Item E•
2
Cudjoe Status
December 2015
(Snapshot at December 7, 2015)
Finance Status
(Since AUG 2012)
FKAA
Advances to date
Expenditures to date
Advance Balance on hand
$139.2 million
$135.3 million
$ 3.9 million
CURRENT STATUS REPORT FOR CUD10E REGIONAL WASTEWATER PROGRAM
(As of December 4, 2015)
1. Inner Islands' Collection
Work continues on the master pump stations for Summerland
System
and Upper Sugarloaf Keys. Asphalt restoration being applied
on Summerland Key.
Action: FDEP approved Cudjoe Key collection/transmission
system for operation. System connections being installed
and inspected on Cudjoe Key.
2. Advanced Wastewater
Facility now in operation. FDEP has issued permit for deep
Treatment Facility
well. Latest aquifer testing shows no measurable impact from
shallow wells and aquifer performance is satisfactory for
anticipated effluent flow rates.
Action: Finish site work for mobilization of drilling
operation. Issue Notice to Proceed to contractor to drill deep
well upon executed contract documents.
3. Outer Islands' Collection
Layne has completed collection system piping on Lower
System
Sugarloaf, Ramrod and Little Torch. Collection system work on
Big Pine Key continues.
Action: Continue transmission work along US1, collection
system completions on Big Pine Key.
4. Public Information
FKAA held first of many workshops on October 29th regarding
wastewater system connections. FKAA sent reminder letters
for easements.
Action: Continue with public outreach, additional
connection workshops, website updates and field meetings.
5. On -Site Systems
County approved central system to be extended onto No Name
Key and Big/Middle Torch.
Action: Minimize number of onsite systems upon County
acceptance of adding properties to central system.
PROJECT STATUS REPORT
November 2015
Engineering/Roads/Project Management/Fac.dides/Fleet/Solid
ENGINEERING / ROADS
Card Sound Bridge Repair Project — Staff negotiating cost proposal for construction engineering and
inspection services (CEI) services with Parsons Brinkerhoff, the highest ranked respondent.
Construction project advertised for bids on October 28 h. Bids are due on December le -
Card Sound Toll Study — Staff and consultant finalized customer survey that will be handed out to
users of the toll for a week beginning on December 7`h and available online via a link on the county
website and to Ocean Reef residents and businesses through email dissemination.
Lake Surprise Estates Roadway and Drainage Improvement Project — Contractor working on utility
locates and submittals. FDOT approved contractor staging area on FDOT right of way. Nuisance
flooding data provided to Engineer of Record; staff requested cost proposal to revise design to
incorporate minimum elevation adaptation for additional sea level rise into project.
Roadway and Drainage Improvement Program — Staff finalized RFQ for Stock Island II
(Maloney/McDonald Avenue) Roadway Improvement Pro�ect Engineering Design and Permitting services;
RFQ will be advertised with a response date of January 14 .
Key Largo I Roadway and Drainage Improvement Project- Staff met with design consultant onsite on
November 4d; Staff reviewing geotechnical and environmental reports. Awaiting survey information to
determine whether road elevations need to be increased to allow for sea level rise.
No Name Key Bridge Repair Project — Contractor to finish remaining two pile jacket installations by the
end of December. Metallizing of remaining nine bent caps to be completed by 2nd week of January.
Punch list items are ongoing. FDOT final Construction Audit is scheduled for the middle of January.
Pigeon Key Ramp Repair Project — Consultant provided results of preliminary assessments
including foundation survey notes, structural inspection notes, and 3D survey plans and reviewed
with staff on conference call on November 23`d. Preliminary design/conceptual report due on
December 11 d'.
Sexton Cove Roadway and Drainage Improvement Project — Project design complete; construction
delayed until May 2016 to allow FKAA to upgrade water lines in subdivision prior to county road work.
Staff reviewing final elevations to confirm roads will be at minimum desirable elevation to account for
sea level rise.
Stock Island Roadway and Drainage Improvement Project — Engineering of Record working on
incorporating comments on 60% plans for 90% plan submittal in late December, 2015. Anticipate
scheduling public information meeting in January, 2016.
US 1 Bayside Pedestrian Bridge — Contracts for CEI and construction on December BOCC agenda for
approval.
US 1 Bayside Trail — Awaiting contractor submittal of final pay application to close out project.
Awaiting results of Florida Highway Beautification Program Landscaping grant application ranking on
November 19, 2015.
PROJECT STATUS REPORT
November 2015
Engineering/Roads/Project Management/Facilities/Fleet/Solid
9th Avenue Stock Island Drainage Project — Project complete. Engineer of Record creating digital
record drawings from as built.
Grouper Lane (Key Largo) Drainage Project — Project is 50% complete. Revised drawings received
from Engineer of Record (EOR) to raise road by approximately an additional 6" to address recent high
levels of nuisance flooding.
Duck Key Security District Cameras — Contract with TYCO Integrated Security is on the December 9`''
BOCC agenda for approval.
Garrison Bight Bridge Repair Project — Staff is in process of negotiating cost proposal with
Kisinger Campo & Associates for Design Services
Sugarloaf Boulevard Bridge Replacement Project — Design project kick off meeting scheduled
with consultant on December 16`h; preliminary utility coordination meeting scheduled for
December 17'h.
Old Seven Mile Bridge Repair Project — staff coordinating with FDOT utility coordination
department to execute Joint Participation Agreement for FDOT contractor to remove abandoned
18" waterline belonging to Monroe County from the bridge during the rehabilitation project.
Anticipate JPA will be on January BOCC agenda for approval.
JOB B0ARD(FUNDEDJOBS 2015)
DESCRIPTION
CONSTRUCTION
NOTES
#
TASK
PM
ALT/PM
LOCATION
STATUS
BUDGET
FIRM
ACCOUNT
1
Big Pine Swim Hole
CR
DB
LOWER
Scoping meeting for park development
$ 2,000,000.00
Little John
2
MEN Sidewalks
CR
DB
UPPER
FOOT review
UKN
MC
3
MEN Marquee
CR
DB
UPPER
Waiting for direction
UKN
MC
4
Harry Harris Shed
CR
DB
UPPER
Engineer behind schedule
$ 25,000.00
Horn
5
Key Largo Park Residence
CR
DB
UPPER
Engineer behind schedule
$ 50,000.00
Horn
304-24000-560620-CG1505
6
Marathon Customs Fac
CR
DS
MIDDLE
Airport wide Fire suppression issues
$ 1,010,000.00
MBI
63 588-560620-GAM073/63597-560620-GAMD72
7
Rowells Marina
CR
DS
UPPER
RFQ issue in Nov/Dec
$ 130,000.00
TAD Grant encumbered 11/18/15
8
1 Murray Nelson Generator
CR
DS
UPPER
Bids 12/17
$ 25,000.00
Horn/CSA
304-24000-560630-CG1411
9
Marathon IT HVAC
CR
JY
JY
MIDDLE
UPPER
contract to BOCC in December
60% review complete
$ 7,500.00
$ 225,000.00
CSA
CSA
304-24000-560620-CG1514
304-23000-560630-PE1301
10
PKWWDecomm
CR
11
Roth WW Decomm
CR
JY
UPPER
60%review complete
$ 150,000.00
CSA
304-23000-560630-PE1301
12
Big Pine Park Vista
DB
CR
I LOWER
Permitting
$ 500,000.00
Stantec
13
Reynolds St. Vista
DB
CR
LOWER
60%desing due in December
$ 500,000.00
Stantec
14
BPK Docks
DB
CR
LOWER
Mangrove trimming
UKN
15
Senior Nutrition Center
DB
DS
LOWER
Negotiating with Hertz for sub lease
$ 660,000.00
Horn
102-22500-530310
16
Jefferson Brown Chillers
DB
DS
LOWER
ILA being drafted by legal/getting survey of lot
$ 158,000.00
TYLinn
17
Summeriand FS
DB
DS
LOWER
Phase 2 complete/no additional issues
$ 4,500,000.00
314-26008-560620-CP1501
18
PK Fuel Station Relocation
DB
DS
UPPER
Scheduling survey for road abandonment
$ 250,000.00
19
Ellis Renovations
DB
DS
UPPER
Bill Horn under contract for design
$ 250,000.00
20
Magnolia St. Public Works
DB
DS
UPPER
construction on schedule
$ 1,250,000.00
CSA
304-24000-560620-CG1416
21
Higgs Beach Sand Phase 1
DB
lY
LOWER
Design rejected by FDEP
$ 100,000.00
TYLinn
LAP
22
Higgs Beach Sand Phase 2
DB
JY
LOWER
Applying for TDC grant to cover
$ 1,500,000.00
TYLinn
LAP
23
Gato Ext Painting
DB
JY
LOWER
Contract Awarded/waiting for executed copy
$ 98,000.00
Bender
304-24000-560620-CG1510
24
Harvey Ext Painting
DB
JY
LOWER
Contract Awarded/waiting for executed copy
$ 180,000.00
Bender
25
PK Court House
DS
ALL
UPPER
Pre App submitted
$ 16,000,000.00
CSA
314-26008-560620-CP1503
26
Cotton Property
DS
I DB
I LOWER
Negotiating one year lease
$ 25,000.00
Horn
27
Sugarloaf Fire Dorm
DS
DB
LOWER
Community/Tower negotiations
$ 300,000.00
28
Fleet Wash Stations
JY
All
On hold for more scoping
$ 200,000.00
29
Bernstein Park
JY
CR
LOWER
Permitting and design revisions
$ 5,100,000.00
Horn
304-25000-560630-CC1403
30
MCDC & MCSO Lighting
lY
CR
LOWER
Under contract
$ 360,000.00
304-24000-560620-CG1515
31
MCSO Roof
lY
CR
LOWER
will RFP after Chiller replacement
$ 158,000.00
32
Ramp Repairs
JY
CR
LOWER
Permitting with USACOE
$ 180,000.00
Keith & Sc
157-62520-530340
33
Marathon Library
JY
CR
I MIDDLE
Contract Awarded/waiting for executed copy
$ 3,500,000.00
SRS
304-25000-560620-CC1401
34
Crawl Key Fire Training
lY
CR
MIDDLE
On schedule
$ 2,100,000.00
Horn
314-26008-560620-CP1502
35
Transfer Stations Office
JY
CR
MIDDLE
Design
$ 1,000,000.00
Pike
414-40000-560620
36
Med Examiners Chillers
JY
CR
MIDDLE
Permitting
$ 80,000.00
Contractor
37
Pigeon Key Fire Sprinklers
JY
DB
LOWER
No bidders/ rescoping project $ 185,000.00
1 Contractor
38
East Martello ADA upgrades
JY
DB
LOWER
PermittinoDC grant application
$ 300,000.00
MBI
Grant due Jan 2016
39
Atlantic St Relocation
JY
DB
LOWER
In redesign 60% due in January
$ 3,500,000.00
TYLinn
40
KW Light House
JY
DB
LOWER
Light House complete ahead of schedule
$ 635,000.00
Bender
117-77040-530340-TM57492X
41
Marathon Annex, Repairs
JY
DB
MIDDLE
In design $ 110,000.00
Horn
304-24000-560620-CG1509
42
Pidgeon Key Roof
JY
DB
MIDDLE
Applying for TDC grant to cover increase in costs
1 $ 65,000.00
119-79040-530340-TM59622X
$ 47,366,500.00
�On Schedule On budget
Slightly delayed Schedule or Budget Changes
Off Schedule Off Budget