4th Change Order 05/15/2018MONROE COUNTY /ENGINEERING / PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
M'CSO Fence Replacement
CHANGE ORDER NO: 4
INITIATION DATE: 05110118
TO CONTRACTOR:
Florida Fence Corp.
161 Georgia Avenue
Tavernier, FL 33070 -0227
The Contract is changed as follows:
CONTRACT DATE: July 19, 2017
The original (Contract Sum) (Guaranteed Maximum Price) ........................ ....................$197,250.00
Net change by previously authorized Change Orders ..................... ..............................$ 0.00
The &oCitract Sum (Guaranteed Maximum Price) prior to this Change order was .............$ 197,250.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged by this Change Order ....... $ 0.00
The new (Contact Sure (Guaranteed Maximum Price) including this Change Order is ...... t97 - , 0,00
The Contract Time will be incr esed) (decreased) (unchanged) by... ................ D ; ys
The date of Substantial Completion a of the elate cif this Change Order is ............... ......... Ai;� °it 20 2018
Detailed description of change order and justification:
Inn, ase date of sy 's cn ! leta.�gi..tm h yrs Errata tvtarc ' 3'I' ?t�IILtp �di�rt #..� A tyo
cattsecl b y the i of t lu rricgnt
Th is c h a n_q Order t 0% � rigfal contract iorice.
Not yallt until sIgned by OWner, Architect (if ap IlEAl2 � Contractor
CONTRACTOR:
DIRECTOR PROJECT MANAGEMi
COUNTY/ASSISTANT ADMINISTRA
Kevin Wilson t `i'!r
Christine Hurley
Me a I I ',•� •
PROJECT TITLE:
MCSO Fence Replacement
TO CONTRACTOR:
Florida Fence Corp.
161 Georgia Avenue
Tavernier, FL 33070 -0227
The Contract is changed as follows:
141 - EC 4ISM
INITIATION DATE: 05110118
CONTRACT DATE: July 19, 2017
The original (Contract Sum) (Guaranteed Maximum Price) ......................... ...................$197,250.00
Net change by previously authorized Change Orders ..................... ..............................$ 0.00
The Contract Sum (Guaranteed Maximum Price) prior to this Change order was .............$ 197,250.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged by this Change Order ......,$ 0.00
The new , (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ...,:� s0.00
The Contract Time will be (increased) (decreased) (unchanged) by ............................... ' I ys
The date of Substantial Completion as of the date of this Change Order is ......................`Aril 23 2018
Detailed description of change order and justification:
Increase e late of substantial cr�rmi )'Lb -y rla �s, from March d+,, 2018 to _A r l 2 due t gLola
caused b y the impact of Hurricane Irma_
Thi cha nge girder is 0% of the on ina contract price
...
CONTRACTOR:
DIRECTOR PROJECT MANAGEMENT
; Ted o en, FlorijFen 'or ate,
ary ight Iatc
COUNTY /ASSISTANT ADMINISTRATOR: ,
Roman Gastesi Date
Kevin Wilson
Christine Hurley
i
Change Order Attachment per Ordinance No. 004 -1999
Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
Additional delays due to Hurricane Irma.
Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ❑ No
If no, explanation of why: No architect on project.
Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
M ni -Ann
From: floridafence @aol.com
Sent: Thursday, May 10, 2018 3:09 PM
To: Mytnik -Ann
Subject: Additional time request
Attachments: Interim Affidavit.pdf, Certificate of Substantial Completion.pdf
Good Afternoon Ann,
It was nice to speak to you!I
As discussed, the project was delayed from March 31, 2018 to April 23rd, 2018 due to impacts caused by Hurricane Irma.
If you could be so kind as to prepare the Change order for us to sign, We would appreciate it.
And I believe we will need a consent of surety.
I have Attached the 2 documents that we had already mailed on /around April 28, 2018.
Thank you
Elizabeth Sassine
Florida Fence Corp
305 - 852 -4324