#2nd Change Order 01/12/2018 r Jacobs Key West International Airport 01/18 Monroe County Strengthen/Rehabilitate Commercial Apron Project No. GAKAP148 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 2 Strengthen/Rehabilitate Commercial Apron INITIA l'ED ON: January 2,2018 CONTRACT: GAKAP148 TO(Contractor):ABC Construction,Inc. 7215 NW 7th Street Miami,Florida 33126 CONTRACT DATE:November 22,2016 You are hereby authorized and directed to make the following change(s)in this Contract: Due to Hurricane Irma and unexpected high tides, the existing base material became saturated and unusable. The area existing base material will be excavated and replaced with flowable fill per the discretion of the OAR. A new unit price has been established for this additional work. The unit price of flowable fill is$404.41/CY. The original Contract Sum $ 9,250,000.00 Net change by previously approved Change Orders $ 37,733.30 The Contract Sum will be unchanged by this Change Order $ TBD The new Contract Sum including this Change Order will be $ 9,287,733.30 The Contract Time will be increased by N/A Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays,disruption,inefficiency,acceleration and all other claims. RECOMMENDED: AGREED TO: Jacobs Engineering ABC Construction,Inc. 01-o5-Z018 \ 1D l�'yAA.,,,if,,,,,,,,,- Date By ate AUTHORIZED: Key West International Airport Monroe County 349 uth Roose It Blvd. 1100 Simonton Street K We t,FL 0 0 Key W , 330 /_jJJ ) � �( pli I8 By Date y Dat MONROE COUNTY ATTORNEY'SS OFFICE pte1./IEDASpF02/J) PATRICIA EAMES ASSISTANT COUNTY A18'RNEY DATE: / — 3 " Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Base material had to be excavated and replaced with flowable fill due to Hurricane Irma and unexpected high tides which caused base material to become saturated and unusable. • Change Order was included in the original specifications. Yes ❑ No ❑ If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No • Explain: