation for
B. Sanitary facilities:
1. Provide temporary sanitary facilities in the quantity required for use by all
personnel.
2. Maintain in a sanitary condition at all times.
2.2 ENCLOSURES
A. Provide and maintain for the duration of construction all scaffolds, tarpaulins,
canopies, warning signs, steps, platforms, bridges, and other temporary
TEMPORARY FACILITIES 01500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
construction necessary for proper completion of the Work in compliance with
pertinent safety and other regulations.
B. Upon completion of the Work, remove job signs.
C. Except as otherwise specifically approved by the Owner, do not permit other
signs or advertising on the job site.
2.3 TEMPORARY FENCING
A. Provide and maintain for the duration of construction a temporary fence or
barricade of design and type needed to prevent entry onto the Work by the
public.
2.4 PROJECT SIGNS:
A.
Securely fasten the sign to the building or posts set in the ground as approved by
Project Management. A design provided by, or approved by Project Management
name; major ress, and telephone
PART 3 EXECUTION
3.1 MAINTENANCE AND REMOVAL
A. Maintain temporary facilities and controls as long as needed for safe and proper
completion of the Work.
B. Remove such temporary facilities, to include existing mobile home, and controls
as rapidly as progress of the Work will permit, or as directed by the Owner.
End of Section 01500
TEMPORARY FACILITIES 01500-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
'327869'8-32%-(7
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Construction aids.
2. Temporary enclosures.
1.2 REQUIREMENTS OF REGULATORY AGENCIES
B. Comply with Federal, State and local codes and regulations.
PART 2 - PRODUCTS
2.1 MATERIALS - GENERAL
A. Materials may be new or used, suitable for the intended use and shall not violate
requirements of applicable codes and standards.
2.2 CONSTRUCTION AIDS
A. The Contractor shall be responsible for furnishing, installing, maintaining, and
removing on completion of the Work all scaffolds, staging, ladders, stairs, ramps,
runways, platforms, railings, chutes, and other such facilities and equipment
required by his personnel to insure their safety and facilitate the execution of the
Work.
1. The Contractor shall comply with all Federal, State and local codes, laws
and regulations governing such construction aids.
2. The Contractor shall relocate such construction aids as required by the
progress of construction, by storage or work requirements, and to
accommodate the legitimate requirements of the Owner or Project
Management or other separate contractors employed at the site.
3. The Contractor shall completely remove temporary scaffolds, access,
platforms, and other such materials, facilities, and equipment, at the
completion of the Work or when construction needs can be met by the
use of the permanent construction, provided Project Management has
approved and authorized such use. The Contractor shall clean up and
shall repair any damage caused by the installation or by the use of such
temporary construction aids. The Contractor shall restore any permanent
facilities used for temporary purposes to their specified condition.
The foregoing obligations of the Contractor are in addition to his obligations under Article
10 of the General Conditions.
2.3 TEMPORARY ENCLOSURES
CONSTRUCTION AIDS 01520-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A. The Contractor shall be responsible for installing the permanent closure in an
opening in an exterior wall and shall be responsible for installing, maintaining,
and removing, as the Work progresses, a temporary weather-tight enclosure for
that opening as necessary to provide acceptable working conditions, to provide
weather protection for interior materials, to allow for effective temporary heating
and/or cooling, and to prevent entry of unauthorized persons.
1. The Contractor shall install such temporary enclosures as soon as is
practical after the opening is constructed or as directed by Project
Management.
2. Temporary enclosures shall be removable as necessary for the Work and
for handling of materials.
3. Temporary enclosures shall be completely removed when construction
needs can be met by the use of the permanent closures.
4. The Contractor responsible for providing, maintaining, and removing the
temporary enclosure shall clean and shall repair any damage caused by
the installation of such enclosure.
5. The Contractor shall remain responsible for insuring that his work,
material, equipment, supplies, tools, machinery, and construction
equipment is adequately protected from damage or theft and shall
provide, maintain and remove such additional temporary enclosures as
may be deemed necessary.
The foregoing obligations of the Contractor are in addition to his obligations under Article
10 of the General Conditions.
End of Section 01520
CONSTRUCTION AIDS 01520-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
%'')7763%(7%2(4%6/-2+%6)%7
A. The Contractor shall be responsible for installing and maintaining, until the
completion of his Work any temporary access roads or parking facilities required
by his Work, other than that which has been provided or required by the Owner.
The Contractor shall remove temporary access roads and parking facilities and
restore the areas to original or required grades.
B. Any Contractor excavating across an access road or parking area shall back-fill
and compact his excavation and resurface the road or parking area to match the
existing surface. The Contractor shall comply with all applicable Specifications
when so doing.
End of Section 01550
ACCESS ROADS AND PARKING AREAS 01550-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
8)1436%6='3286307
PART 1 - GENERAL
1.1 SUMMARY OF WORK BY THE CONTRACTOR
A. Section Includes:
1. Water control.
2. Dust control.
3. Erosion and sediment control.
4. Pollution control.
B. Related sections:
1. SCOPES OF WORK
1.2 WATER CONTROL
A. Contractor shall grade site to drain.
B. Protect site from puddling or running water. Provide water barriers to protect site
from soil erosion. Maintain excavations free of water. Provide, operate, and
maintain pumping equipment.
1.3 DUST CONTROL
A. Execute the Work by methods to minimize raising dust from construction
operations.
B. Provide positive means to prevent airborne dust from dispersing into
atmosphere.
1.4 EROSION AND SEDIMENT CONTROL
A. Plan and execute construction by methods to control surface drainage from cuts
and fills, from borrow and waste disposal areas. Prevent erosion and
sedimentation.
B. Minimize amount of bare soil exposed at one time.
C. Provide temporary measures such as berms, dikes, and drains, to prevent water
flow.
D. Construct fill and waste areas by selective placement to avoid erosive surface
silts or clays.
E. Inspect earthwork to detect evidence of erosion and sedimentation; promptly
apply corrective measures.
1.5 POLLUTION CONTROL
TEMPORARY CONTROLS 01560-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A. Provide methods, means, and facilities to prevent contamination of soil, water,
and atmosphere from discharge of noxious, toxic substances, and pollutants
produced by construction operations.
End of Section 01560
TEMPORARY CONTROLS 01560-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
*-)0(3**-')7%2(7,)(7
A. The Contractor shall furnish, install, and maintain a temporary field office if
required by Project Management for his use, the use of his employees, and the
use of Project Management during the construction period. The location of the
Field Office shall be determined by Project Management.
B. The Contractor shall furnish, install, and maintain temporary storage and work
sheds to adequately protect his work, materials, equipment, supplies, tools,
machinery, and construction equipment from damage and theft.
C. The Contractor shall arrange his field office and sheds so as not to interfere with
the construction. The locations of field offices and sheds shall be coordinated
with Project Management. The type, size and location of field offices and sheds
are subject to approval by Project Management.
D. The Contractor shall arrange and pay for temporary electricity and telephone
service for his field office and sheds, if he should require such services.
E. The Contractor shall relocate his field office and sheds as directed by Project
Management, at no additional cost to the Owner.
F. The Contractor shall remove his field office and sheds on completion of the Work
or when directed by Project Management. The Contractor shall remove all debris
and rubbish and shall leave the area in a clean and orderly condition.
End of Section 01590
FIELD OFFICES AND SHEDS 01590-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
'327869'8-32'0)%2-2+
PART 1 - GENERAL
1.1 SUMMARY OF WORK PERFORMED BY THE CONTRACTOR
A. Section includes:
1. Cleaning during progress of work.
1.2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with codes, ordinances,
regulations, and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on Project Site.
2. Do not dispose of volatile wastes such as mineral spirits, oil or paint
thinner in storm or sanitary drains.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Use only those cleaning materials which will not create hazards to health or
property and which will not damage surfaces.
B. Use only those cleaning materials and methods recommended by manufacturer
of the surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by cleaning material
manufacturer.
D. Sweeping compounds used in cleaning operations shall leave no residue on
concrete floor surfaces that may affect installation of finish flooring materials.
PART 3 - EXECUTION
3.1 DURING CONSTRUCTION
A. Execute cleaning to keep the Work, the Site and adjacent properties free from
accumulations of waste materials, rubbish and windblown debris, resulting from
construction operations.
B. Provide on-site containers for the collection of waste materials, debris, and
rubbish.
C. Dispose of waste materials, debris and rubbish off site at a state permitted
disposal site.
CONSTRUCTION CLEANING 01595-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
D. Trash containers shall be provided by Contractor and located in trash
accumulation areas designated by Project Management. Contractor each day
shall collect and deposit in the containers, all rubbish, waste materials, debris,
and other trash from his operations, including any trash generated by his
employees during lunch periods or coffee breaks. Shipping dunnage is also to
be removed by the contractor. Paper, boxes and bulk packaging shall be folded
or cut into reasonable sizes and shapes as appropriate and confined to prevent
loss of trash due to wind relocation. Full trash containers shall be disposed and
replaced as necessary to maintain above requirements and/or as directed by
Project Management.
End of Section 01595
CONSTRUCTION CLEANING 01595-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
1%8)6-%0%2()59-41)28
PART 1 - GENERAL
1.1 SUMMARY OF WORK PERFORMED BY THE CONTRACTOR
A. Section includes:
1. Products.
2. Transportation and handling.
3. Storage and protection.
4. Security.
1.2 PRODUCTS
A. Products: means new material, machinery, components, equipment, fixtures,
and systems forming the Work. Products do not include machinery and
equipment used for preparation, fabrication, conveying and erection of the Work.
Products may also include existing materials or components required for reuse.
B. Do not use materials and equipment removed from existing premises, except as
specifically permitted by the Contract Documents.
C. Provide interchangeable components of the same manufacturer, for similar
components.
1.3 TRANSPORTATION AND HANDLING
A. The Contractor shall be responsible for the transportation of all materials and
equipment furnished under this contract. Unless otherwise noted, the Contractor
shall also be responsible for loading, receiving and off-loading at the site all
material and equipment installed under this Contract, whether furnished by the
Contractor or the Owner. The Contractor shall be responsible for coordinating
the installation within the buildings of equipment that is too large to pass through
finished openings.
B. Transport and handle products in accordance with manufacturer's instructions.
C. Promptly inspect shipments to assure that products comply with requirements,
quantities are correct, and products are undamaged.
D. Provide equipment and personnel to handle products by methods to prevent
soiling, disfigurement, or damage.
1.4 STORAGE AND PROTECTION
The Contractor shall be responsible for the proper storage of all materials,
supplies, and equipment to be installed under this Contract. Materials stored on
site but not adequately protected will not be included in estimates for payment.
Except for materials stored within designated and approved storage sheds, vans,
or trailers, the Contractor shall not bring onto nor store in any manner at the site
MATERIALS AND EQUIPMENT 01600-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
any materials and equipment which will not be incorporated into the permanent
Work within seven (7) days from the delivery date. The Contractor shall be
responsible for arranging and paying for the use of property off the site for
storage of materials and equipment as may be required.
1.5 SECURITY
A. The Contractor shall be totally responsible for the security of his work, materials,
equipment, supplies, tools, machinery, and construction equipment.
End of Section 01600
MATERIALS AND EQUIPMENT 01600-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
4378'3286%'879&78-898-327
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Post-proposal substitutions.
1.2 SUBSTITUTIONS
A. Base Proposal shall be in accordance with the Contract Documents.
B. After the end of the proposal period, substitution requests, from the successful
Proposer, will be considered only in the case of:
1. Product unavailability.
2. Other conditions beyond the control of the Contractor.
C. Submit a separate request for each substitution. Support each request with the
following information:
1. Complete data substantiating compliance of proposed substitution with
requirements stated in Contract Documents:
a. Product identification, including manufacturer's name and
address.
b. Manufacturer's literature, identifying:
1) Product description.
2) Reference standards.
3) Performance and test data.
c. Samples, as applicable.
d. Name and address of similar projects on which product has been
used and date of each installation.
2. Itemized comparison of the proposed substitution with product specified,
listing significant variations.
3. Data relating to changes in construction schedule.
4. Effects of substitution on separate contracts.
5. List of changes required in other work or products.
6. Accurate cost data comparing proposed substitution with product
specified.
a. Amount of net change to Contract Sum.
7. Designation of required license fees or royalties.
8. Designation of availability of maintenance services, sources of
replacement materials.
D. Substitutions will not be considered for acceptance when:
1. A substitution is indicated or implied on shop drawings or product data
submittals without a formal request from Proposer.
2. Acceptance will require substantial revision of Contract Documents.
POST CONTRACT SUBSTITUTIONS 01630-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
3. In judgment of Project Management the substitution request does not
include adequate information necessary for a complete evaluation.
4. Requested directly by a subcontractor or supplier.
E. Do not order or install substitute products without written acceptance of Project
Management.
F. Project Management will determine acceptability of proposed substitutions.
G. No verbal or written approvals other than by Change Order will be valid.
1.3 CONTRACTOR'S REPRESENTATION
A. In making formal request for substitution the Contractor represents that:
1. The proposed product has been investigated and it has been determined
that it is equivalent to or superior in all respects to the product specified.
2. The same warranties or bonds will be provided for the substitute product
as for the product specified.
3. Coordination and installation of the accepted substitution into the Work
will be accomplished and changes as may be required for the Work to be
complete will be accomplished.
4. Claims for additional costs caused by substitution which may
subsequently become apparent will be waived by the Contractor.
5. Complete cost data is attached and includes related costs under the
Contract, but not:
a. Costs under separate contracts.
b. Project Management's costs for redesign or revision of Contract
Documents.
1.4 POST-PROPOSAL SUBSTITUTION FORM
A. The form is attached to this section.
B. Substitutions will be considered only when the attached form is completed and
included with the submittal with back-up data.
POST CONTRACT SUBSTITUTIONS 01630-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
POST-PROPOSAL SUBSTITUTION FORM
TO: Project Management
We hereby submit for your consideration the following product instead of the specified item for
the above project:
DRAWING NO: DRAWING NAME:
SPEC. SEC. SPEC. NAME PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Attach complete information on changes to Drawings and/or Specifications which proposed
substitution will require for its proper installation.
Submit with request necessary samples and substantiating data to prove equal quality and
performance to that which is specified. Clearly mark manufacturer's literature to indicate
equality in performance.
The undersigned certifies that the function, appearance and quality are of equal performance
and assumes liability for equal performance, equal design and compatibility with adjacent
materials.
Submitted By:
Signature Title
Firm
Address
Telephone Date
Signature shall be by person having authority to legally bind his firm to the above terms. Failure
to provide legally binding signature will result in retraction of approval.
*SVYWIF]XLI%VGLMXIGX*SVYWIF]XLI3[RIV4VSN1KQX
: :
Recommended Recommended as noted Approved
Not Recommended Received too late Not Approved
Insufficient data received Approved as noted
By: By:
Date: Date:
POST CONTRACT SUBSTITUTIONS 01630-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
Fill in Blanks Below:
A. Does the substitution affect dimensions shown on Drawings?
Yes No If yes, clearly indicate changes:
B. Will the undersigned pay for changes to the building design, including engineering and
detailing costs caused by the requested substitution?
Yes No If no, fully explain:
C. What effect does substitution have on other Contracts or other trades?
D. What effect does substitution have on construction schedule?
E. Manufacturer's warranties of the proposed and specified items are:
Same Different. Explain:
F. Reason for Request:
G. Itemized comparison of specified item(s) with the proposed substitution; list significant
variations:
H. This substitution will amount to a credit or extra cost to the Owner of:
dollars ($ ).
I. Designation of maintenance services and sources:
(Attach additional sheets if required.)
End of Section 01630
POST CONTRACT SUBSTITUTIONS 01630-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463(9'8,%2(0-2+
PART I--GENERAL
1.1 DESCRIPTION: THE CONTRACTOR SHALL BE RESPONSIBLE FOR
A. Work included. Protect products scheduled for use in the Work by means
including, but not necessarily limited to, those described in this Section.
B. Related work:
1. Documents affecting work of this Section include, but are not
necessarily limited to, General Conditions, Supplementary
Conditions, and Sections in Division of these Technical Special
Provisions.
2. Additional procedures also may be prescribed in other Sections of
these Technical Special Provisions.
1.2 QUALITY ASSURANCE
A. Include within the Contractor's quality assurance program such
procedures as are required to assure full protection of work and materials.
1.3 MANUFACTURERS' RECOMMENDATIONS
A. Except as otherwise approved by Project Management, determine and
comply with manufacturers' recommendations on product handling,
storage, and protection.
1.4 PACKAGING
A. Deliver products to the job site in their manufacturer's original container,
with labels intact and legible.
1. Maintain packaged materials with seals unbroken and labels intact
until time of use.
2. Promptly remove damaged material and unsuitable items from the
job site, and promptly replace with material meeting the specified
requirements, at no additional cost to the Owner.
B. Project Management may reject as non-complying such material and
products that do not bear identification satisfactory to Project
Management as to manufacturer, grade, quality, and other pertinent
information.
1.5 PROTECTION
A. Protect finished surfaces through which equipment and materials are
handled.
PRODUCT HANDLING 01640-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. Provide protection for finished floor surfaces in traffic area prior to
allowing equipment or materials to be moved over such surfaces.
C. Maintain finished surfaces clean, unmarred, and suitably protected until
accepted by the Owner.
1.6 REPAIRS AND REPLACEMENTS
A. In event of damage, promptly make replacements and repairs to the
approval of Project Management and at no additional cost to the Owner.
B. Additional time required to secure replacements and to make repairs will
not be considered by Project Management to justify an extension in
Contract Time of Completion.
End of Section 01640
PRODUCT HANDLING 01640-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
'3286%'8'037)398
PART 1 GENERAL
1.1 PROJECT TERMINATION
A. The Contract requirements are met when construction activities have
successfully produced, in this order, these three terminal activities:
1. Substantial Completion.
2. Final Completion.
3. Final Payment.
1.2 NOTICE OF SUBSTANTIAL COMPLETION
A. Contractor shall submit to Project Management when work is substantially
complete:
1. A written notice that the Work, or designated portion thereof, is
substantially complete.
2. Request Substantial Completion Observation at a mutually
agreeable date.
3. Certifications of systems and testing/balancing final reports.
4. Submit evidence of compliance with requirements of governing
authorities:
a. Certificate of Occupancy (or Completion)
b. Certificates of Inspection as applicable:
1) Electrical systems if required by Code
B. Within a reasonable time after receipt of such notice, the Owner and the
Contractor will make an observation to determine the status of
completion.
C. Should the Owner determine that the work is not substantially complete,
the following will occur:
1. The Owner will promptly notify the Contractor in writing, giving the
reasons.
2. The Contractor shall remedy the deficiencies in the Work, and
send a second written notice of substantial completion to the
Owner.
3. The Owner will re-observe the Work.
D. When the Owner concurs that the Work is substantially complete, the
following will occur:
1. Project Management will prepare a Certificate of Substantial
Completion accompanied by the Punch List of items to be
completed or corrected, as verified and amended by Project
Management. Contract responsibilities are not altered by
inclusion or omission of required Work from the punch list.
CONTRACT CLOSEOUT 01700-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
2. The Owner will submit the certificate to the contractor for written
acceptance of the responsibilities assigned to them in the
certificate.
E. Contractor shall complete or correct items identified on the punch list and
required by the Contract requirements within time limit established by the
certificate.
1.3 FINAL COMPLETION
A. To attain final completion, the Contractor shall complete activities
pertaining to substantial completion, complete Work on punch list items
and submit written request to the Owner for final inspection within thirty
(30) calendar days of date of substantial completion.
B. When the Work is complete, the Contractor shall submit written
certification that:
1. The Contract Documents have been reviewed.
2. Work has been inspected for compliance with the Contract
Documents.
3. Work has been completed in accordance with the Contract
Documents.
4. Equipment and systems have been tested in the presence of the
Owner's representative and are operational.
5. Work is completed and ready for final observation.
C. The Owner and the Contractor will make an inspection to verify the status
of completion with reasonable promptness after receipt of such
certification.
D. Should the Owner consider that the Work is incomplete or defective:
1. The Owner will promptly notify the Contractor in writing, listing the
incomplete or defective work.
2. The Contractor shall take immediate steps to remedy the stated
deficiencies and send a second written certification to the Owner
that the Work is complete.
3. The Owner will re-inspect the Work.
E. When the Work is acceptable under the Contract Documents as
determined by the Owner, the Owner will request the Contractor to make
close-out submittals. Warranties & Guarantees for everything will begin
at Substantial Completion.
1.4 THE CONTRACTOR'S CLOSEOUT SUBMITTALS TO THE OWNER
Contractor shall provide two (2) hard copies in tabulated divided binders and one
(1) saved electronically tabbed and indexed in Adobe Acrobat file (.PDF) format
delivered on a downloadable CD/DVD of the all the following but not limited to:
A. Project Record Documents (As Built Documents).
CONTRACT CLOSEOUT 01700-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. Operating and maintenance data, instructions to the Owner's personnel.
C. Warranties, bond and guarantees.
D. Keys and keying schedule.
E. Spare parts and maintenance materials.
F. Electronic copies of approved submittals
G. Evidence of payment and final release of liens and consent of surety to
final release (includes final release from all utilities and utility companies).
1.5 FINAL ADJUSTMENT OF ACCOUNTS
A. Submit a final statement of accounting to the Owner.
B. Statement shall reflect adjustments to the Contract Sum:
1. The original Contract Sum
2. Additions and deductions resulting from:
a. Previous Change Orders
b. Allowances
c. Deductions for uncorrected Work
d. Deductions for Liquidated Damages
e. Deductions for Re-inspection Payments
f. Other Adjustments
C. The Owner will prepare a final Change Order, reflecting adjustments to
the Contract Sum which were not previously made by Change Orders.
1.6 FINAL APPLICATION FOR PAYMENT
A. The Contractor shall submit the final Application for Payment in
accordance with procedures and requirements stated in the Conditions of
the Contract.
End of Section 01700
CONTRACT CLOSEOUT 01700-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
*-2%0'0)%2-2+
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1.
1.2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with codes,
ordinances, regulations, and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on the Project
Site.
2. Do not dispose of volatile wastes such as mineral spirits, oil or
paint thinner in storm or sanitary drains.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Use only those cleaning materials which will not create hazards to health
or property and which will not damage surfaces.
B. Use only those cleaning materials and methods recommended by
manufacturer on the surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by cleaning
material manufacturer.
PART 3 - EXECUTION
3.1 DUST CONTROL
A. Handle materials in a controlled manner with as little handling as
possible.
3.2 FINAL CLEANING
A. Employ skilled workmen for final cleaning.
B. Remove grease, mastic, adhesives, dust, dirt, stains, fingerprints, labels,
and other foreign materials from sight-exposed interior and exterior
surfaces.
C. Polish glossy surfaces to a clear shine.
D. Broom clean exterior paved surfaces; rake clean other surfaces of the
grounds.
FINAL CLEANING 01710-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
E. Prior to final completion, or the Owner occupancy, conduct an inspection
of sight-exposed interior surfaces, exterior surfaces and work areas, to
verify that the entire Work is clean.
F. Clean tunnels and closed off spaces of packing boxes, wood frame
members and other waste materials used in the Construction.
G. Remove temporary labels and stickers from fixtures and equipment. Do
not remove permanent name plates, equipment model numbers and
ratings.
H. Remove from the Site all items installed or used for temporary purposes
during construction.
I. Restore all adjoining areas to their original or specified condition.
End of Section 01710
FINAL CLEANING 01710-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
463.)'86)'36((3'91)287
PART 1 - GENERAL
1.1 SUMMARY
A. Contractor shall:
1. Maintain at the job site one copy of:
a. Record Contract Drawings.
b. Record Project Manual.
c. Coordination drawings.
d. Addenda.
e. Reviewed shop drawings.
f. Change Orders.
g. Other modifications to the Contract.
h. Field test records.
1.2 GENERAL
A. Store documents in cabinets in temporary field office, apart from
documents used for construction.
B. Maintain documents in clean, dry, legible condition.
C. Do not use Project Record Documents for construction purposes.
D. Make documents available for inspection by Project Management.
E. Failure to maintain documents up-to-date will be cause for withholding
payments.
F. Obtain from Project Management (at no charge) two sets of the Contract
Documents for Project Record Documents including:
1. Specifications with all addenda.
2. Two complete sets of black-line prints of all Drawings.
1.3 RECORDING
A. Label each document "Project Record".
B. Keep record documents current.
C. Do not permanently conceal any work until required information has been
recorded.
D. Contract Drawings:
PROJECT RECORD DOCUMENTS 01720-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1. Required information may, as an option, be entered on a "working
set" and then at completion of Project transfer the information to
final submitted "Project Record" set.
2. Legibly mark to record actual construction:
a. Depths of various elements of foundation in relation to
survey data.
b. Horizontal and vertical location of underground utilities and
appurtenances referenced to permanent surface
improvements.
c. Location of internal utilities and appurtenances concealed
in construction referenced to visible and accessible
features of structure.
d. Field changes of dimension and detail.
e. Changes made by Change Order or Construction Change
Directive.
f. Details not on original Contract Drawings.
E. Specifications and Addenda:
1. Legibly mark up each Section to record:
a. Manufacturer, trade name, catalog number and supplier of
each product and item of equipment actually installed.
b. Changes made by Change Order or Construction Change
Directive.
c. Other items not originally specified.
F. Conversion of schematic layouts:
1. Arrangement of conduits, circuits, piping, ducts and similar items
are in most cases shown schematically on the Drawings.
2. Legibly mark to record actual construction:
a. Dimensions accurate to within 1" on the centerline of items
shown schematically.
b. Identify each item, for example, "cast iron drain"
"galvanized water".
c. Identify location of each item, for example, "under slab", "in
ceiling plenum", "exposed".
3. Project Management may waive requirements of schematic layout
conversion, when in his opinion, it serves no beneficial purpose.
Do not, however, rely on waivers being issued except when
specifically issued by Project Management in writing.
1.4 SUBMITTAL
A. At completion of Project, deliver Project Record Documents to Project
Management and one (1) saved electronically tabbed and indexed copy
in Adobe Acrobat file (.PDF) format delivered on a downloadable CD/DVD
prior to request for final payment.
B. Accompany submittal with transmittal letter, in duplicate, containing:
1. Date
PROJECT RECORD DOCUMENTS 01720-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
2. Project title and Project number
3. The Contractor's name and address
4. Title and number of each record document
5. Certification that each document as submitted is complete and
accurate.
6. Signature of the Contractor, or his authorized representative.
End of Section 01720
PROJECT RECORD DOCUMENTS 01720-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
34)6%8-32%2(1%-28)2%2')(%8%
PART 1 - GENERAL
1.1 SUMMARY: THE CONTRACTOR SHALL PROVIDE OPERATION AND
MAINTENANCE DATA;
A. Section includes:
1. Format and content of manuals.
2. Schedule of submittals.
B. Related sections:
1. SECTION 01301 - SUBMITTALS
2. SECTION 01700 - CONTRACT CLOSEOUT
3. Individual Specifications Sections: specific requirements for
operation and maintenance data.
1.2 QUALITY ASSURANCE
A. Prepare instructions and data by personnel experienced in maintenance
and operation of described products.
1.3 FORMAT
A. Prepare data in the form of an instructional manual.
B. Binders: commercial quality, 8-1/2" x 11" three-ring binders with
hardback, cleanable, plastic covers; 1-1/2" maximum ring size. When
multiple binders are used, correlate data into related consistent
groupings.
C. Cover: identify each binder with typed or printed title OPERATION AND
MAINTENANCE INSTRUCTIONS; list title of the Project and separate
building; identify subject matter of contents.
D. Arrange content by systems under Section numbers and sequence of
Table of Contents of these Specifications.
E. Provide tabbed fly leaf for each separate product and system, with typed
description of product and major component parts of equipment.
F. Text: manufacturer's printed data, or typewritten data on 20 pound paper.
G. Drawings: provide with reinforced punched binder tab. Bind in with text;
fold larger drawings to size of text pages.
H. Provide one (1) indexed digital electronic copy of all Operation
Maintenance Data on CD
1.4 CONTENTS, EACH VOLUME
OPERATION MAINTENANCE DATA 01730-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
A. Table of Contents: provide title of the Project; names, addresses, and
telephone numbers of Project Management, consultants, and the
Contractor with name of responsible parties; schedule of products and
systems, indexed to content of the volume.
B. For each product or system: list names, addresses and telephone
numbers of subcontractors and suppliers, including local source of
supplies and replacement parts.
C. Product data: mark each sheet to clearly identify specific products and
component parts, and data applicable to installation. Delete inapplicable
information.
D. Drawings: supplement product data to illustrate relations of component
parts of equipment and systems, to indicate control and flow diagrams.
Do not use the Project Record Documents as maintenance drawings.
E. Type text: as required to supplement product data. Provide logical
sequence of instructions for each procedure, incorporating manufacturer's
instructions.
F. Warranties and bonds: bind in copy of each.
1.5 MANUAL FOR MATERIALS AND FINISHES
A. Building products, applied materials, and finishes: include product data,
with catalog number, size, composition, and color and texture
designations. Provide information for re-ordering custom manufactured
products.
B. Instructions for care and maintenance; include manufacturer's
recommendations for cleaning agents and methods, precautions against
detrimental agents and methods, and recommended schedule for
cleaning and maintenance.
C. Moisture protection and weather exposed products: include product data
listing applicable reference standards, chemical composition, and details
of installation. Provide recommendations for inspections, maintenance,
and repair.
D. Additional requirements; as specified in individual product specification
Sections.
1.6 MANUAL FOR EQUIPMENT AND SYSTEMS
A. Each item of equipment and each system: include description of unit or
system, and component parts. Identify function, normal operating
characteristics, and limiting conditions. Include performance curves, with
engineering data and tests, and complete nomenclature and commercial
number of replaceable parts.
OPERATION MAINTENANCE DATA 01730-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
B. Maintenance requirements: include routine procedures and guide for
trouble-shooting; disassembly, repair, and re-assembly instructions; and
alignment, adjusting, balancing, and checking instructions.
C. Provide servicing and lubrication schedule, and list of lubricants required.
D. Include manufacturer's printed operation and maintenance instructions.
E. Provide original manufacturer's parts list, illustrations, assembly drawings,
and diagrams required for maintenance.
F. Provide the Contractor's coordination drawings.
G. Provide list of original manufacturer's spare parts, current prices, and
recommended quantities to be maintained in storage.
H. Include test reports.
I. Additional requirements: as specified in individual product specification
Sections.
J. Provide a listing in Table of Contents for design data, with tabbed fly
sheet and space for insertion of data.
1.7 SUBMITTALS
A. Submit two copies of operation and maintenance data for review by
Project Management prior to Final Inspection. One copy will be returned
with comments.
B. Submit the required number of copies per each Specification Section or
two (2) copies each if not specified of approved data in final form within
ten (10) days after Final Inspection.
C. For equipment or component parts of equipment put in service during
construction and operated by the Owner, submit operation and
maintenance data within ten days after acceptance.
D. Submit two copies of approved revised volumes of data in final form
within ten (10) days after final inspection.
End of Section 01730
OPERATION MAINTENANCE DATA 01730-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
7)'8-32
;%66%28-)7
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 1 Specification Sections,
apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for the
Contractior for warranties required by the Contract Documents, including
manufacturers standard warranties on products and special warranties.
1. Refer to the General Conditions for terms of the Contractor's
period for correction of the Work.
B. Related Sections: The following Sections contain requirements that
relate to this Section:
1. Division 1 Section "Submittals" specifies procedures for submitting
warranties.
2. Division 1 Section "Contract Closeout" specifies contract closeout
procedures.
3. Certifications and other commitments and agreements for
continuing services to Owner are specified elsewhere in the
Contract Documents.
C. Disclaimers and Limitations: Manufacturer's disclaimers and limitations
on product warranties do not relieve the Contractor or the warranty on the
Work that incorporates the products. Manufacturer's disclaimers and
limitations on product warranties do not relieve suppliers, manufacturers,
and subcontractors required to countersign special warranties with the
Contractor.
D. Separate Prime Contracts: Each prime contractor is responsible for
warranties related to its own contract.
1.3 DEFINITIONS
A. Standard products warranties are preprinted written warranties published
by individual manufacturer's for particular products and are specifically
endorsed by the manufacturer to the Owner.
B. Special warranties are written warranties required by or incorporated in
the Contract Documents, either to extend limits provided by standard
warranties or to provide greater rights for the Owner.
WARRANTIES 01740-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
1.4 WARRANTY REQUIREMENTS
A. Related Damages and Losses: When correcting failed or damaged
warranted construction, remove and replace construction that has been
damaged as a result of such failure or must be removed and replaced to
provide access for correction of warranted construction.
B. Reinstatement of Warranty: When Work covered by a warranty has failed
and been corrected by replacement or rebuilding, reinstate the warranty
by written endorsement. The reinstated warranty shall be equal to the
original warranty with an equitable adjustment for depreciation.
C. Replacement Cost: Upon determination that Work covered by a warranty
has failed, replace or rebuild the Work to an acceptable condition
complying with requirements of the Contract Documents. The Contractor
is responsible for the cost of replacing or rebuilding defective Work
regardless of whether the Owner has benefited from use of the Work
through a portion of its anticipated useful service life.
D. Owner's Recourse: Expressed warranties made to the Owner are in
addition to implied warranties and shall not limit the duties, obligations,
rights, and remedies otherwise available under the law. Expressed
warranty periods shall not be interpreted as limitations on the time in
which the Owner can enforce such other duties, obligations, rights or
remedies.
E. Where the Contract Documents require a special warranty, or similar
commitment on the Work or part of the Work, the Owner reserves the
right to refuse to accept the Work, until the Contractor presents evidence
that entities required to countersign such commitments are willing to do
so.
1.5 SUBMITTALS
A. Submit written warranties to Project Management prior to the date
of Substantial Completion designates a commencement date for
warranties other than the date of Substantial Completion for the Work, or
a designated portion of the Work, submit written warranties upon request
of the Owner.
B. When the Contract Documents require the Contractor, or the Contractor
and a subcontractor, supplies manufacturer to execute a special
warranty, prepare a written document that contains appropriate terms and
identification, ready for execution by the required parties. Submit a draft
to the Owner, through Project Management, for approval prior to final
execution.
C. Form of Submittal: At Final Completion compile 2 copies of each required
warranty properly executed by the Contractor, or by the Contractor,
subcontractor, supplier, or manufacturer. Organize the warranty
WARRANTIES 01740-Page of
4EGOIX4K
'E
7XSGO-WPERH*MVI7XEXMSR,:%'6ITEMVW
documents into an orderly sequence based on the table of contents of the
Project Manual.
D. Bind warranties and bonds in heavy-duty, commercial-quality, durable 3-
ring, vinyl-covered loose-leaf binders, thickness as necessary to
accommodate contents, and sized to receive 8 ½ x 11" (115-by-280-mm)
paper and one (1) saved electronically tabbed and indexed copy in Adobe
Acrobat file (.PDF) format delivered on a downloadable CD/DVD.
1. Provide heavy paper dividers with celluloid covered tabs for each
separate warranty. Mark the tab to identify the product or installation.
Provide a typed description of the product or installation, including the
name of the product, and the name, address, and telephone number of
the Installer.
2. Identify each binder on the front and spine with the typed or printed title
"WARRANTIES", Project title or name, and name of the Contractor.
3. When warranted construction requires operation and maintenance
manuals, provide additional copies of each required warranty, as
necessary, for inclusion in each required manual.
END OF SECTION 01740
WARRANTIES 01740-Page of
4EGOIX4K