11th Change Order 04/02/2018MONROE COUNTYI NGINEERING/ P ROJECT MANAGE CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 11 HVAC System Improvements Stock Island Jail Complex INITIATION DATE: March 15, 2018 TO CONTRACTOR: Sea Tech of the Florida Keys, Inc 131 Palomino Horse Trail Big Pine Key, Florida 33043 The Contract is changed as follows: CONTRACT DATE: June 15, 2016 Contractors Change Order Request: 11 The original (Contract Sum) (Guaranteed Maximum Price) .............. ..................$1,538,612.00 Net change by previously authorized Change Orders ....... ............................... $ 42,983.14 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was..$1,581,595.14 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (Unchanged) by this Change Order.. $00.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order $1,581,595.14 The Contract Time will be (increased) (decreased) (unchanged) by .....................35 Days The date of Substantial Completion as of the date of this Change Order is April 20, 2018 Detailed description of change order and justification: Sea Tech to remove and replace the security bars at Air Handler Unit C -1 in the main detention Center. Substantial completion increase of 35 days from March 16, 2017 to April 20, 2018 This chap a Order is 0.0% of the on final contract price, ARCHITECT: CONTRACTOR: PROJECT MANAGEMENT: 16 ' - ./19 ate COUNTY /ASSISTANT ADMINISTRA t Date .Le'V� 2 APR 2(18 Date Change Order Attachment per Ordinance No. 004 -1999 I'ONROE COUNT' /ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 11 HVAC System Improvements Stock Island Jail Complex INITIATION DATE: March 15, 2018 TO CONTRACTOR: Sea Tech of the Florida Keys, Inc 131 Palomino Horse Trail Big Pine Key, Florida 33043 The Contract is changed as follows: CONTRACT DATE: June 15, 2016 Contractors Change Order Request: 11 The original (Contract Sum) (Guaranteed Maximum Price)......... ...... ..................$1,538,612.00 Net change by previously authorized Change Orders ....... ............................... $ 42,983.14 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was..$1,581,595.14 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (Unchanged) by this Change Order.. $00.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order $1,581,595.14 The Contract Time will be (increased) (decreased) (unchanged) by .....................35 Days The date of Substantial Completion as of the date of this Change Order is April 20, 2018 Detailed description of change order and justification: Sea Tech to remove and replace the security bars at Air Handler Unit C -1 in the main detention Center. Substantial completion increase of 35 days from March 16, 2017 to April 20, 2018 This chap a Order is 0.0° of the on inal contract price. ARCHITECT: CONTRACTOR: PROJECT MANAGEMENT: , .r ate COUNTY /ASSISTANT ADMINISTRA Date Date Change Order Attachment per Ordinance No. 004 -1999 Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Sea Tech to remove and replace the security bars at Air Handler Unit C -1 in the main detention Center. The deteriorated of the bars where discovered after Air Handlers intake plenum was removed. Substantial completion increase of 35 days front March 16, 2017 to April 20, 2018 Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: Change Order exceeds $50,000 or 5% of contract price (whichever is greater).Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: Project architect approves the change order. Yes ® No ❑ If no, explanation of why: Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Inc March 15, 2018 Attn: Dan Bensley Monroe County PWD 1100 Simonton St Key West, FL 33040 Re: MCSO HVAC Upgrades Subject: Time Extension Dear Mr. Bensley, Sea Tech is requesting a thirty -five (35) day no cost time extension to our contract. Change Order #10 to replace the security bars at AHU C -1 will not be complete until 6APR2018 due to fabrication lead times. Once this is complete we will be able to complete the commissioning and complete the test & balance. These delays will result in a substantial completion date of 20APR2018. Sea Tech has every intention of accelerating the work progress to reduce the time indicated on the project schedule. Please advise if you need additional information. I may be reached at (305) 872 -0888. Sincerely, Ryon LaChapelle Project Manager