#5th Change Order 05/10/2018Jacobs Key West International Airport 04/18 Monroe County Strengthen/Rehabilitate Commercial Apron Project No. GAKAP148 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 5 Strengthen/Rehabilitate Commercial Apron INITIATED ON: April 23, 2018 CONTRACT: GAKAP148 TO (Contractor): ABC Construction, Inc. 7215 NW 7 Street Miami, Florida 33126 CONTRACT DATE: November 22, 2016 You are hereby authorized and directed to make the following change(s) in this Contract: Modify taxiway centerlines to accommodate B737 -70OW and EMB 175 access to newly striped parking positions. The original Contract Sum ............................... Net change by previously approved Change Orders........ The Contract Sum will be unchanged by this Change Order ...................... The new Contract Sum including this Change Order will ................ ............................... The Contract Time will be increased by ........................... $ 9,250,000.00 $ 37,733.30 $ 3.850.00 $ 9,291,583.30 N/A Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims. RECOMMENDED: Jacobs Engineering • 2 �I� y I Date Key West International Airport 3491 South Roosevelt Blvd. st, FL 0 Ke 0 S -q -lp N Y ' Date 1 Monroe County 1100 Simonton Street Key West 33040 5 o i� By baie ROE N PRO b O , I E ERG f-'.ec . 'e� D �BT/�l" 1' 606U TY ATTORidE1�s AUTHORIZED: Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ❑ No If Yes, explanation: • Change Order was included in the original specifications. Yes ® No ❑ If Yes, explanation of increase in price: Modify taxiway centerlines to .accommodate. B737- 700W and EMB 175 access to newly striped parking positions. • Change Order exceeds $25,000 or 5% of contract. price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Z. Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: ABC CONSTRUCTION, INC. 7215 NW 7th Street Phone: 305 - 663 -0322 NO. 0 MIAMI, FL. 33126 Fax: 305 -267 -2403 TITLE: Re- Stripe per Revised Design DATE: 03/07/2018 PROJECT: Keys Strengthen Rehabilitate Commercial Apron TO: Attn: Lasa (Adams) Ennis, P.E. Jacobs 200 West Forsyth Street Suite 1520 Jacksonville, Florida 32202 Phone: 904.636.5432 Fax:561.799.6579 PROPOSED CHANGE ORDER JOB: GAKAP145 CONTRACTlPO: GAKAP145 SUBMITTED: 03/07/2018 COMPLETED: REQUIRED: 03/28/2018 DESCRIPTION Restripe to include 9 hours of travel time from Miami to Key West and Back to Miami. 3 hours to complete the work on the site with 2 employees and the material theereof. ABC reserves its right to claim for addtional time and conpensation related to this change. Num Item Description Ref Qty Unit Unit Price Amount 1 Re -Stripe per Revised Design 1.000 Lump 3,500.00 3,500.00 2 ABC O/H Profit 1.000 Lump 350.00 350.00 Total: $3,850.00 By: Date: Date: u3 /07 /LU1 8