2nd Change Order 02/23/2018MO NROE CO UN'T'Y /ENGINEERING / PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Sexton Cove Roadway and Drainage Project CHANGE ORDER NO: 2 TO CONTRACTOR: H&R Paving, Inc. The Contract is changed as follows: INITIATION DATE: 1/18/18 CONTRACT DATE: 1/9/17 The original Contract Sum ...................................... .............................. ..................$1,105,342.35 Net change by previously authorized Change Order # 1 .. ............................... .....................$43,262.80 The Contract Sum prior to this Change order was .......................... ............................... $1,148,605.15 The Contract Sum is (decreased) by this Final Reconciliation Change Order #2 ..................... $(46,064.35) The Final Contract Sum including this Change Order is . ............................... ..................$1,102,540.80 Pursuant to contract article 7.2.2, the cost or credit to the owner resulting from a change in the Work shall be determined in one or more of the following: 7.2.2.1 mutual acceptance of lump sum properly itemized and supported by sufficient substantiating data to permit evaluation 7.2.2.2 unit prices stated in the Contract Documents or subsequently agreed upon 7.2.2.3 cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee The under /overrun amounts to the contract bid amounts are as follows: Bid Item Description decrease Quantity Unit cost $ Amount 160-4 Type B Stabilization decrease (13314) $2.00 ($26,628.00) 570 -1 -2 Performance Turf Sod decrease (2792) N�EA $7.00 ($19,544.00) 706 -3 Retro Reflective Pavement decrease (1) $5.00 ( $5.00) 711 -11125 Thermo Std White Solid 24" increase 33.09 LF $5.00 $165.45 711 -16211 Thermo Std Yellow Solid 6° decrease (0.02) NM $5,280.00 ($105.60) 711 -16231 Thermo Std Yellow Skip 6" increase .04 GM $1,320.00 6 $52.80 Final Reconciliation Change Order 2 Net Contract Decrease Amount ($46,064:36) The date of Substantial Completion was July 29, 2017. Due to rework, Final Completion was not achieved until November 17, 2017. Total contract was 235 days. The CEI (RS &H) concurs with the contract revisions. Contractor agrees to accept the decrease in monetary compensation and hereby waives and releases any and all claims for any additional compensation related to these bid This Change Order is (4.19 %) of the original contract price. valid ENGINEERING SERVICES DIRECTO Z/ F-A " — ate ASSISTANT COUNTY ADMINISTRAT (/ it P� I ate C Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Final installed quantities of Type B stabilization and Sod and other items were lower than bid quantities. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes []No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: RSsll 3100 Overseas Highway Marathon Florida Monroe County Engineering Department January 18, 2018 Judith Clarke, P.E. 1100 Simonton Street Key West, FL 33040 Project: Sexton Cove Subject: Change Order #2 Overruns and Underruns The summary of contract dollar changes is shown below: Original contract amount ................................................ ............................... $1,105,342.35 Net change by previous authorized change orders # 1 .......... ............................... $43,262.80 The contract sum prior to this change order ................... ............................... $1,148,605.10 The contract sum will be decreased by this change order #2 ........................... ($46,064.35) The new contract sum including this change order ... ............................... $1,102,540.80 The contract time was increased 3 days due to change order 1, 41 days due to weather and 18 days due to holidays. The summary of contract time changes is shown below: Original contract ................ ............................... ............................173 days Contract time extension from change order 1 ..... ..............................3 days Weather.............................................................. .............................41 days Holidays............................................................. ............................. days Total Contract days ............ ............................... ............................235 days Below is a detailed description of change order #2 Overruns and Underruns; Pay Item 160 -4 Stabilization The existing stabilization was sampled and tested. The existing material had an average LBR of 136, minimum LBR required is 40. The material also met all minimum density requirements. The material was left in place at no pay. This resulted in an underrun of 13314 SY. Pay Item 570 -1 -2 Performance Turf Monroe County representative and the CEI jointly elected not to place sod in an area that would be affected by vehicle parking and in an area not disturbed by the construction. This resulted in an undemm 2792 SY. Pay Item 706 -3 Retro - Reflective Pavement Markers Based on certification of quantities from the contractor one less reflector was used. This resulted in an undemm of 1 EA. Pay Item 711 -11125 Thermoplastic Standard White Solid 24" Asphalt placement was extend on two Side Street to improve the tie in to exiting asphalt joints, this resulted in having to replace the two stops bars. This resulted in an overrun of 33.09 LF. Pay Item 711 -16211 Thermoplastic Standard Yellow Solid 6" Based on certification of quantities from the contractor one less reflector was used. This resulted in an underrun of .02 NM. Pay Item 711 -16213 Thermoplastic Standard Yellow Skip 6" There is a plan quantity error resulting in an overrun of .04 GM. Overruns and Underruns Under Pay Item Item Description /Over Unit Quantity Unit Price Bid Item Total 160 -4 Type B Stabilization Under SY -13314 2.00 $ (26,628.00) 570 -1 -2 Performance Turf, Sod Under SY -2792 7.00 $ (19,544.00) 706 -3 Retro- Reflective Pavement Markers Under EA. -1 5.00 $ (5.00) Thermoplastic, Standard, White, $ 711 -11125 Solid, 24" Over LF 33.09 5.00 $ 165.45 Thermoplastic, Standard, Yellow, 711 -16211 Solid, 6" Under NM -0.02 $ 5,280.00 $ (105.60) Thermoplastic, Standard, Yellow, 711 -16231 Skip, 6" Over GM 0.04 $ 1,320.00 $ 52.80 Total Overrun / Underrun Final Reconciliation $ (46,064.35) If you have any questions or need clarification of the above item summaries, please call Jackson Taylor at 561- 436 -2860. Sincerely, Digitally Signed by Jackson Jackson Tayloro e:7018.01.1911:1330 -0500' Jackson Taylor Project Administrator, RSH Cc: Judith Clarke, Debra London, Jacki Hart, P.E, File Page 2 of 2