Loading...
1st Change Order 03/27/2018PROJECT TITLE: CHANGE ORDER NO: 1 Demolition of Old, and Installation of New Transfer Station Offices INITIATION DATE: February 22, 2018 TO CONTRACTOR: CONTRACT DATE: May 17, 2017 Pedro Falcon Contractors, Inc. 31160 Avenue C Big Pine Key F133043 -4516 The Contract is changed as follows: The original ( Contract Sur - n ) (Guaranteed Maximum Price). - ...$1,105,410.00 Net change by previously authorized Change Orders- .... 0.00 The ( Contract Sump (Guaranteed Maximum Price) prior to this Change order was - ...........$1,105,410.00 The (Contract Sum) (Guaranteed Maximum Price) will be (inoreasedl (decreased) unchan ed) by this Change Order ...,,.$ The new ( Contract Su m) _ Maximur Price) including this Change Order is, ...... 0,00 $1,105,410.00 The Contract Time will be increased} (decreased) (unchanged) by' ........ 150 days The date of Substantial Completion as of the date of this Change Order is .............. ....... April 26, 2018 Detailed description of change order and justification' Increase substantinI ccrrrr let on b 150 catendar days, from o e her 2 20 7 to A fll 26 201 due to hurricane #rrna dela�+°s Chan e order i 0 t of on ina! cor$tracC rice Not valid uIng it s. ned b Owner Architect if a licable or ARCHITECT: «` Pike Arlo Date CONTRACTOR:' P r alcon C a i rs, Inc. Date DIRECTOR PROJECT MANAGEMENT 1 1 n D to COUNTY /ASSISTANT ADMINISTRATOR: , c esl D to Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004 -1999 Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Hurricane Irma caused delays on completion of this project Change Order was included in the original specifications. Yes ❑ No ® ' If Yes, explanation of increase in price: e Change Order exceeds $50,000 or 5 of contract price (whichever is greater). Yes ❑ No ® " If Yes, explanation as to why it is not subject for a calling for bids: i e Project architect approves the change order. Yes ® No ❑ If no, explanation of why: Change Order is correcting an error or omission in design document. Yes ❑No ® ' Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Project: Deniolition and Installation of New'17ranst'er Offices Change Order Request No: PCO - 001 Description: No Cost Time Extegsion Itent L — Exten,d, Contract-Subsiantial CoUt letion fi-oln 2 7 Jvo vember 2017 to 26 At? 2018 Date to Hurricane Iraw Dely1w N et Amount of Request for Change Order:.............................. ..........................$0.00 Additional Time Requested for Change: 150 Calendar Days for Substantial Completion. Respectfully Submitted. Ken Bygler Project Manager a Industrial • Commercial - Institutional • Utility Established 1955