3rd Change Order 03/06/2018MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
MCSO Fence Replacement
TO CONTRACTOR:
Florida Fence Corp
161 Georgia Ave
Tavernier FI 33070 -0227
INITIATION DATE: March 6, 2018
CHANGE ORDER NO: 3
CONTRACT DATE: July 19 2017
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)... ...... ... --$197,250.00 Ple
Net change by previously authorized Change Orders... o....,........,....,.......$ 0
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was .............$197,250.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order....., 10.00
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is,....,.$197,250.00
The Contract Time will be (increased) (decreased) (unchanged) b 82 days
The date of Substantial Completion as of the date, of this Change Order is ........................March 31, 2018
Detailed description of change order and justification:
Proiects delayed 82 days due to impacts caused by Hurricane Erma. Substantial Co m pletion has been
moved 82 calendar days from January 8. 2018 to March 31, 2018.
CONTRACTOR:
DIRECTOR PROJECT MANAGEMENT
COUNTY /ASSISTANT ADMINISTRATOR:
a
MIR
Gafy Knig Date
1tl
' Rom 4 n Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004 -1999
Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation;
Delay cause by impact of Cat 4 Hurricane and Subsequent closure of florida Keys for Recovery
Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
Change Order is correcting an error or omission in design document. Yes ❑No JZ
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
1. 161 Georgia Avenue, P.O. Box 227
Tavernier, FL 33070 -0227
Telephone: (305) 852 -4324
Date 02 -28 -18
Name MCBOCC
Attn:Johnny Young
Address MCSO
City, Stock Island , FL.
Re: Time Extension Fence Replacement Project
: Mr. Young
Florida Fence is requesting an extension to finish fence replacement project at the MCSO until March
31 of 2018.
Sincerely,
Ted Gordon, President
Florida Fence Corporation
P.O. Box 227
Tavernier, FL 33070 -0227
Office: (305) 852 -4324
Cellphone: (305) 393 -2290
Email: floridafence @aol.com